Endres Plumbing Corp. v. State

198 Misc. 546, 95 N.Y.S.2d 574, 1950 N.Y. Misc. LEXIS 1434
CourtNew York Court of Claims
DecidedMarch 8, 1950
DocketClaim No. 28126
StatusPublished
Cited by3 cases

This text of 198 Misc. 546 (Endres Plumbing Corp. v. State) is published on Counsel Stack Legal Research, covering New York Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Endres Plumbing Corp. v. State, 198 Misc. 546, 95 N.Y.S.2d 574, 1950 N.Y. Misc. LEXIS 1434 (N.Y. Super. Ct. 1950).

Opinion

Lounsberry, P. J.

In December of 1940, the claimant entered into a contract with the State of New York to install the plumbing in buildings 3 and 4 of a new State hospital to be constructed near Deer Park, Long Island. The completion date specified in the contract was June 1, 1942. At about the same time, a contract for the general construction was let to Amsterdam Construction Company, also to be completed by June 1, 1942.

Claimant complains that the Amsterdam company failed to progress its work thus making it impossible for claimant to complete its contract until September of 1944. As a result, it alleges, it was unable to perform the plumbing work in the orderly, expeditious manner it had contemplated and thereby had considerable increased labor and overhead expense, for which it now seeks to charge the State.

Unquestionably, the general construction work overran the completion date. Plaster and tiling was not entirely complete in building 4 until July 25, and in building 3 until September 26, 1942. With this, however, the general construction was 97% complete and nothing remained to prevent claimant from setting fixtures, the last step in its work, except final tests and adjustments. By its own admission claimant had contemplated and could then have completed the fixture installation in twenty working days, or before November 1, 1942, by using a force of twenty men. Actually, it used no more than five and thus carried the work through December. Even then, it lacked certain vital equipment which it was unable to secure and install until January and March of 1944.

There was one other source of delay. The State did not let the sewer and water line contract until October 27, 1942, and [548]*548these services were not available until February, 1944. Until then, claimant could not run final tests and adjustments. Nothing in its contract required it to remain on the job meanwhile, however, or even to forego final payment until completion of tests. All that was reasonably required was a return to the scene for certainly no more than one month to complete the work. It did, in fact, string along the final adjustments, which could have been made by two men in two weeks, over a six-month period, but did so at its own election and over the State’s protest:

From the foregoing it is apparent that no more than five month’s delay, from June 1 to November 1, 1942, plus an additional month for tests and adjustments, can reasonably be attributed to lack of progress in the general construction and in the furnishing of connections. During the rest of the period of the claimed delay, claimant was either working on another job (it spent only about two weeks of 1943 at the Deer Park project), or was performing work which could have been performed sooner by use of an adequate force, or had equipment been available. It is significant that after May, 1942, when union rules were changed to forbid a foreman in charge of more than four men to work with tools, claimant never operated with more than a working foreman and four men, regardless of its original progress schedule or of the needs of the work.

There is no evidence in the record of any specific unreasonable or inefficient conduct by the Amsterdam company, or any active interference by it with claimant’s work, or that it used other than sound and accepted construction methods. Likewise, there is no evidence that the State at any time arbitrarily interfered with the work of either contractor, or imposed any changes of specifications or other unanticipated demands or conditions, or in any way caused the delay, so far as the fixture installation is concerned. It did contribute to the delay in running the tests, but the claimant itself was not able to run them until it installed certain mixing valves in January, 1944, which were not previously available. The tests were run soon thereafter. Hence, the claimant is scarcely in a position to complain of this particular delay.

The claimant’s contention seems to be that the State is automatically liable if through a delay by one of its contractors, another is delayed. The cases are not entirely harmonious but we are satisfied that such is not the law. The law is, rather, that there is no automatic liability, but that the State may become liable for delay where it furnishes misleading specifications, requires or permits substantial changes in the speci[549]*549fications or procedures, arbitrarily interferes with the progress of the work or unreasonably fails to progress it, takes some action not contemplated by the parties to the contract, or otherwise actively or negligently causes an unreasonable delay, resulting in damage to a contractor. Reference to some of the decided cases will illustrate:

In American Bridge Co. v. State of New York (245 App. Div. 535 [1935]), involving the construction of a bridge, the foundation contractor encountered serious difficulties, thus delaying the claimant who was the superstructure contractor. Although it was obvious that the delay would be prolonged, the State nevertheless ordered the claimant to proceed with the fabrication of its steel, which then had to be stored out-of-doors until it could be used. As a result, it had to be repainted at considerable additional expense to the claimant. The court allowed a claim for damages on the ground that the damages arose from active interference by the State rather than merely from delay.

In Cauldwell-Wingate Co. v. State of New York (276 N. Y. 365 [1938]) involving the erection of the State Office Building in New York, the claimant, who held the superstructure contract, suffered a long delay by reason of the inability of the foundation contractor to complete its work on schedule. The specifications for the foundation prepared by the State indicated that it could be completed in about three weeks and the foundation contract so required. Claimant based its progress plans on the assumption that this would be done. The foundation specifications proved to be so utterly misleading and inadequate, however, that some nine months were required for completion. The court allowed a claim for damages by the superstructure contractor on the ground that while it assumed the risk of delay by the foundation contractor in the performance of its contract according to the specifications supplied, it did not assume the risk of delay resulting from defective specifications. The court at page 372 said: The Cauldwell Cpmpany, by the contract provision above quoted, accepted the contingency of delay in the execution of the foundation contract, but only such delay as was occasioned in the performance of that contract, according to plans and specifications.”

In Hayes Constr. Co. v. State of New York (254 App. Div. 915 [1938], affd. 279 N. Y. 755) a highway construction contractor sought damages for delays by a town in completing certain bridges, and by the State in failing to remove certain structures, [550]*550poles and hydrants. The court disallowed the claim, holding that the delays were related to the contract and were within the contemplation of the parties; that they were not unreasonable, and that they were not caused by the direct interference of the State.

In Waples Co. v. State of New York (178 App. Div. 357 [1917]) the claimant had contracted to clean and waterproof the stonework of the State Capitol building, the method of waterproofing to be proposed by the contractor and approved by the State.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

New Again Construction Co. v. City of New York
76 Misc. 2d 943 (New York Supreme Court, 1974)
Snyder Plumbing & Heating Corp. v. State
21 Misc. 2d 591 (New York State Court of Claims, 1960)
C. F. Mentzinger's Son, Inc. v. State
278 A.D. 1019 (Appellate Division of the Supreme Court of New York, 1951)

Cite This Page — Counsel Stack

Bluebook (online)
198 Misc. 546, 95 N.Y.S.2d 574, 1950 N.Y. Misc. LEXIS 1434, Counsel Stack Legal Research, https://law.counselstack.com/opinion/endres-plumbing-corp-v-state-nyclaimsct-1950.