MCI CONSTRUCTORS, INC. v. Hazen and Sawyer, PC

310 F. Supp. 2d 754, 2004 U.S. Dist. LEXIS 4886, 2004 WL 615649
CourtDistrict Court, M.D. North Carolina
DecidedMarch 10, 2004
Docket1:99 CV 00002, 1:02 CV 00396
StatusPublished
Cited by1 cases

This text of 310 F. Supp. 2d 754 (MCI CONSTRUCTORS, INC. v. Hazen and Sawyer, PC) is published on Counsel Stack Legal Research, covering District Court, M.D. North Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
MCI CONSTRUCTORS, INC. v. Hazen and Sawyer, PC, 310 F. Supp. 2d 754, 2004 U.S. Dist. LEXIS 4886, 2004 WL 615649 (M.D.N.C. 2004).

Opinion

MEMORANDUM OPINION AND ORDER

OSTEEN, District Judge.

I. BACKGROUND

This matter is presently before the court on National Union’s and the City of Greensboro’s motions for summary judgment on the City of Greensboro’s claims against National Union. The general background of the case has been set forth in the court’s Memorandum Opinions, dated March 24, 2000, October 6, 2000, January 18, 2001, September 6, 2002, and November 1, 2002. The following facts are relevant to the motions at hand.

On January 16, 1996, the City of Greensboro (“the City”) entered into a contract with MCI Constructors, LLC (“MCI”) for construction of the T.Z. Osborne Wastewa-ter Treatment Plant in Greensboro, North Carolina (“the project”). Pursuant to the contract between MCI and the City, MCI was to secure a performance bond that was to remain “valid” for one year after the date the certificate of substantial completion was issued. Supplementary Conditions § 5.1.1. MCI subsequently arranged for National Union Fire Insurance Company of Pittsburgh, Pennsylvania (“National Union”), to provide the performance bond for the project. National Union’s contract to issue the bond incorporated by reference the terms of the underlying contract between MCI and the City. The work began soon after the underlying contract was signed. After various delays, the City gave notice of termination to MCI by a letter, dated June 17, 1998. By the terms of the letter, termination became effective seven days after this date. Notice of MCI’s termination was also sent the same day to National Union.

After MCI’s termination, contractors were hired to complete the work on the project. The City made a demand under the bond as a result of MCI’s termination, and, on May 5, 2000, joined National Union to the ongoing litigation between the City and MCI. The claims against National Union were later dismissed for lack of subject matter jurisdiction and procedural reasons. MCI Const., LLC v. Hazen and Sawyer, P.C., No. 1:99CV00002, slip op. at 10-11 (M.D.N.C. Oct. 6, 2000). Specifically, this court held that the disputes clause in the MCI-City contract, requiring submission of all questions regarding performance of the contract to the City Manager, operated *756 as a condition precedent to bringing suit on the contract. (Id. at 10.)

On May 31, 2001, a Certificate of Substantial Completion was issued following the additional work performed by the replacement contractors. On February 5, 2003, a hearing was held by the City Manager who, pursuant to the contractual authority of his position in resolving disputes, awarded damages in the amount of $13,377,842.73 to the City against MCI. The City once again made a demand under the bond by a letter, dated February 11, 2003. Having failed to receive the claimed amount, the City again joined National Union to this litigation on March 11, 2003. The City’s claims are now the subject of National Union’s and the City’s motions for summary judgment.

II. STANDARD OF REVIEW

Summary judgment is appropriate where an examination of the pleadings, affidavits and other proper discovery materials before the court demonstrates that there is no genuine issue of material fact, thus entitling the moving party to judgment as a matter of law. Fed.R.Civ.P. 56(c); Celotex Corp. v. Catrett, 477 U.S. 317, 322-23, 106 S.Ct. 2548, 2552, 91 L.Ed.2d 265 (1986). If the moving party has met that burden, the nonmoving party must then persuade the court that a genuine issue does remain for trial.

When the moving party has carried its burden under Rule 56(c), its opponent must do more than simply show that there is some metaphysical doubt as to the material facts. In the language of the Rule, the nonmoving party must come forward with “specific facts showing that there is a genuine issue for trial.”

Matsushita Elec. Indus. Co., Ltd. v. Zenith Radio Corp., 475 U.S. 574, 586-87, 106 S.Ct. 1348, 1356, 89 L.Ed.2d 538 (1986) (citations omitted) (quoting Fed.R.Civ.P. 56(e)). The court must view the facts in the light most favorable to the nonmovant, drawing inferences favorable to that party if such inferences are reasonable. Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 255, 106 S.Ct. 2505, 2513, 91 L.Ed.2d 202 (1986); Cole v. Cole, 633 F.2d 1083, 1092 (4th Cir.1980). However, there must be more than just a factual dispute; the fact in question must be material and the dispute must be genuine. Fed R. Civ. P. 56(c); Anderson, 477 U.S. at 248, 106 S.Ct. at 2510. A dispute is only “genuine” if “the evidence is such that a reasonable jury could return a verdict for the nonmov-ing party.” Anderson, 477 U.S. at 248, 106 S.Ct. at 2510.

III. ANALYSIS

A. National Union’s Motion for Summary Judgment

National Union has moved, pursuant to Rule 56 of the Federal Rules of Civil Procedure, for summary judgment on the following two claims asserted by the City: (1) breach of contract by National Union for failure to honor the City Manager’s February 5, 2003 Damages Award totaling $13,377,842.73; and, in the alternative, (2) breach of contract by National Union resulting in a loss exceeding $16,000,000, as may be proven at trial. Resolution of these claims requires, first, an examination of both the law of contract interpretation and then the applicability of statutes of limitation to activities carried on by municipalities. Specifically, National Union asserts that the contract contains a limitations period barring the City’s suit. Additionally, it contends that the suit is barred by the applicable statute of limitations.

1. Contract Interpretation

In North Carolina, “[i]f the plain language of a contract is clear, the inten *757 tion of the parties is inferred from the words of the contract.” Walton v. City of Raleigh, 342 N.C. 879, 881, 467 S.E.2d 410, 411 (1996). If a contract is clear and unambiguous, the meaning of the contract is a matter of law for the court. Atlantic & E. Carolina Ry. Co. v. Southern Outdoor Adver., Inc., 129 N.C.App. 612, 617, 501 S.E.2d 87, 90 (1998).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Beachcrete, Inc. v. Water Street Center Associates, L.L.C.
615 S.E.2d 719 (Court of Appeals of North Carolina, 2005)

Cite This Page — Counsel Stack

Bluebook (online)
310 F. Supp. 2d 754, 2004 U.S. Dist. LEXIS 4886, 2004 WL 615649, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mci-constructors-inc-v-hazen-and-sawyer-pc-ncmd-2004.