Cauldwell-Wingate Co. v. State

156 Misc. 901, 283 N.Y.S. 285, 1935 N.Y. Misc. LEXIS 1545
CourtNew York Court of Claims
DecidedOctober 5, 1935
DocketClaim No. 21953
StatusPublished
Cited by4 cases

This text of 156 Misc. 901 (Cauldwell-Wingate Co. v. State) is published on Counsel Stack Legal Research, covering New York Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Cauldwell-Wingate Co. v. State, 156 Misc. 901, 283 N.Y.S. 285, 1935 N.Y. Misc. LEXIS 1545 (N.Y. Super. Ct. 1935).

Opinion

Ryan, J.

The claimant Cauldwell-Wingate Company entered into a contract with the State of New York, dated March 1, 1928. The contract provided for the construction of the State office building on the site bounded by Center, Worth, Baxter and Leonard streets in New York city. The contract contained certain provisions which are important to our consideration and to which, for convenience, we shall assign a letter in quoting them as follows:

“A. Information for Bidders, page 1, paragraph 8. Visit to site: Proposals will be held as having been made with full knowledge of conditions and requirements. The Contractor will be held to have visited the premises, prior to the time of submitting his proposal, and to have appraised the conditions under which the work of this contract is to be executed.
“B. General Description, page 3, paragraph 3. Work not included: The work of this contract is contingent upon the execution of the foregoing work by the Foundation Contractor and shall follow said work in orderly sequence. This Contractor shall so execute his work as to avoid interference with, or delay of, other contracts.
C. Addenda No. 3, paragraph 6. Time of Completion of Foundation Work. The time of completion specified for the foundation work is July 1, 1928.
“ D. Article 23, page 8, changes in the work. Changes and. extension of time: The State without invalidating the contract, may make changes by altering, adding to or deducting from the work, the contract sum being adjusted accordingly.
E. Article 33, page 11, delays. Extension of time: If the Contractor be delayed in the completion of the work by any act or neglect of the State, or by changes ordered in the work, or by any cause which the Architect shall deem to justify the delay as being beyond the Contractor’s control, then the time of completion shall be extended for such reasonable time as the Architect may decide.
F. Article 36, page 12, damages. Damages for delays: No charges or claim for damages shall be made by the Contractor, under the provisions of this Article, for any delays or hindrance, from any cause whatsoever, during the progress of any portion of the work [903]*903embraced in this contract. Such delays or hindrances shall be compensated for under the provisions of Article 33.
“ G. Article 40, subcontracts, page 14. Contractual relations: Nothing contained in the contract documents shall create any contractual relations between any subcontractor and the State.
“ H. Agreement: The work to be commenced promptly * * * and to be fully completed on or before March 31, 1929.”

Several orders on contract authorizing additions and deductions were issued during the progress of the work. As to these there is no controversy with the exception of Force Order No. 42, to which we shall give consideration later.

The time for completion of the contract was extended to November 10, 1929 (Letter March 14, 1929) and was again extended to December 20, 1929 (Letter November 18, 1929, Exhibit 20). The work was finally completed on or about the latter date. Final estimate was issued and final payment was accepted by Cauldwell-Wingate Company on January 20, 1930, with reservation of the right to file claim for damages.

Shortly after the execution of the contract Cauldwell-Wingate Company submitted to the State its proposed progress schedule (Exhibit 9) which was returned by the chief engineer with letter dated April 26, 1928, which read as follows: “ This schedule is approved with the understanding that the work of your contract is contingent upon the execution of the foundation work now being performed under separate contract, all as noted in your Specification #5014.” (Exhibit 20.)

To this Cauldwell-Wingate Company replied by letter dated May 7, 1928: We acknowledge receipt of your letter of April 26th returning one copy of our progress schedule in connection with the erection of the superstructure of the State Office Building, New York city, which schedule is approved tentatively contingent upon the execution of the foundation work, which was awarded under separate contract.

“ We are proceeding with our work as called for under our contract, and in accordance with Addenda #3 to the specifications, and will be ready to begin erection of steel on July 1st, 1928.

If at any time it can be determined with reasonable accuracy the completion of the foundation contract will be delayed and the terms of such delay, it is most important that we be notified that we may prevent a large accumulation of fabricated material and the consequent expense of handling, storage, etc.” (Exhibit 20.)

Under date of May 10, 1928, the chief engineer advised Cauldwell-Wingate Company: “ there has been some delay in the Foundation Work, due to conditions as encountered at the site,” and under [904]*904date of May 18, 1928, the chief engineer advised Cauldwell-Wingate Company as follows: This is to advise that the time of completion of J. L. McDonald’s contract for Construction of Foundations, State Office Building, New York City, has been extended from July 1st to August 20th, 1928.

Your contract provides that the progress of your work is contingent upon the completion of this foundation contract. You should be governed accordingly.” (Exhibit 20.)

In the meantime the foundation contractor, McDonald, whose work was to be completed on or before July 1, 1928 (Exhibit 22), had entered upon his work. Before bidding McDonald had examined the site of the proposed work and found it “ to be covered with cinders at an elevation of about two feet above the curb level except where it was occupied by two brick buildings, one a two-story building and one a one-story building.” Likewise before bidding, McDonald had examined the plans and specifications for his work and found that they provided that contractor “ should remove existing structures from the premises including buildings, fences, piles, masonry and other existing work within the limits of the area bounded by the curb lines of the streets bounding the site.” The plans furnished McDonald by the State included a cross section and showed the elevation and artificial structures to be removed and only represented thereon the aforesaid two buildings.”

When McDonald began work with his steam shovel it was immediately disclosed upon excavation that beneath said two feet of cinders were foundation walls and masonry footings of about thirty houses, apartments and office buildings superimposed on wooden piles from fifteen to twenty feet in length which structures had formerly occupied said entire block and a portion of which had been erected in former days over a pond which once had water to a depth of about fifty feet, and these old foundation walls had been covered with said cinder fill.” McDonald was then directed by the State Department of Public Works “ to make thirty-seven composite borings over the entire site which borings were made to varying depths including one boring to the depth of one hundred twenty-seven feet.” These borings “ disclosed the existence of said old foundation and the existence of said pond ” and thereupon the specifications in McDonald’s contract

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Teal v. Potash Company of America
292 P.2d 99 (New Mexico Supreme Court, 1956)
J. Harry McNally, Inc. v. State
170 Misc. 914 (New York State Court of Claims, 1939)
De Riso Bros. v. State
161 Misc. 934 (New York State Court of Claims, 1937)

Cite This Page — Counsel Stack

Bluebook (online)
156 Misc. 901, 283 N.Y.S. 285, 1935 N.Y. Misc. LEXIS 1545, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cauldwell-wingate-co-v-state-nyclaimsct-1935.