MCI Constructors, Inc. v. City of Greensboro

125 F. App'x 471
CourtCourt of Appeals for the Fourth Circuit
DecidedMarch 15, 2005
Docket04-1395, 04-1729
StatusUnpublished
Cited by4 cases

This text of 125 F. App'x 471 (MCI Constructors, Inc. v. City of Greensboro) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fourth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
MCI Constructors, Inc. v. City of Greensboro, 125 F. App'x 471 (4th Cir. 2005).

Opinion

PER CURIAM.

The City of Greensboro, North Carolina entered into a contract with MCI Constructors, LLC on January 16, 1996, for the construction of a wastewater ti'eatment plant in Greensboro, for a cost of roughly $29 million. Greensboro’s City Manager signed the contract on behalf of the City. As required by North Carolina law, MCI obtained a performance bond from National Union Fire Insurance Company of Pittsburgh, Pennsylvania. The bond incorporated the terms of the contract between the City and MCI and guaranteed that MCI would “well and truly perform” the contract. The contract includes Article 16 which provides that Greensboro’s City Manager resolve disputes relating to the performance of the contract and that the City Manager’s decision “shall be final and conclusive” and “in case any question touching the contract shall arise between *474 the parties, such ... decision shall be a condition precedent to the right of [MCI] to receive any monies under the Contract.”

When construction of the wastewater plant became substantially delayed, the City terminated the contract, and the City Manager thereafter acting as “referee” under Article 16 of the contract, determined that MCI materially breached the contract and owed the City roughly $13.4 million in damages.

MCI commenced this action challenging, among other things, the City Manager’s determination. The district court ruled that the City Manager’s determination in favor of the City was analogous to the determination of a third party arbitrator, such as an architect or engineer, and should not be set aside except on a showing of “fraud, bad faith, or gross mistake.” Because MCI failed to advance evidence sufficient to prove fraud, bad faith, or gross mistake, the district court entered summary judgment in favor of the City. The district court also entered summary judgment against the surety, National Union, on its bond.

On appeal, MCI contends (1) that the district erred in requiring MCI to submit its claims first to the City Manager; (2) that the district court erred in applying a standard of “fraud, bad faith, or gross mistake” to review the City Manager’s decision; and (3) that MCI was denied procedural due process when the City Manager acted arbitrarily and when the district court subsequently decided the City’s claims based on the City Manager’s decisionmaking authority, which in MCI’s view amounts to “a taking of property without any process whatsoever.” Independent of the issues raised by MCI, National Union contends that the claim against it on the bond was barred by a one-year contractual-limitations period or a three-year statute-of-limitations period. National Union also challenges the judgment against it because it was not given the opportunity “to perform as surety” and complete the contract, thereby reducing the damages which were based on inflated costs.

We affirm all the rulings of the district court except its application of the “fraud, bad faith, or gross mistake” standard, which it applied to review the decision of the City Manager. On that issue, we reverse and remand for further proceedings. We conclude that since the City Manager signed the contract for the City and in essence was adjudicating his own performance, rights, and liabilities under the contract, North Carolina law requires that the City Manager’s performance be measured by a standard of objective reasonableness “based upon good faith and fair play”—a standard that must be read into the contract so as to prevent the contract from being rendered illusory. Accordingly, we affirm in part, reverse and vacate in part, and remand to the district court for further proceedings consistent with this opinion.

I

MCI commenced this diversity action against the City and the City’s engineer, alleging claims for breach of contract, breach of warranty, quantum meruit, negligent misrepresentation, wrongful termination, and declaratory relief that the City’s termination of the contract was wrongful. The City filed a motion to dismiss as well as a counterclaim for breach of contract. It also filed a third-party claim against National Union on its bond. Pursuant to motions filed by the parties, the court dismissed most of the claims, concluding that Article 16 of the contract was “broadly worded” and required that “all disputes regarding the fulfillment of the contract by MCI go to the City Manager.”

*475 The parties submitted their claims to the City Manager, and on April 16, 2002, the City Manager ruled that the City had properly terminated MCI “for cause” and rejected MCI’s claim that the termination was “for convenience.” MCI returned to the district court and moved to vacate the decision for “evident partiality” under the Federal Arbitration Act and sought to enjoin further proceedings before the City Manager with respect to damages. The district court rejected MCI’s claims and ruled that the proceedings before the City Manager were controlled by North Carolina law, not the Federal Arbitration Act.

After the City Manager conducted hearings on damages, he rendered a decision on February 5, 2003, concluding that “MCI Constructors shall pay to the City of Greensboro the sum of $13,377,842.73.” On receipt of this decision, MCI filed a second amended complaint to add claims for fraud, conspiracy, and “fraud on the court.”

Thereafter on the City’s motion for summary judgment, the district court found that “there is no legally sufficient evidentiary basis for a reasonable jury to find that the City Manager’s decision was influenced by fraud, bad faith, or gross mistake” and that “MCI [is left] with no further viable claims.” The court also granted the City’s motion for summary judgment against National Union as surety. On MCI’s Rule 59 motion for a new trial, MCI renewed its objection to the application of the fraud standard for reviewing the City Manager’s decision and argued, for the first time, that Article 16 in fact operated as a “satisfaction clause,” which would render the contract illusory and therefore unenforceable. The district court denied this motion. From the district court’s final judgment, this appeal followed.

II

MCI contends first that the district court erred by “requiring MCI to submit issues to [the City Manager] that the Contract did not allow [the City Manager] to decide.” As a consequence, the City Manager allegedly exceeded the authority conferred on him because, as MCI argues, the contract did not empower him to decide issues concerning the City’s breach of the contract or the propriety of the City Manager’s own conduct; it only allowed him to render decisions regarding MCI’s performance.

The district court ruled that the language of Article 16 of the contract “is broadly worded” and “requires that all disputes concerning the fulfillment of the contract by MCI go to the City Manager.” * Article 16 thus “acts as a condition precedent to MCI’s recovery of payment under the contract, but the condition precedent does not, as MCI argues, act as a limit on the scope of the claims which must be submitted to the City Manager.”

The City Manager rendered a decision first that the City’s termination of MCI *476 was for the delays in the project and therefore was for cause.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Russo v. School Board
835 F. Supp. 2d 125 (E.D. Virginia, 2011)
MCI CONSTRUCTORS, LLC v. City of Greensboro
610 F.3d 849 (Fourth Circuit, 2010)
Strategic Outsourcing, Inc. v. Continental Casualty Co.
414 F. Supp. 2d 545 (W.D. North Carolina, 2006)
Beachcrete, Inc. v. Water Street Center Associates, L.L.C.
615 S.E.2d 719 (Court of Appeals of North Carolina, 2005)

Cite This Page — Counsel Stack

Bluebook (online)
125 F. App'x 471, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mci-constructors-inc-v-city-of-greensboro-ca4-2005.