D'Angelo v. State

200 Misc. 657, 106 N.Y.S.2d 350, 1951 N.Y. Misc. LEXIS 2071
CourtNew York Court of Claims
DecidedJuly 7, 1951
DocketClaim No. 29779
StatusPublished
Cited by10 cases

This text of 200 Misc. 657 (D'Angelo v. State) is published on Counsel Stack Legal Research, covering New York Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
D'Angelo v. State, 200 Misc. 657, 106 N.Y.S.2d 350, 1951 N.Y. Misc. LEXIS 2071 (N.Y. Super. Ct. 1951).

Opinion

Ryan, J.

This suit was brought to recover damages for breach of contract and for extra work, labor and services performed. After the matter was at issue the parties consented to entry of judgment in favor of claimants in the sum of $29,835.87, the balance admitted by the defendant to be due and owing upon the contract for the quantities furnished in constructing a highway at the line item prices. The award was made without interest and the question of the right to recover interest was directed to be held in abeyance until the trial of this part of the claim. We shall consider this question later.

After the severance of the first cause of action and after the entry of judgment thereon, claimants, upon due notice, moved to amend their claim by adding thereto allegations of certain items of extra work, labor and services performed not included in the sum awarded as hereinabove recited and not previously pleaded. The motion was granted and an order of amendment granted. Although the Attorney-General appeared and opposed the motion and at the time did not claim surprise nevertheless he again attacks the ruling of the court and, since he does, we make comment. The Attorney-General’s position is not well taken. All of the items pleaded and on which proof was offered arose out of the work of construction under the contract and the circumstances surrounding these disputes were or should have been within the knowledge of the engineers who represented the [661]*661State of New York. There has been no loches on the part of the claimants, the defendant has not been prejudiced and the amendment was proper and within the discretion of the court. (Court of Claims Act, § 9, subd. 8; Murray v. State of New York, 202 App. Div. 597 [1922]; Burrows Paper Co. v. State of New York, 174 Misc. 850, 856 [1940]; Warranty Holding Corp. v. State of New York, 59 N. Y. S. 2d 512 [1946]; Banko, Inc., v. State of New York, 186 Misc. 491 [1946]; Fitzgerald Bros. Constr. Co. v. State of New York, 188 Misc. 940 [1947]. See, also, Murray v. State of New York, No. 24923 [1939], unreported, and Street Bros. Constr. Co. v. State of New, No. 25386 [1940], unreported.)

Claimants entered into a contract with the State of New York to construct a farm to market, or secondary, road known as the Phoenicia-Stony Clove Highway, Part 2, FAS SH 47-9 State highway. The construction was to be three miles of grading, drainage and bituminous macadam pavement. The road ran through the Catskill State Forest Preserve and where it deviated from the old location the highway was to be built on lands owned by the State of New York as part of the Preserve. Item No. IS of claimants’ itemized proposal was for the necessary quantities of clearing and grubbing, a lump sum bid in the amount of $2,331.87. Before preparing their bid claimants inspected the site and found, in the area to be cleared and grubbed, a timber growth. There being nothing in the contract to prohibit them, claimants planned to salvage the timber from the areas which they would clear and grub and to sell it at a profit and they made their lump sum bid accordingly. Claimants’ bid was filed and accepted on September 17, 1947. Thereafter and before the written contract was signed claimants were informed by a representative of the Department of Public Works that the State Conservation Department demanded that the trees cut in clearing for the building of the new road be piled in four foot lengths on the right of way and made available for crews of that department to collect for use on State recreational campsites. This information was available to the Department of Public Works on September 16, 1947, but was not made known to claimants until September 30, 1947. Thereupon claimants offered to fell the trees if the State would remove them so that claimants could proceed with their work. There ensued extended correspondence, in writing and by telephone, between the State Department of Public Works and the State Conservation Department in which i lie latter department amended its requirements with respect to [662]*662the timber “ to provide that any oak, ash and hemlock saw logs designated by the representative of this Department shall be cut in log lengths and made available on skidways to our trucks. * * * The balance of the wood to be cut in 4 ft. lengths as originally provided.” The final position of the State was not communicated to the claimants until November 18, 1947. In the meantime and on October 8, 1947, within three weeks from the award to them of the contract, the claimants had started work. Clearing and grubbing was, of course, one of the first operations on the job. Claimants reached that part of the right of way which was on forest preserve lands on October 24, 1947. Although it was, and still is, claimants’ contention that in accordance with the usual and standard practice, custom and agreement, trees cut pursuant to the contract Item IS became the contractor’s property, claimants yielded to the demands of the Conservation Department, transmitted to them through the Department of Public Works. This was, however, upon the understanding that the saw logs and cord wood would be removed promptly by the State. Claimants proceeded to fell the trees and the State removed part of the ash logs. But it is undisputed that the State did not fully or promptly carry out its part of the agreement. The trees remained in claimants’ way until nearly the close of the job in the fall of 1948. Some of them had to be removed by the claimants. In general, claimants were impeded and interfered with in the progress- of their work.

To this item of the claim the State offers several defenses. The first is that section 1 of article XIV of the Constitution, which provides that the forest preserve shall be forever kept as wild forest lands and that the timber thereon shall not be sold, removed or destroyed, prohibited claimants from availing themselves of any salvage from the trees and that they should have known the law and the Constitution before they bid. The fact is that the plans for the highway to be built through the forest preserve necessarily contemplated that a certain amount of growing timber would be cut, removed or destroyed. The Attorney-G-eneral concedes as much. This was a proper exercise of authority by the State Department of Public Works. (L. 1921, ch. 401, as amd. by L. 1937, ch. 488.) As the plans did not call for the removal of timber to any material or unreasonable degree, the Constitution was not violated. (Association for Protection of Adirondacks v. MacDonald, 253 N. Y. 234 [1930].)

A second defense interposed is that the claimants had actual knowledge of the Conservation Department’s demand for the [663]*663timber prior to the time they started work and prior to the actual signing of the contract on November 1, 1947; that claimants chose to enter into the contract with full knowledge that they would not be permitted to dispose of the timber; that the contract was integrated by the writings (Higgs v. de Maziroff, 263 N. Y. 473 [1934]); that claimants are attempting to vary the terms of the written agreement by paroi evidence. As we have already pointed out, the contract was awarded to the claimants on September 17, 1947, upon a bid which they had made which contemplated that they would have the avails of whatever could be salvaged in the clearing and grubbing area.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States v. John P. Hannon
728 F.2d 142 (Second Circuit, 1984)
City of New York v. State
95 Misc. 2d 810 (New York State Court of Claims, 1978)
D'Angelo v. State
350 N.E.2d 615 (New York Court of Appeals, 1976)
Buckley & Co., Inc. v. State
356 A.2d 56 (New Jersey Superior Court App Division, 1975)
Acme Builders, Inc. v. County of Nassau
36 A.D.2d 317 (Appellate Division of the Supreme Court of New York, 1971)
Fehlhaber Corp. v. State
64 Misc. 2d 167 (New York State Court of Claims, 1970)
Tippetts-Abbett-McCarthy-Stratton v. State
27 Misc. 2d 506 (New York State Court of Claims, 1960)
Rusciano & Son Corp. v. State
201 Misc. 690 (New York State Court of Claims, 1952)

Cite This Page — Counsel Stack

Bluebook (online)
200 Misc. 657, 106 N.Y.S.2d 350, 1951 N.Y. Misc. LEXIS 2071, Counsel Stack Legal Research, https://law.counselstack.com/opinion/dangelo-v-state-nyclaimsct-1951.