MCI Constructors, Inc. v. Hazen and Sawyer, PC

401 F. Supp. 2d 504, 2005 U.S. Dist. LEXIS 30536, 2005 WL 3157584
CourtDistrict Court, M.D. North Carolina
DecidedNovember 25, 2005
Docket1:99CV00002, 1:02CV00396
StatusPublished

This text of 401 F. Supp. 2d 504 (MCI Constructors, Inc. v. Hazen and Sawyer, PC) is published on Counsel Stack Legal Research, covering District Court, M.D. North Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
MCI Constructors, Inc. v. Hazen and Sawyer, PC, 401 F. Supp. 2d 504, 2005 U.S. Dist. LEXIS 30536, 2005 WL 3157584 (M.D.N.C. 2005).

Opinion

MEMORANDUM OPINION AND ORDER

OSTEEN, District Judge.

This matter is before the court on motions relating to claims by Plaintiff MCI Constructors, Inc. (“MCI”) against Defendant City of Greensboro (“the City”) and a counterclaim by the City against MCI. Both parties have moved for summary judgment on both the claim and counterclaim. For the reasons stated below, all motions will be denied.

I. BACKGROUND

The general background of the case has been set forth in the court’s memorandum opinions, dated March 24, 2000, October 6, 2000, January 18, 2001, September 6, 2001, and November 1, 2002. The following facts are relevant to the motions at hand.

In 1996, MCI and the City entered into a contract for the upgrade and expansion of the T.Z. Osborne Wastewater Treatment Plant (“the project”). The contract contained a provision allowing the City to terminate the contract if MCI failed to comply with the contract’s requirements; 1 *507 upon termination under this provision, MCI would become liable for the City’s costs to complete the project, to the extent that they exceeded the contract price. The contract also contained a provision, Article 16, dictating that certain disputes between the parties regarding the fulfillment of the contract would be submitted to the City Manager, who would be empowered to resolve them. 2

Construction of the wastewater treatment plant was divided into several phases. Phase II was scheduled to be completed by October 7, 1997, but was not completed by that date. In May 1998, the parties agreed to a revised schedule, with a new completion date set for September 15, 1998. In June 1998, the City concluded that MCI would not be able to comply with the new schedule and completion date and terminated MCI’s participation in the project. MCI was notified of the termination by a letter written by the City Manager, Ed Kitchen, dated June 17, 1998.

Thereafter, MCI filed suit alleging multiple violations of North Carolina law, including a claim of wrongful termination. The City filed a counterclaim seeking compensation for the cost of completing the plant after MCI was terminated. In an order dated October 6, 2000, the court invoked Article 16 of the contract and directed both parties to submit' their claims to the City Manager for resolution.

The City Manager held two hearings. The first was held for the purpose of determining whether the City had terminated MCI for cause or for convenience (the “cause hearing”); the second was for the purpose of determining damages (the “damages hearing”). The City Manager concluded that the termination had been for cause and that MCI was required under the contract to pay the City approximately $13.4 million in damages. 3

In a memorandum opinion issued between the cause hearing and the damages hearing, the court indicated to the parties that it would apply North Carolina law and consider the City Manager’s decision final as to all issues, “absent a showing of bad faith or a failure to exercise honest judgment.” (Sept. 6, 2002 Mem. Op. at 19). Following the issuance of the City Manager’s decision, MCI challenged it, alleging bad faith. Ultimately, the court concluded that MCI had not demonstrated a “legally sufficient evidentiary basis for a reasonable jury to find that the City Manager’s decision was influenced by fraud, bad faith, or gross mistake.” (Mar. 10, 2004 Judgment and Order ‘ at 2.) Accordingly, the court granted judgment as a matter of law in favor of the City on all of MCI’s claims *508 and ordered MCI to pay the City the amount awarded by the City Manager.

MCI appealed the judgment on the grounds that the court had applied the wrong standard in reviewing the City Manager’s decision. The Fourth Circuit agreed and overruled the March 10 judgment. The Fourth Circuit, in its opinion, indicated that the proper standard is “an objective standard of reasonableness based upon good faith and fair play.” MCI Constructors, Inc. v. City of Greensboro, No. 04-1395 (4th Cir. Apr. 8, 2005). The case was remanded to this court to be resolved through application of this standard.

