The Pike Company, Inc. v. Tri-Krete Limited

CourtDistrict Court, W.D. New York
DecidedMarch 24, 2025
Docket6:18-cv-06311
StatusUnknown

This text of The Pike Company, Inc. v. Tri-Krete Limited (The Pike Company, Inc. v. Tri-Krete Limited) is published on Counsel Stack Legal Research, covering District Court, W.D. New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
The Pike Company, Inc. v. Tri-Krete Limited, (W.D.N.Y. 2025).

Opinion

UNITED STATES DISTRICT COURT WESTERN DISTRICT OF NEW YORK

THE PIKE COMPANY, INC.,

Plaintiff, DECISION AND ORDER v. 6:18-CV-06311 EAW TRI-KRETE LIMITED,

Defendant.

INTRODUCTION

Plaintiff The Pike Company (“Pike”) commenced this action on April 20, 2018, against Defendant Tri-Krete Limited (“Tri-Krete”) for breach of contract. (Dkt. 1). Tri- Krete thereafter asserted several counterclaims against Pike, including common law causes of action for breach of contract, unjust enrichment, nonpayment of invoices and statements of accounts, and violations of the New York Prompt Payment Act, N.Y. Gen. Bus. Law §§ 756 et seq. (“PPA”). (Dkt. 5 at 4-7). Pending before the Court are the parties’ motions for partial summary judgment. (Dkt. 82; Dkt. 83). For the following reasons, Tri-Krete’s motion (Dkt. 82) is granted in part and denied in part, and Pike’s motion (Dkt. 83) is denied. BACKGROUND Pike filed its complaint on April 20, 2018. (Dkt. 1). Tri-Krete filed an answer with counterclaims on June 25, 2018. (Dkt. 5). Contemporaneously with the filing of its answer, Tri-Krete filed a motion to stay the action and to compel arbitration (Dkt. 7), and Pike thereafter filed a motion to stay arbitration on July 2, 2018 (Dkt. 9). Pike filed an answer to Tri-Krete’s counterclaims on July 16, 2018. (Dkt. 13). On August 7, 2018, Pike filed a motion for a temporary restraining order (Dkt. 17), which it withdrew without prejudice on August 8, 2018 (Dkt. 20). Thereafter, Pike filed a motion for a preliminary injunction on August 29, 2018, as well as a motion to expedite.

(Dkt. 22; Dkt. 23). On November 11, 2018, the Court issued a Decision and Order granting Tri-Krete’s motion to stay the federal court action, denying Pike’s motion to stay arbitration, and denying Pike’s motion for a preliminary injunction, concluding that the alleged PPA violations encompassed by Tri-Krete’s fourth counterclaim were arbitrable. (Dkt. 39). The Court directed the parties to provide status updates concerning the status of

the arbitration. (Dkt. 40). On November 16, 2020, Tri-Krete filed a motion to confirm the arbitration award (Dkt. 43), and on December 11, 2020, Pike filed a motion to stay enforcement of the arbitration award (Dkt. 46). On November 9, 2021, the Court issued a Decision and Order granting in part and denying in part the motion to confirm the arbitration award, to enter

partial final judgment, and to lift the stay. (Dkt. 51). The case was referred to former United States Magistrate Judge Marian W. Payson for discovery. (Dkt. 52). Pike and Tri-Krete filed motions for partial summary judgment on April 30, 2024. (Dkt. 82; Dkt. 83). The parties filed responses to the motions on May 28, 2024 (Dkt. 88; Dkt. 89), and replies were filed on June 11, 2024 (Dkt. 94; Dkt. 95). DISCUSSION I. Legal Standard Rule 56 of the Federal Rules of Civil Procedure provides that summary judgment

should be granted if the moving party establishes “that there is no genuine dispute as to any material fact and the movant is entitled to judgment as a matter of law.” Fed. R. Civ. P. 56(a). The Court should grant summary judgment if, after considering the evidence in the light most favorable to the nonmoving party, it finds that no rational jury could find in favor of that party. Scott v. Harris, 550 U.S. 372, 380 (2007) (citing Matsushita Elec.

Indus. Co. v. Zenith Radio Corp., 475 U.S. 574, 586-87 (1986)). “The moving party bears the burden of showing the absence of a genuine dispute as to any material fact[.]” Crawford v. Franklin Credit Mgmt. Corp., 758 F.3d 473, 486 (2d Cir. 2014). “Where the non-moving party will bear the burden of proof at trial, the party moving for summary judgment may meet its burden by showing the evidentiary materials of record, if reduced

to admissible evidence, would be insufficient to carry the non-movant’s burden of proof at trial.” Johnson v. Xerox Corp., 838 F. Supp. 2d 99, 103 (W.D.N.Y. 2011) (citing Celotex Corp. v. Catrett, 477 U.S. 317, 322-23 (1986)). Once the moving party has met its burden, the opposing party “must do more than simply show that there is some metaphysical doubt as to the material facts, and may not

rely on conclusory allegations or unsubstantiated speculation.” Robinson v. Concentra Health Servs., Inc., 781 F.3d 42, 44 (2d Cir. 2015) (quoting Brown v. Eli Lilly & Co., 654 F.3d 347, 358 (2d Cir. 2011)). Specifically, the non-moving party “must come forward with specific evidence demonstrating the existence of a genuine dispute of material fact.” Brown, 654 F.3d at 358. Indeed, “the mere existence of some alleged factual dispute between the parties will not defeat an otherwise properly supported motion for summary judgment; the requirement is that there be no genuine issue of material fact.” Anderson v.

