MCI Constructors, Inc. v. Hazen and Sawyer, Pc

405 F. Supp. 2d 621, 2005 U.S. Dist. LEXIS 30537, 2005 WL 3481328
District Court, M.D. North Carolina·Decided November 28, 2005·No. 1:99CV00002, 1:02CV00396·Published·Cited by 3 cases

Opinion

MEMORANDUM OPINION AND ORDER

OSTEEN, District Judge.

Plaintiff MCI Constructors, Inc. (“MCI”) filed this diversity suit against Defendant Hazen and Sawyer, P.C. (“Hazen and Sawyer”) alleging violations of North Carolina law, including negligence, professional malpractice, negligent misrepresentation, tortious interference with contract, unfair and deceptive trade practices, bad faith breach of duty, fraud, conspiracy to defraud, and fraud on the court. This matter is before the court on two motions by Hazen and Sawyer for summary judgment.

I. BACKGROUND

These claims are part of an ongoing dispute arising out of a contract between MCI and the City of Greensboro, North Carolina (“the City”) for the construction of a wastewater treatment plant. The background of the claims against the City can be found in the court’s memorandum opinions, dated March 24, 2000, October 6, 2000, January 18, 2001, September 6, 2001, and November 1, 2002. The following facts are relevant to the motion at hand.

In 1995, after a competitive bidding process, MCI and the City entered into a contract for the upgrade and expansion of the T.Z. Osborne Wastewater Treatment plant (“the project”). Hazen and Sawyer, an engineering and consulting firm, was to act as a project supervisor. Hazen and Sawyer had designed the upgrade and extension and had participated in compiling the information made available to construction companies for the preparation of bids.

The contract called for MCI to complete the project in four phases. Heavy rain in 1996 delayed Phase I, and MCI utilized contract procedures to request an extension of time, which the City granted. Phase II was also delayed by unexpected conditions on the project site. These conditions caused MCI to spend larger amounts than planned to continue construction and caused the project to fall behind schedule. MCI did not use contract procedures to request a time extension. Phase II was not completed by the contractually established deadline of October 7, 1997. Accordingly, in May 1998, MCI and the City agreed to a new completion date of September 15, 1998. Shortly thereafter, the City concluded that MCI was not able to comply with the revised schedule. On June 17, Ed Kitchen, the Greensboro City Manager (“the City Manager”), notified MCI that the City was terminating the contract.

Following the termination of the contract, MCI sued Hazen and Sawyer, alleging torts associated with the breach of Hazen and Sawyer’s professional duties. These allegations included misfeasance by Hazen and Sawyer during the bidding pro *625 cess and during the building process. Further allegation, as well as one of Hazen and Sawyer’s defenses arose after the suit was filed.

In addition to suing Hazen and Sawyer, MCI sued the City, alleging causes of action centered around a breach of contract theory. The court concluded that it was required to enforce a provision of the contract, Article 16, dictating that certain disputes between the parties regarding the fulfillment of the contract would be submitted to the City Manager, who would be empowered to resolve them. The City Manager held two hearings. The first was held for the purpose of determining whether the termination was “for cause” or “for convenience”; 1 the second was for the purpose of determining damages. The City Manager concluded that the termination had been for cause and that MCI was required under the contract to pay the City approximately $13.4 million in damages. The amount of the award was based on a series of costs detailed in a change order (“Change Order 6”), issued by the City shortly before the beginning of the proceedings before the City Manager. Change Order 6 adjusted the contract price in such a way as to increase the amount of money owed by MCI to the City. Pursuant to the contract, Change Order 6 was approved by Hazen and Sawyer.

MCI challenged the City Manager’s decision and award in this court. The court upheld the decision and entered an order enforcing it. MCI successfully appealed the order, and further review of the City Manager’s decision is now pending.

II. STANDARD OF REVIEW

Summary judgment is appropriate when an examination of the pleadings, affidavits, and other proper discovery materials before the court demonstrates that there is no genuine issue of material fact, thus entitling the moving party to judgment as a matter of law. Fed.R.Civ.P. 56(c); Celotex Corp. v. Catrett, 477 U.S. 317, 322-23, 106 S.Ct. 2548, 2552, 91 L.Ed.2d 265 (1986). If the non-moving party is to prevail, there must be more than just a factual dispute; the fact in question must be material and the dispute must be genuine. See Fed R. Civ. P. 56(c); Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 248, 106 S.Ct. 2505, 2510, 91 L.Ed.2d 202 (1986). Although the court must view the facts in the light most favorable to the nonmovant, see Anderson, 477 U.S. at 255, 106 S.Ct. at 2513, “bare allegations unsupported by legally competent evidence do not give rise to a genuine dispute of material fact.” Solis v. Prince George’s County, 153 F.Supp.2d 793, 807 (D.Md.2001). Summary judgment should be granted unless a reasonable jury could return a verdict in favor of the nonmovant on the evidence presented. McLean v. Patten Communities, Inc., 332 F.3d 714, 719 (4th Cir.2003) (citing Anderson, 477 U.S. at 247-48, 106 S.Ct. at 2509-10).

III. ANALYSIS

Hazen and Sawyer has advanced several alternative theories under which it believes it is entitled to summary judgment. There are nine counts listed in the complaint, and each is addressed by at least one of the theories. Specifically, in its first motion, Hazen and Sawyer moved for summary judgment on: (1) all counts, *626 on the basis of a defense of res judicata and collateral estoppel; (2) all counts, on the basis of lack of evidence of damages; (3) counts involving negligence, on the basis of a defense of contributory negligence; (4) counts involving rock, on the basis of lack of evidence; (5) the claim of unfair trade practices, on the basis of a defense, the “learned profession” exception; and (6) the claim of tortious interference with contract, on the basis of a defense of qualified privilege. In its Second Motion for Summary Judgment, Hazen and Sawyer renewed its claims of res judicata and collateral estoppel. MCI has conceded that it has failed to establish a claim for unfair trade practices, and summary judgment will be granted on .that claim. The other bases for summary judgment are addressed in turn.

A. Res judicata and Collateral Estop-pel

Hazen and Sawyer argues that all of MCI’s claims are barred by res judicata or collateral estoppel. “Under the doctrine of res judicata, or claim preclusion, ‘a final judgment on the merits in a prior action will prevent a second suit based on the same cause of action between the same parties or those in privity with them.’ ” State ex rel. Tucker v.

Free access — add to your briefcase to read the full text and ask questions with AI

MCI Constructors, Inc. v. Hazen and Sawyer, Pc, 405 F. Supp. 2d 621, 2005 U.S. Dist. LEXIS 30537, 2005 WL 3481328 (M.D.N.C. 2005).

405 F. Supp. 2d 621 (MCI Constructors, Inc. v. Hazen and Sawyer, Pc) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Alexander v. City of Greensboro
762 F. Supp. 2d 764 (M.D. North Carolina, 2011)