Wright & Kremers, Inc. v. State

238 A.D. 260, 264 N.Y.S. 393, 1933 N.Y. App. Div. LEXIS 9481
CourtAppellate Division of the Supreme Court of the State of New York
DecidedMay 10, 1933
DocketClaim No. 21683
StatusPublished
Cited by12 cases

This text of 238 A.D. 260 (Wright & Kremers, Inc. v. State) is published on Counsel Stack Legal Research, covering Appellate Division of the Supreme Court of the State of New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Wright & Kremers, Inc. v. State, 238 A.D. 260, 264 N.Y.S. 393, 1933 N.Y. App. Div. LEXIS 9481 (N.Y. Ct. App. 1933).

Opinion

Taylor, J.

In September, 1928, plaintiff entered into a contract with defendant to construct a shop building on the site of Auburn [261]*261Prison. Plaintiff has a judgment for $30,809.26, mainly for damages resulting from delays caused by the State.

Sections 76 and 78 of article 20 of the contract read as follows: “ If the Contractor is delayed in the completion of his work by any act or neglect of the State, or by changes ordered in the work, or by any cause which the Chief Engineer shall deem to justify the delay as being.beyond the Contractor’s control, then the time of completion shall be extended for such reasonable time as the Chief Engineer may decide.” (§ 76.)

“No charges or claim for damages shall be made by the Contractor for any delays or hindrances, from any cause whatsoever, during the progress of any portion of the work embraced in this contract. Such delays or hindrances shall be compensated for by an extension of time as above provided.” (§ 78.)

Leaving out of consideration delays caused by claimant or its subcontractors, the only relief available to the claimant for delays resulting “ from any cause whatsoever ” was an extension of claimant’s time for completion. Since it appears that none of the delays caused by the State was unrelated to the contract or not within the contemplation of the parties (Johnson v. City of New York, 191 App. Div. 205; affd., 231 N. Y. 564); that none was caused by direct interference on the part of the State (Waples Co. v. State of New York, 178 App. Div. 357); and that none of the delays was so great or unreasonable that it might fairly be deemed to indicate an abandonment of the contract (People ex rel. Wells & Newton Co. v. Craig, 232 N. Y. 125, 144; Brady & Co. v. Board of Education, 222 App. Div. 504), the claimant is concluded by the portions of the contract referred to. (Norcross v. Wills, 198 N. Y. 336; Mechanics' Bank v. City of New York, 164 App. Div. 128; Mack v. State of New York, 122 Misc. 86; affd., 211 App. Div. 825.)

The haulage and steam heat items ($3,163.50 and $186.90), the latter paid by the claimant under compulsion, were in fairness extras under the contract and claimant should have judgment for them. (Contract, art. 209, methods 3 and 4; amended art. 3605, § 36, subd. 8.)

The judgment should be modified by reducing it to the amount of $3,350.40, plus interest, and as thus modified affirmed, without costs; certain findings of fact and conclusions of law disapproved and reversed or modified and new findings and conclusions made.

All concur.

Judgment modified on the law and facts in accordance with the opinion, and as modified affirmed, without costs of this appeal to either party. Certain findings of fact and conclusions of law disapproved and reversed and new findings and conclusions made.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Corinno Civetta Construction Corp. v. City of New York
493 N.E.2d 905 (New York Court of Appeals, 1986)
Kalisch-Jarcho, Inc. v. City of New York
448 N.E.2d 413 (New York Court of Appeals, 1983)
Peckham Road Co. v. State
32 A.D.2d 139 (Appellate Division of the Supreme Court of New York, 1969)
Websco Construction Corp. v. State
57 Misc. 2d 9 (New York State Court of Claims, 1966)
Falls v. Thomas S. Clarkson Memorial College of Technology
5 A.D.2d 918 (Appellate Division of the Supreme Court of New York, 1958)
D'Angelo v. State
200 Misc. 657 (New York State Court of Claims, 1951)
In re the Arbitration between Herbert G. Martin, Inc. & Municipal Housing Authority
277 A.D.2d 904 (Appellate Division of the Supreme Court of New York, 1950)
Endres Plumbing Corp. v. State
198 Misc. 546 (New York State Court of Claims, 1950)
Shore Bridge Corp. v. State
186 Misc. 1005 (New York State Court of Claims, 1946)
J. Harry McNally, Inc. v. State
170 Misc. 914 (New York State Court of Claims, 1939)
Cauldwell-Wingate Co. v. State
249 A.D. 892 (Appellate Division of the Supreme Court of New York, 1937)
Cauldwell-Wingate Co. v. State
156 Misc. 901 (New York State Court of Claims, 1935)

Cite This Page — Counsel Stack

Bluebook (online)
238 A.D. 260, 264 N.Y.S. 393, 1933 N.Y. App. Div. LEXIS 9481, Counsel Stack Legal Research, https://law.counselstack.com/opinion/wright-kremers-inc-v-state-nyappdiv-1933.