NASDI, LLC v. Skanska Koch Inc. Kiewit Infrastructure Co. (JV)

CourtCourt of Appeals for the Second Circuit
DecidedMarch 26, 2024
Docket23-571
StatusUnpublished

This text of NASDI, LLC v. Skanska Koch Inc. Kiewit Infrastructure Co. (JV) (NASDI, LLC v. Skanska Koch Inc. Kiewit Infrastructure Co. (JV)) is published on Counsel Stack Legal Research, covering Court of Appeals for the Second Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
NASDI, LLC v. Skanska Koch Inc. Kiewit Infrastructure Co. (JV), (2d Cir. 2024).

Opinion

23-571 NASDI, LLC v. Skanska Koch Inc. Kiewit Infrastructure Co. (JV)

UNITED STATES COURT OF APPEALS FOR THE SECOND CIRCUIT

SUMMARY ORDER RULINGS BY SUMMARY ORDER DO NOT HAVE PRECEDENTIAL EFFECT. CITATION TO A SUMMARY ORDER FILED ON OR AFTER JANUARY 1, 2007, IS PERMITTED AND IS GOVERNED BY FEDERAL RULE OF APPELLATE PROCEDURE 32.1 AND THIS COURT’S LOCAL RULE 32.1.1. WHEN CITING A SUMMARY ORDER IN A DOCUMENT FILED WITH THIS COURT, A PARTY MUST CITE EITHER THE FEDERAL APPENDIX OR AN ELECTRONIC DATABASE (WITH THE NOTATION “SUMMARY ORDER”). A PARTY CITING TO A SUMMARY ORDER MUST SERVE A COPY OF IT ON ANY PARTY NOT REPRESENTED BY COUNSEL.

At a stated term of the United States Court of Appeals for the Second Circuit, held at the Thurgood Marshall United States Courthouse, 40 Foley Square, in the City of New York, on the 26th day of March, two thousand twenty-four.

PRESENT: DENNY CHIN, SUSAN L. CARNEY, RICHARD J. SULLIVAN, Circuit Judges. _____________________________________

NASDI, LLC,

Plaintiff-Counter- Defendant-Appellant,

v. No. 23-571

SKANSKA KOCH INC. KIEWIT INFRASTRUCTURE CO. (JV), d.b.a. SKANSKA KIEWIT JV,

Defendant-Counter- Claimant-Appellee. ∗ _____________________________________

∗ The Clerk of Court is respectfully directed to amend the official case caption as set forth above. For Plaintiff-Counter- DOUGLAS W. EYRE (Mark L. McAlpine, on Defendant-Appellant: the brief), McAlpine PC, Auburn Hills, MI.

For Defendant-Counter- ROBERT H. BELL (Paul Monte, on the brief), Claimant-Appellee: Peckar & Abramson, P.C., New York, NY.

Appeal from a judgment of the United States District Court for the Southern

District of New York (Denise L. Cote, Judge).

UPON DUE CONSIDERATION, IT IS HEREBY ORDERED,

ADJUDGED, AND DECREED that the March 10, 2023 judgment of the district

court is AFFIRMED.

NASDI, LLC appeals from the district court’s grant of summary judgment

in favor of Skanska Koch Kiewit Inc. Infrastructure Co. (JV) (“SKK”) on NASDI’s

claims for breach of contract, quantum meruit, and breach of the covenant of good

faith and fair dealing. The parties’ dispute stems from demolition work that

NASDI subcontracted to complete for SKK after the Port Authority of New York

and New Jersey selected SKK as the general contractor for a four-stage project to

reconstruct the Bayonne Bridge between Staten Island and New Jersey.

According to the subcontract, NASDI would handle demolitions in Stages 1 and

2, stand down during Stage 3, and resume demolition work in Stage 4. By the

time Stage 2 wrapped up in December 2014, the project was already ten months

behind schedule, and it became apparent that the start of NASDI’s Stage 4 work

2 would be delayed significantly. Though the subcontract had a “no-damages-for-

delay” clause that barred NASDI from suing SKK over delays, it also set forth a

procedure for NASDI to submit claims to SKK for additional compensation, as

well as a protocol for splitting any delay-related settlements that the Port

Authority paid to SKK. At SKK’s invitation, NASDI submitted a claim in mid-

2016 in connection with the expected Stage 4 delays, which SKK forwarded to the

Port Authority along with claims from SKK’s other subcontractors. The Port

Authority indicated that it would pay out these claims in a bulk settlement to SKK,

which would then allocate it among the subcontractors.

In December 2016, SKK sent NASDI a revised schedule indicating that Stage

4 work would begin in February 2017, about nineteen months later than what the

parties had originally contemplated. NASDI initially agreed to that schedule.