II. STANDARD OF REVIEW

Summary judgment is appropriate when an examination of the pleadings, affidavits, and other proper discovery materials before the court demonstrates that there is no genuine issue of material fact, thus entitling the moving party to judgment as a matter of law. Fed.R.Civ.P. 56(c); Celo-tex Corp. v. Catrett, 477 U.S. 317, 322-23, 106 S.Ct. 2548, 2552, 91 L.Ed.2d 265 (1986). If the non-moving party is to prevail, there must be more than just a factual dispute; the fact in question must be material and the dispute must be genuine. See Fed R. Civ. P. 56(c); Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 248, 106 S.Ct. 2505, 2510, 91 L.Ed.2d 202 (1986). Although the court must view the facts in the light most favorable to the nonmovant, see Anderson, 477 U.S. at 255, 106 S.Ct. at 2513, “bare allegations unsupported by legally competent evidence do not give rise to a genuine dispute of material fact.” Solis v. Prince George’s County, 153 F.Supp.2d 793, 807 (D.Md.2001). Summary judgment should be granted unless a reasonable jury could return a verdict in favor of the nonmovant on the evidence presented. McLean v. Patten Communities, Inc., 332 F.3d 714, 719 (4th Cir.2003) (citing Anderson, 477 U.S. at 247-48, 106 S.Ct. at 2509-10).

III. ANALYSIS

The central issue in these summary judgment motions is whether the facts are sufficiently settled for the court to determine that the City Manager’s decision was either reasonable or unreasonable. The facts and circumstances have developed in this case in a way probably anticipated by no one at the time the contract was signed. The application of the correct standard to the unique situation at hand is difficult to determine from the case law. The City urges the court to adopt a “substantial evidence” approach and to uphold the City Manager’s decision as long as there is substantial evidence supporting it. MCI opposes this approach and urges the court to focus on the deficiencies in the City Manager’s decision and to overturn it if it finds the City Manager either did something he should not have done or failed to do something he should have done. The court will consider each of these arguments in turn.

A. The City’s Motion

The City bases its summary judgment motion on the argument that the court should adopt a substantial evidence test for evaluating the reasonableness of the City Manager’s decision.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
Mezzanotte v. Freeland
200 S.E.2d 410 (Court of Appeals of North Carolina, 1973)
Welborn Plumbing & Heating Co. v. Randolph County Board of Education
150 S.E.2d 65 (Supreme Court of North Carolina, 1966)
Elec-Trol, Inc. v. C. J. Kern Contractors, Inc.
284 S.E.2d 119 (Court of Appeals of North Carolina, 1981)
Weyerhaeuser Co. v. Godwin Building Supply Co.
253 S.E.2d 625 (Court of Appeals of North Carolina, 1979)
Smith v. Currie
253 S.E.2d 645 (Court of Appeals of North Carolina, 1979)
Wheeler v. Wheeler
263 S.E.2d 763 (Supreme Court of North Carolina, 1980)
Midulla v. Howard A. Cain Co., Inc.
515 S.E.2d 244 (Court of Appeals of North Carolina, 1999)
Resort Realty of the Outer Banks, Inc. v. Brandt
593 S.E.2d 404 (Court of Appeals of North Carolina, 2004)
Wilder v. Squires
315 S.E.2d 63 (Court of Appeals of North Carolina, 1984)
Zurn Engineers v. STATE OF CALIF., DEPT. WATER RES
69 Cal. App. 3d 798 (California Court of Appeal, 1977)
Foster Enterprises, Inc. v. Germania Federal Savings & Loan Ass'n
421 N.E.2d 1375 (Appellate Court of Illinois, 1981)
Solis v. Prince George's County
153 F. Supp. 2d 793 (D. Maryland, 2001)
McAden v. . Craig
24 S.E.2d 1 (Supreme Court of North Carolina, 1943)
McAden v. Craig
222 N.C. 497 (Supreme Court of North Carolina, 1943)
McLean v. Patten Communities, Inc.
332 F.3d 714 (Fourth Circuit, 2003)
Smith v. Dickinson
290 S.E.2d 770 (Court of Appeals of North Carolina, 1982)

Cite This Page — Counsel Stack

Bluebook (online)
401 F. Supp. 2d 504, 2005 U.S. Dist. LEXIS 30536, 2005 WL 3157584, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mci-constructors-inc-v-hazen-and-sawyer-pc-ncmd-2005.