Tippetts-Abbett-McCarthy-Stratton v. State

27 Misc. 2d 506, 212 N.Y.S.2d 247, 1960 N.Y. Misc. LEXIS 2026
New York Court of Claims·Decided December 14, 1960·No. Claim No. 34766·Published·Cited by 1 cases

Opinion

Bernard Ryan, P. J.

The above-entitled claimant is a partnership consisting of several individual engineers, each licensed to engage in his profession in this State. As such entity they sue for the agreed and reasonable value of services rendered pursuant to a contract with the State of New York acting by and through the Superintendent of Public Works, less certain payments received on account. As originally pleaded the claim contained five causes of action. The first cause of action was for a balance due on account in the amount of $153,389.31. This demand has been reduced to $82,517.12 as the result of voluntary payments by the State in the sum of $40,823.23 and additional payments, by virtue of a severance order, decision and judgment of this court, in the amount of $26,685.91 for retained percentages, and in the amount of $3,363.02 for utility design. The question of the -claimant’s right to recover interest on certain sums already paid was reserved in and by the prior decision. The question of the [508]*508right to interest upon a sum previously paid is all that remains of the second cause of action to be adjudicated herein. The third cause of action has been discontinued. Recovery under the fourth and fifth causes of action has been granted pursuant to the earlier decision and judgment, and upon those two causes of action there remains only the question of the right to interest on the sums therein awarded. Our main concern is the question of the interpretation of the meaning of the phrase “ current prices ” as applied to Item 2B “ Unclassified Excavation” of the claimant’s contract.

On July 11, 1951 claimant partnership received a letter of intent from the New York State Department of Public Works inquiring as to whether it would be interested in performing the survey and design of a project on the Hudson section of the Thruway from Tuckahoe Eoad to Eoute 9 in the vicinity of Tarrytown, Westchester County. The estimated construction cost of the project was given as $13,500,000. A proposed contract dated October 24, 1951 was first sent to claimant on November 26, 1951. Claimant signed it and returned it on November 28. On December 18, 1951 the State Department of Public Works transmitted to the claimant a copy of the document duly executed by its officials and authenticated.

The contract was entitled:

1 AGREEMENT EOR THE PRELIMINARY SURVEY, CONTRACT PLANS, ESTIMATES, SPECIFICATIONS AND RIGHTS-OF-WAY MAPS FOR THE PORTION OF THE NEW YORK STATE THRUWAY, HUDSON SECTION, FROM TUCKAHOE ROAD TO ROUTE 9 (DISTRICT SECTION 10) WESTCHESTER COUNTY. ’ ’

It designated the first party as Superintendent and the second party, the claimant, as Engineer. It ivas divided into four parts, namely: Survey; Preliminary Plans; Contract Plans; Eight of Way Maps. It required the Engineer to:

‘ ‘ Render all services and furnish all materials and equipment necessary to provide the State with plans, estimates and other data more specifically prescribed under Part I, Part II, Part III and Part IV as follows:” [We quote the clauses deemed pertinent, viz.:]

Part II

(d) “A preliminary estimate of the construction cost of the Project at current prices, with separate breakdowns for the highway portion for each structure. The structure estimates shall show the approximate quantities required for sub-structure, superstructure and temporary construction.”

[509]*509Part III

(c) An itemized estimate with neat and rounded quantities of the construction cost of each contract of the Project, computed at current prices as used by the Department of Public Works. Separate breakdown estimates shall be prepared in similar form for each structure and for the highway portions of each contract. The structure estimates shall be sub-divided into sub-structure, superstructure and temporary construction. A cost analysis shall accompany the highway estimate.”

provision fob payment

(4c) “ Subject to the completion and acceptance of the work required under Part III of this Agreement, the State shall pay to the engineer, and the engineer agrees to accept as full compensation therefor 3%% of the estimated construction cost, at current prices, of the Project as approved by the superintendent under Part III of this Agreement, less the sum of $120,000.00 (representing the amount paid to the engineer for services under Part II hereof).”

Immediately upon receipt of the letter of intent in July, 1951 claimant started work. Part I, Survey, was completed in December of 1952. Part II, Preliminary Plans, was begun in October, 1951 and completed in December, 1952. Part III, which constituted the final design, was begun in August, 1952 and was completed in October, 1953.

The site of the work was in District No. 8 (the designation of the site as in District No. 10 in the title of the contract was, apparently, a clerical error (see 1951 Legis. Manual, p. 534) of the State Department of Public Works. At the time James S. Bixby was District Engineer. In October, 1951, after a conference with Mr. Bixby, representatives of the claimant were told that they were to use unit prices provided by the State of New York for standard items, but that major items such as excavation, and probably the major concrete items, were to be analyzed and developed by the claimant from knowledge that claimant had acquired about this particular project. Because of the prevalence of rock on the site, an understanding was reached that excavation would be divided into two classifications in accordance with Public Works specifications of January 2, 1951, viz., Item 3B — Classified Earth Excavation, and Item 4B — Classified Bock Excavation. For preliminary purposes it was agreed that a reasonable price for Item 3B would be 90 cents per cubic yard and for Item 4B $3 per cubic yard.

On June 11, 1952 a supplemental agreement which provided for the performance of certain additional work modified the [510]*510original contract. Under date of October 17, 1952 Mr. Bixby transmitted to the claimant (Exhibit 15) copy of a letter dated September' 29, 1952 addressed to him by J. B. MeMorran, Chief Engineer of the Department of Public Works (Exhibit 16) entitled “Be: Payment to Contractors.” We quote from that letter:

‘ ‘ The Superintendent has ruled that on all existing Design Contracts, the term “ current prices ” shall be interpreted to mean 1951 average bid prices for the District in which the Project is located. Items for which there are no District average prices shall be computed at State-wide average prices.

“ The Engineering News Becord factor, which indicates the trend in construction prices since January 1, 1952, shall be added to or subtracted from the total amount of the estimate in order to establish current prices as of the date final payment to the Engineer is approved. As determined from this factor, construction prices for August 1952 are nine percent (9%) higher than the' 1951 average.

“ Factors for subsequent months will be forwarded as received.”

Under date of November 10, 1952 claimant submitted to Mr. Bixby the preliminary estimate which it had prepared pursuant to that part of the contract hereinabove quoted as Part II (d). This estimate for the cost of the project was $12,931,000, and included therein were the following items:

Item
No. Item

Free access — add to your briefcase to read the full text and ask questions with AI

Tippetts-Abbett-McCarthy-Stratton v. State, 27 Misc. 2d 506, 212 N.Y.S.2d 247, 1960 N.Y. Misc. LEXIS 2026 (N.Y. Super. Ct. 1960).

27 Misc. 2d 506 (Tippetts-Abbett-McCarthy-Stratton v. State) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Tippetts-Abbett-McCarthy-Stratton v. New York State Thruway Authority
27 Misc. 2d 533 (New York State Court of Claims, 1961)