American Bronze Corp. v. Streamway Products

456 N.E.2d 1295, 8 Ohio App. 3d 223, 8 Ohio B. 295, 37 U.C.C. Rep. Serv. (West) 687, 1982 Ohio App. LEXIS 11256
CourtOhio Court of Appeals
DecidedDecember 16, 1982
Docket44828
StatusPublished
Cited by44 cases

This text of 456 N.E.2d 1295 (American Bronze Corp. v. Streamway Products) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
American Bronze Corp. v. Streamway Products, 456 N.E.2d 1295, 8 Ohio App. 3d 223, 8 Ohio B. 295, 37 U.C.C. Rep. Serv. (West) 687, 1982 Ohio App. LEXIS 11256 (Ohio Ct. App. 1982).

Opinion

Pryatel, C.J.

This appeal arises solely from a counterclaim brought by defendant-appellant, Streamway Products, alleging that the plaintiff-appellee, American Bronze Corporation, 1 breached its contract to produce certain equipment for defendant Streamway.'The case was tried to the court which, on the basis of the evidence heard, entered the following Findings of Fact and Conclusions of Law:

Findings of Fact

“ 1. The parties stipulated to the sum of Nine Thousand Four Hundred Eighty-nine Dollars and Sixty-four Cents ($9,489.64), due on account as alleged by American in its Complaint.
“2. Purchase Order No. B 03210, (Streamway’s Exhibit A) dated November 21, 1979, was sent to American confirming a telephone order for same. American accepted said Purchase Order and produced all of the #108-R castings ordered, but refused to deliver the one thousand (1,000) #961-IH castings which were ordered. Streamway was notified of American’s refusal to produce said castings on January 24, 1981 [sic].
“3. Purchase Order No. C 1029, (Streamway’s Exhibit B) dated December 27, 1979, was sent to American confirming a telephone order for same. American accepted said Purchase Order requiring the production of thirteen thousand (13,000) #13789-R castings. American partially performed on said order deliving [sic] five thousand eighty-seven (5,087) of the castings ordered, but American refused to deliver the remaining seven thousand nine hundred thirteen (7,913) castings outstanding. Streamway was notified of American’s refusal to produce said castings on January 24, 1980.
“4. Purchase Order No. C 1036, (Streamway’s Exhibit C), dated January 3,1980, was sent to American confirming a telephone order for same. American accepted said order but then failed to deliver any of the three (3) types of castings ordered. Streamway was notified of American’s refusal to produce said castings on January 24, 1980.
“5. Purchase Order No. C1076 (Streamway’s Exhibit D), dated January 14, 1980, was sent to American confirming a telephone order for same. American on January 18, 1980, returned said order refusing to produce the requested castings.
“6. On January 17, 1980, Gerald Goldstein (Goldstein), American’s Vice-President, in a telephone conversation, informed Ronald Varesco (Varesco), Streamway’s Plant Manager and Joseph DiGiacomo (DiGiacomo), Streamway’s *225 President, that American would no longer accept new Purchase Orders from Streamway but that American would produce all open orders then in existence. 2
“7. On January 24, 1980, in a telephone conversation between Goldstein and Varesco, Goldstein informed Varesco that American would not produce the castings which were on open order with Streamway, and in addition, that American had melted down any of the castings which had been produced for said open orders.
“8. As a result of American’s refusal to produce the castings on open order, Streamway placed orders with Wolverine Brass Works in Grand Rapids, Michigan, for cover for said castings. These orders were reflected in Purchase Order Nos. C 1092; C 1089; C 1134; C 1126; and C 1090 (Streamway’s Exhibits, E, F, G, H, and I respectively.)
“9. The difference in price which Streamway had to pay for cover of those items which American refused to produce was Sixteen Thousand Three Hundred and One Dollars and Thirty Cents ($16,301.30). The cost to Streamway in converting castings #1108 to castings #108 which American refused to produce was Two Thousand Three Hundred Seventy-four Dollars and Eleven Cents ($2,374.11). The cost of retooling due to American’s refusal to produce various castings which'had been on open order was Two Thousand Nine Hundred and Seventy Dollars ($2,970.00). Other miscellaneous costs incurred by Stream-way as [sic] result of American’s refusal to produce the castings on open order was Three Thousand Five Hundred Dollars ($3,500.00). The total cost incurred by Streamway as a result of American’s action was Twenty-five Thousand One Hundred Forty-five Dollars and Forty-one Cents ($25,145.41).
“10. None of Streamway’s active and running tooling was removed from American’s foundry until American refused to produce the castings on open order on January 24, 1980.
“11. American was the only supplier to Streamway for the castings at issue in this case, and Streamway’s castings were unique and were custom made by American. There was no duplication of tooling with another foundry.
“12. Streamway did not cancel its open orders with American.
“13. American requested adequate assurances from Streamway in order to continue production of castings. The assurances requested were bringing their account current, paying future invoices within ten (10) days, arriving at an agreed price for scrap returned, and holding American harmless for any failure to produce the castings. Streamway, on January 18,1980, delivered a check in excess of Sixty-six Thousand Dollars ($66,000.00), which brought its account current with American.
“14. In the normal course of dealing Streamway would call in orders to American and then confirm same in writing with a purchase order.
“15. American accepted the purchase orders at issue.
“16. All exhibits presented were found to be admissible into evidence.
“Conclusions of Law
“1. .American is due the sum of Nine Thousand Four Hundred Eighty-nine Dollars and Sixty-four Cents ($9,489.64), on account with statutory interest at the rate of eight percent (8%) per annum beginning December 3, 1981.
“2. It was not a commercially unreasonable period of time, from November 21, 1979, to January 24, 1980, for American to unilaterally rescind its ac *226 ceptance of part of Purchase Order No. B 03210, and therefore, there was no breach of contract.
“3. It was not a commercially unreasonable period of time, from December 27, 1979, to January 24, 1980, for American to unilaterally rescind its acceptance of part of Purchase Order No. C 1029, and therefore, there was no breach of contract.
“4. It was not a commercially unreasonable period of time from January 3, 1980, to January 24, 1980, for American to unilaterally rescind its acceptance of Purchase Order No. 1036, and therefore there was no breach of contract.
“5. American received adequate assurances from Streamway in the form of full payment on account on January 18, 1980, however, American was still justified in unilaterally rescinding the three above mentioned purchase orders on January 24, 1980.
“6. There being no breach of contract, Stream way has no damages.
“7.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