But days later, NASDI demanded that SKK immediately settle its claim over the

Stage 4 delays, even though SKK was still finalizing the bulk settlement with the

Port Authority. Several weeks later, NASDI sent SKK a notice of termination

asserting that SKK had “abandoned” the subcontract due to the delays and SKK’s

failure to negotiate NASDI’s claim in good faith. Sp. App’x at 14. Though

NASDI quickly attempted to rescind that termination, SKK declared NASDI to be

3 in default and hired a replacement demolition firm to help complete the work.

That substitute performance cost SKK an extra $24 million, which it covered by

making a demand on NASDI’s performance bond.

NASDI filed this action in May 2017, asserting claims for breach of contract,

quantum meruit, and breach of the covenant of good faith and fair dealing. SKK

moved for summary judgment on all three claims, which the district court granted.

This appeal followed.

We review a district court’s grant of summary judgment de novo, construing

facts in the light most favorable to the nonmoving party and resolving all

ambiguities and drawing all reasonable inferences against the moving party. See

Kee v. City of New York, 12 F.4th 150, 157 (2d Cir. 2021). Summary judgment is

appropriate only when there is no genuine dispute of material fact that would

allow a reasonable jury to rule in favor of the nonmoving party. See Fed. R. Civ.

P. 56(a).

I. The No-Damages-For-Delay Clause

NASDI first takes issue with the district court’s grant of summary judgment

on its breach of contract claim, which the district court held was barred by the

4 subcontract’s no-damages-for-delay clause. 1 Such clauses – which prevent a

plaintiff from suing a defendant over delays that occur while performing on a

contract – are generally valid and enforceable in New York. See Corinno Civetta

Constr. Corp. v. City of New York., 67 N.Y.2d 297, 309 (1986). And while New York

law recognizes several exceptions under which a plaintiff can sue a defendant for

delay, plaintiffs face a “heavy burden” in seeking to invoke them. N. Star

Contracting Corp. v. City of New York, 611 N.Y.S.2d 11, 12 (1st Dep’t 1994). 2

NASDI contends that two of these exceptions apply here. First, it argues

that the clause was unenforceable because the delays here – nineteen months in

total 3 – were “uncontemplated.” Corinno, 67 N.Y.2d at 309. But New York

1 The subcontract provides the no-damages-for-delay clause in section 13.1: “13.1 NO DAMAGE FOR DELAY. Except as otherwise provided . . . , Subcontractor agrees that it shall have no Claim against Contractor for any loss or damage it may sustain through delay, disruption, suspension, stoppage, interference, interruption, compression, or acceleration of Subcontractor’s Work (‘Delay Damages’) caused or directed by Contractor for any reason, and that all such Claims shall be fully compensated for by Contractor’s granting Subcontractor such time extensions as it is entitled to as a result of any of the foregoing.” App’x at 43. 2 To the extent NASDI relies on a third exception – bad faith – to the enforceability of a no-

damages-for-delay clause, we discuss the issue below in our analysis of the claims for breach of the covenant of good faith and fair dealing. 3 Stage 4 was scheduled to commence in July 2015 but did not begin until February 2017. Though NASDI asserts that it had to contend with twenty-nine months of delays – ten months in completing Stages 1 and 2 and nineteen months in starting Stage 4 – that figure is inaccurate as it double counts the ten-month delay in finishing Stages 1 and 2. Indeed, Stage 4 started nineteen months later than originally scheduled, which includes the ten months of overrun accrued in Stages 1 and 2.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Kulak v. City of New York
88 F.3d 63 (Second Circuit, 1996)
Kee v. City of New York
12 F.4th 150 (Second Circuit, 2021)
Corinno Civetta Construction Corp. v. City of New York
493 N.E.2d 905 (New York Court of Appeals, 1986)
Bovis Lend Lease LMB Inc. v. GCT Venture, Inc.
6 A.D.3d 228 (Appellate Division of the Supreme Court of New York, 2004)
Commercial Electrical Contractors, Inc. v. Pavarini Construction Co.
50 A.D.3d 316 (Appellate Division of the Supreme Court of New York, 2008)
Gottlieb Contracting, Inc. v. City of New York
86 A.D.2d 588 (Appellate Division of the Supreme Court of New York, 1982)
Manshul Construction Corp. v. Board of Education
160 A.D.2d 643 (Appellate Division of the Supreme Court of New York, 1990)
North Star Contracting Corp. v. City of New York
203 A.D.2d 214 (Appellate Division of the Supreme Court of New York, 1994)

Cite This Page — Counsel Stack

Bluebook (online)
NASDI, LLC v. Skanska Koch Inc. Kiewit Infrastructure Co. (JV), Counsel Stack Legal Research, https://law.counselstack.com/opinion/nasdi-llc-v-skanska-koch-inc-kiewit-infrastructure-co-jv-ca2-2024.