Lieberman v. . Templar Motor Co.

140 N.E. 222, 236 N.Y. 139, 29 A.L.R. 1089, 1923 N.Y. LEXIS 867
CourtNew York Court of Appeals
DecidedMay 29, 1923
StatusPublished
Cited by36 cases

This text of 140 N.E. 222 (Lieberman v. . Templar Motor Co.) is published on Counsel Stack Legal Research, covering New York Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Lieberman v. . Templar Motor Co., 140 N.E. 222, 236 N.Y. 139, 29 A.L.R. 1089, 1923 N.Y. LEXIS 867 (N.Y. 1923).

Opinion

*143 Cardozo, J.

The Hudson Auto Body Corporation, plaintiff’s assignor, made a contract on August 21, 1919, with the defendant, the Templar Motor Company, to manufacture automobile bodies for use in the defendant’s cars. The contract is in writing. It calls for 2,500 bodies to be made according to a special design. Deliveries are to commence on December 1, and to continue at the rate of ten bodies a day. The price is to be $130 per body, F. O. B. freight cars, New York city. If railroad facilities are lacking, the bodies may be stored at the defendant’s expense. The manufacturer is not to be held responsible for delay by reason of strikes or other causes not within its control.

The Hudson Company began work upon the bodies as soon as the defendant’s specifications were complete. Delay ensued as the consequence of a strike, which started in October, 1919, and ended in February, 1920. Work was then renewed, and shipments were made in April, 1920, and at frequent intervals thereafter. Much inconvenience was caused, however, by the shortage of freight cars. The situation was the subject of'a conference between the Hudson Company’s representatives and those of the defendant held at the Hotel Pennsylvania in New York on May 19, 1920. There is testimony that at this conference the written contract of August was modified by word of mouth. The manufacturer offered to store the completed bodies free of cost in its *144 own rooms until freight cars were at hand,- and thus to save the defendant the enormous loss t resulting from storage in a public warehouse. A weekly invoice was to be forwarded showing the production of bodies for the week, and shipment was to follow as soon as cars could be procured. In return, the defendant’s representatives agreed that when invoices were forwarded with the O. K. of their inspector, they would make payment at once, and in advance of delivery, for the bodies then completed. The Hudson Company, pursuant to this agreement, sent its invoices from week to week, though in many instances without waiting for the inspector’s approval. They shipped the bodies by rail as facilities were offered, and transmitted to the defendant the bills of lading for the shipments.

By August 27, 1920, invoices had been sent to the defendant for 610 bodies. By August 30, all but three of these 610 bodies had been shipped, and bills of lading forwarded. The invoices from April 28 to July 16, inclusive, covering 420 bodies, were paid in full. The invoices from July 23 to August 27, covering 190 bodies, and calling for payments of $24,158.50, were paid in part. There was unpaid a balance of $16,358.50. As early as August 6 the defendant gave evidence of its unwillingness to go forward with the contract. On that day, its president, Mr. Bramley, wrote the Hudson Company that there was “ practically no demand ” for cars, and that he wished to “ arrange to stop production entirely, or limit production to a minimum.” Conferences followed. Mr. Bramley asked for cancellation. He said the defendant was not paying out any money to any one. The Hudson Company said that cancellation was impossible, and that its bills must be paid; but offered concessions. It offered to suspend production altogether if the defendant would pay the overhead charges during the period of suspension. The defendant refused. It offered to take trade acceptances for com *145 pleted bodies if the banks would accept them, but the banks were unwilling. It offered to limit production to 25 cars a week, and this the defendant apparently approved, though continuing to disregard the invoices which steadily accumulated. On September 9, 1920, the Hudson Company’s attorney went to Cleveland to find out why the invoices had not been paid, and if possible collect them. Bramley refused to pay. He said that the defendant had no money even for its payroll. He offered no other excuse. When told that the Hudson Company would sue, he said to go ahead. “ The best thing your company can do is to file a petition in bankruptcy.” This action followed in October, 1920.

Two causes of action are stated in the complaint. The first is for $16,358.50, the balance said to be unpaid for bodies delivered to the defendant, or ready for delivery. The second is for damages resulting from the defendant’s refusal to go forward with performance.