Liberty Lobby, Inc., 477 U.S. 242, 247-48 (1986). II. Tri-Krete’s Motion for Summary Judgment Tri-Krete moves for summary judgment on the following issues: (1) finding that Pike cannot recover “owner damages” totaling $2,700,000, which it identified as part of its December 15, 2021 Rule 26 disclosures, since Pike never incurred such damages; (2)

finding that Pike cannot recover estimated costs in the amount of $300,000, for the completion of the Tri-Krete punch list work, since Pike never incurred such damages; (3) finding that Pike did not have a contractual obligation to complete Building D by August 31, 2017, and therefore precluding the introduction of time-related damages after that time; and (4) finding that Pike failed to mitigate its damages because it did not utilize a

contingency of $2,683,759, to which it was contractually entitled. (Dkt. 82-1 at 7). Pike concedes that Tri-Krete is entitled to summary judgment on the first two issues—that is, that Pike is not entitled to seek owner damages totaling $2,700,000, since Marist College, despite claiming these damages against Pike, did not pursue them, and also that Pike is not entitled to seek damages for punch list and non-conforming work, including

because Pike’s former Senior Project Manager, Gloria Ciminelli, testified that Pike’s costs for this work were “nominal.” (Dkt. 89 at 4). Accordingly, the Court grants Tri-Krete summary judgment on these two issues, and Pike will not be permitted to seek recovery of the $2,700,000 in owner damages, or the $300,000 in punch list work, at trial. The Court examines the remaining two issues in turn. A. Relevant Facts This case arose out of the construction of student dormitory buildings located at

Marist College (“Marist”). (See Declaration of Adam Bombini, Vice President of Tri- Krete, in Support of Tri-Krete’s Motion for Summary Judgment, Dkt. 82-3 ¶¶ 1, 3). The Project was divided into two phases: Phase 1, which consisted of Building A and Building B, and Phase 2, which consisted of Building C and Building D. (Id. at ¶ 3). Tri-Krete was a subcontractor on the project, and it was responsible for installing pre-cast concrete wall

panels for Phase 2 of the project.1 (Id.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

NetJets Aviation, Inc. v. LHC COMMUNICATIONS, LLC
537 F.3d 168 (Second Circuit, 2008)
Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
Scott v. Harris
550 U.S. 372 (Supreme Court, 2007)
Brown v. Eli Lilly and Co.
654 F.3d 347 (Second Circuit, 2011)
Cauff, Lippman & Co. v. Apogee Finance Group, Inc.
807 F. Supp. 1007 (S.D. New York, 1992)
ADC Orange, Inc. v. Coyote Acres, Inc.
857 N.E.2d 513 (New York Court of Appeals, 2006)
U.S. Bank National Ass'n v. Ables & Hall Builders
696 F. Supp. 2d 428 (S.D. New York, 2010)
Travelers Casualty & Surety Co. v. Dormitory Authority-State
735 F. Supp. 2d 42 (S.D. New York, 2010)
Franklin Pavkov Construction Co. v. Ultra Roof, Inc.
51 F. Supp. 2d 204 (N.D. New York, 1999)
Hidden Brook Air, Inc. v. Thabet Aviation International Inc.
241 F. Supp. 2d 246 (S.D. New York, 2002)
Crawford v. Franklin Credit Management Corp.
758 F.3d 473 (Second Circuit, 2014)
Jones v. Cunard Steam Ship Co.
238 A.D. 172 (Appellate Division of the Supreme Court of New York, 1933)
Corinno Civetta Construction Corp. v. City of New York
493 N.E.2d 905 (New York Court of Appeals, 1986)
Bovis Lend Lease LMB Inc. v. GCT Venture, Inc.
6 A.D.3d 228 (Appellate Division of the Supreme Court of New York, 2004)
LaSalle Bank National Ass'n v. Nomura Asset Capital Corp.
47 A.D.3d 103 (Appellate Division of the Supreme Court of New York, 2007)
Ashkenazi v. Kent South Associates, LLC
51 A.D.3d 611 (Appellate Division of the Supreme Court of New York, 2008)

Cite This Page — Counsel Stack

Bluebook (online)
The Pike Company, Inc. v. Tri-Krete Limited, Counsel Stack Legal Research, https://law.counselstack.com/opinion/the-pike-company-inc-v-tri-krete-limited-nywd-2025.