Edwards v. State

14 Misc. 2d 748, 178 N.Y.S.2d 287, 1958 N.Y. Misc. LEXIS 3677
New York Court of Claims·Decided March 19, 1958·No. Claim No. 33850; Claim No. 33849·Published·Cited by 2 cases

Opinion

Russell Gr. Hunt, J.

These two claims involve an identical issue and they differ only slightly in their facts. The sole issue is the construction to be given to the provisions of four contracts respecting claimants’ fees. The claims were tried together upon a single record. Such was the stipulation. The claimants do not contend that they ought to be paid for services as for breach of contract. They contend simply that there is a balance owing to them, under the contract, for the services they performed. The State raises no question about the services having been completed, expertly and well.

The claimants proceeded first with respect to claim No. 33850 in which they seek to recovér a balance for engineering fees under two negotiated contracts with the State (H. C. 2122 and H. C. 2258) relating to engineering work for the construction of sections of the Thruway System. Claim No. 33849 seeks to recover a balance allegedly owing under two negotiated con[750] tracts (H. C. 2619 and H. C. 2621) with the State Thruway Authority for like work for road construction supplementary to that embraced in the aforesaid two contracts with the State.

The contracts provided that the claimants were to do the engineering work of preliminary surveys, plans, estimates, specifications and rights of way maps (and other work not necessary to detail). The work was divided into four parts in the order of (1) surveys and maps (called “ part 1 work ”);

(2) preliminary plans and estimates (called “ part 2 work ”);

(3) detailed contract plans, design drawings and itemized estimates of the construction cost of each project (called “ part 3 work ”), which were to be “ computed at current prices as used by the Department of Public Works ” (so, in the two contracts with the State — and, substantially the same in the two contracts with the Authority, for, according to claimants’ witness, Beck, all four contracts “intended the same meaning”); and, (4) a general map and individual rights of way maps (called “ part 4 work ”).

The claimants were to be paid for each part of the work separately and as the parts progressed. The dispute arises in connection with the fees for the design work (pt. 3 work). For this work the claimants were to be paid “ 3%% of the estimated construction cost at current prices, of the project as approved by the Superintendent ’ ’, or, in the case of the contracts with the Authority, by the chairman thereof; these all ‘ ‘ intended the same meaning ”, Mr. Beck testified.

The proof proceeded first with H. C. 2122, which was dated July 16, 1951 and executed on the same day by the claimants and on August 8, 1951 by the Superintendent of Public Works and approved by ¡the State Comptroller on July 25, 1951, as to - the amount expressly limited by the contract pursuant to section 112 of the State Finance Law, and by the State Budget Director pursuant to section 8 of the Public Works Law. The evidence adduced and the record so made was, by agreement, to be taken as the record in each of the other contract cases. These chronologically followed H. C. 2122. H. C. 2258 was dated October 31, 1951 and was executed by the claimants on December 10, 1951 and by the Superintendent on December 21, 1951; it was approved by the State Comptroller and the Budget Director. H. C. 2619 (with the State Thruway Authority) -was dated October 31, 1952 and executed by the claimants on January 28, 1953 and by the Authority on February 18, 1953. H. C. 2621 (also with the Authority) was' dated October 31, 1952 and executed by the claimants on January 28, 1953 and by the Authority on February 26, 1953. Each one of the contracts was amended by [751] one or more supplemental agreements, and, in each final supplemental agreement there was a clause reciting that the claimants did not waive their claims for the balance of fees allegedly due under each contract as to which claim had been made previously and refused.

The first work was performed by the claimants under H. C. 2122, and, claimants’ monthly estimate No. 1, of the work performed by them, dated August 17,1951 shows that for the period “up to and including August 17, 1951 ”, only part 1 work was performed to a small extent. The first billing for part 2 work was contained in monthly estimate No. 5, dated December 7, 1951 and the first billing for part 3 work was contained in monthly estimate No. 16, dated November 8, 1952.

Free access — add to your briefcase to read the full text and ask questions with AI

Edwards v. State, 14 Misc. 2d 748, 178 N.Y.S.2d 287, 1958 N.Y. Misc. LEXIS 3677 (N.Y. Super. Ct. 1958).

14 Misc. 2d 748 (Edwards v. State) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Edward C. Flaherty Corp. v. State
102 Misc. 2d 438 (New York State Court of Claims, 1979)
Tippetts-Abbett-McCarthy-Stratton v. State
27 Misc. 2d 506 (New York State Court of Claims, 1960)