We think the defendant’s conduct on September 9, 1920, viewed in the fight of earlier happenings, might be found by a jury to have been intended as a repudiation of the contract. The argument is made that the money was not due. The O. K. of the inspector, which was necessary only if payment was demanded before shipment, had not been placed upon the invoices. There is room for doubt whether some castings of trifling value were sent forward with the bodies. The defendant, however, did not put its refusal to pay on any of these grounds. There was not a word in any of the conferences about an invoice or a casting. Such defects, if they existed, could have been easily supplied (2 Wilfiston on Contracts, §§ 743, 744; Strasbourger v. Leerburger, 233 N. Y. 55, 60; Callanan v. Keeseville, A. C. & L. C. R. R. Co., 199 N. Y. 268, 284). There was an unexcused and definitive refusal to pay a dollar either then or in the future (Helgar Corp. v. Warner’s Features, Inc., 222 N. Y. *146 449). The refusal was couched in terms that were equivalent to a renunciation of performance. So, at least, a jury might interpret its significance.

The Appellate Division, conceding repudiation by the defendant, found the evidence insufficient on the side of the plaintiff to show ability and readiness to perform in accordance with the contract. The oral modification on May 19, 1920, was disregarded as ineffective under the Statute of Frauds. The plaintiff or his assignor was held to be in default when performance was tested by the contract as originally made. The test, we think, is inappropriate.

The contract of August 21, 1919, was one by its terms not to be performed within a year. That is the only reason why at the time of its making there was need of a written memorandum (Pers. Prop. Law [Cons. Laws, ch. 41], § 31). Deliveries beginning on December 1, and continuing at the rate of ten bodies a day, would cover a period of ten months from December 1, which would be more than twelve months from August 21. The contract was not one for the sale of goods, for the bodies were to be manufactured according to a special design, which belonged to the defendant and not to dealers generally (Pers. Prop. Law, § 85, subd. 2). Besides, there was part payment, and also acceptance and receipt. Except, therefore, for the element of time a writing was unnecessary. But on May 19, 1920, when the modification was adopted, performance could have been carried to completion-in a time much shorter than a year. In such circumstances, the necessity for a writing no longer existed. A contract originally within the statute because not to be performed within a year, and then reduced to writing so as to be valid at its making, may be modified without a writing at a time when performance within the year is possible (Williams v. Moss’ Empires, Ltd., 1915, 3 K. B. 242; Blake v. Neils Lumber Co., 111 Minn. 513, 516;

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Magnet Resources v. Summit MRI, Inc.
723 A.2d 976 (New Jersey Superior Court App Division, 1998)
Harry Kolomick Contractors, Inc. v. Shelter Rock Estates, Inc.
172 A.D.2d 492 (Appellate Division of the Supreme Court of New York, 1991)
Campagnola v. Mulholland
555 N.E.2d 611 (New York Court of Appeals, 1990)
Pension Benefit Guaranty Corp. v. Beadle
685 F. Supp. 628 (E.D. Michigan, 1988)
Haven Associates v. Donro Realty Corp.
121 A.D.2d 504 (Appellate Division of the Supreme Court of New York, 1986)
Picciano v. Olympic Construction Co.
112 A.D.2d 604 (Appellate Division of the Supreme Court of New York, 1985)
Kenford Co. v. County of Erie
108 A.D.2d 132 (Appellate Division of the Supreme Court of New York, 1985)
Plant Planners, Inc. v. Pollock
457 N.E.2d 781 (New York Court of Appeals, 1983)
Industrial Circuits Co. v. Terminal Communications, Inc.
216 S.E.2d 919 (Court of Appeals of North Carolina, 1975)
Hodes v. Hoffman International Corporation
280 F. Supp. 252 (S.D. New York, 1968)
West, Weir & Bartel, Inc. v. Mary Carter Paint Co.
25 A.D.2d 81 (Appellate Division of the Supreme Court of New York, 1966)
Perfecting Service Co. v. Product Development & Sales Co.
131 S.E.2d 9 (Supreme Court of North Carolina, 1963)
Alexander H. Kerr & Co. v. Fooks
145 F. Supp. 503 (W.D. Arkansas, 1956)
Mutual Ben. Health & Accident Ass'n v. Cohen
194 F.2d 232 (Eighth Circuit, 1952)

Cite This Page — Counsel Stack

Bluebook (online)
140 N.E. 222, 236 N.Y. 139, 29 A.L.R. 1089, 1923 N.Y. LEXIS 867, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lieberman-v-templar-motor-co-ny-1923.