JLP-Orange, L.L.C. v. Tuller Square Northpointe, L.L.C.
2024 Ohio 2236 (Ohio Court of Appeals, 2024)
ZUZEL v. SEPTA
E.D. Pennsylvania, 2021
Espyville of Pennsylvania, L.L.C. v. Ron-Bon, Inc.
2016 Ohio 1304 (Ohio Court of Appeals, 2016)
Spoerke v. Abruzzo
2014 Ohio 1362 (Ohio Court of Appeals, 2014)
Jatsek Constr., Co., Inc. v. Burton Scot Contrs., L.L.C.
2012 Ohio 3966 (Ohio Court of Appeals, 2012)
SEC America, LLC v. Marine Electric Systems, Inc.
2011 VT 125 (Supreme Court of Vermont, 2011)
State v. Calloway
2011 Ohio 4257 (Ohio Court of Appeals, 2011)
Doral Steel, Inc. v. Gray Metal Products, Inc.
672 F. Supp. 2d 798 (N.D. Ohio, 2009)
Mihelich v. Active Plumbing Supply Co., 90965 (5-14-2009)
2009 Ohio 2248 (Ohio Court of Appeals, 2009)

Cite This Page — Counsel Stack

Bluebook (online)
456 N.E.2d 1295, 8 Ohio App. 3d 223, 8 Ohio B. 295, 37 U.C.C. Rep. Serv. (West) 687, 1982 Ohio App. LEXIS 11256, Counsel Stack Legal Research, https://law.counselstack.com/opinion/american-bronze-corp-v-streamway-products-ohioctapp-1982.