Jatsek Constr., Co., Inc. v. Burton Scot Contrs., L.L.C.
Opinion
Court of Appeals of Ohio
EIGHTH APPELLATE DISTRICT COUNTY OF CUYAHOGA
JOURNAL ENTRY AND OPINION No. 98142
JATSEK CONSTRUCTION CO., INC.
PLAINTIFF-APPELLEE
vs.
BURTON SCOT CONTRACTORS, LLC, ET AL.
DEFENDANTS-APPELLANTS
JUDGMENT:
REVERSED AND REMANDED
Civil Appeal from the
Cuyahoga County Court of Common Pleas Case No. CV-758171
BEFORE: Jones, J., Blackmon, A.J., and Boyle, J.
RELEASED AND JOURNALIZED: August 30, 2012 ATTORNEYS FOR APPELLANTS
Andrew J. Natale Philip J. Truax Frantz Ward LLP 2500 Key Center 127 Public Square Cleveland, Ohio 44114
ATTORNEYS FOR APPELLEES For Jatsek Construction Co.
John R. Christie Stafanik & Christie 1375 East Ninth Street, Suite 2450 Cleveland, Ohio 44114
City of Warren
James A. Climer Mazanec, Raskin & Ryder Co, L.P.A. 100 Franklin’s Row 34305 Solon Road Solon, Ohio 44139
For Cuyahoga County
Colleen Majeski Assistant County Prosecutor Justice Center, 9th Floor 1200 Ontario Street Cleveland, Ohio 44113
For Lorain County
Daniel F. Petticord Lorain County Prosecutors Office 225 Court Street, 3rd Floor Elyria, Ohio 44035
LARRY A. JONES, SR., J.:
{¶1} This case came to be heard upon the accelerated calendar pursuant to App.R.
11.1 and Loc.R. 11.1.
{¶2} Defendants-appellants, Burton Scot Contractors, L.L.C. and Westfield Insurance Company (collectively “Burton Scot”) appeal from the trial court’s judgment denying Burton Scot’s motion to stay proceedings pending arbitration. We reverse and remand.
I. Procedural History and Facts
{¶3} In June 2011, plaintiff-appellee Jatsek Construction Company, Inc. initiated this action against the Burton Scot defendants and three other defendants: Cuyahoga County, Lorain County, and the city of Warren. According to the complaint, Burton Scot was the general contractor for three separate public improvement projects. The first project was for the resurfacing of Russia Road in Lorain County; the second project was for the resurfacing of Usher Road in Cuyahoga County; and the third project was for work to be completed for the Greenway bike trail (“Greenway project”) in the city of Warren. The Greenway project is the subject of this appeal.
A. Jatsek’s Complaint Against Burton Scot Relative to the Greenway Project
{¶4} According to Jatsek’s complaint, it was contacted by Burton Scot to submit a subcontractor bid for the Greenway project. Jatsek submitted a bid, but Burton Scot informed the company that it was attempting to find a different contractor for the work. Jatsek’s complaint further alleged that Burton Scot contacted Jatsek again and submitted a proposed subcontract agreement for some, but not all, of the work previously bid on by Jatsek.
{¶5} Jatsek alleged that it informed Burton Scot that, because of the lapse of time from the initial discussions to the proposed amended contract, it was “unable to perform the tasks as originally bid.” Complaint, ¶ 40. According to Jatsek’s complaint, “Burton Scot requested that Jatsek perform whatever duties it was able to, with the understanding that the bid prices for the work performed would be honored.” Id. at ¶ 41.
{¶6} The complaint alleged that Jatsek modified the proposed subcontract and submitted it to Burton Scot. “Jatsek did complete the tasks it agreed to in the modified subcontract agreement, although Burton Scot never executed the document and thus no contract was ever formed.” Id. at ¶ 43. Jatsek further alleged that it was not paid for its work. According to Jatsek, it “understood, by the acts, words, and deeds of Burton Scot that it would be paid the unit prices as set forth in the original bid and in the various proposed subcontracts.” Id. at ¶ 44.
B. Burton Scot’s Answer and Motion to Stay
{¶7} Burton Scot answered, and relative to the Greenway project, admitted that Jatsek performed work on the project, but had not been paid. In its motion to stay proceedings pending arbitration, Burton Scot contended that the subcontract agreement required mandatory and binding arbitration. Burton Scot submitted the affidavit of its vice president in support of the motion to stay. The vice president averred that on May 26, 2010, Jatsek submitted a bid proposal for the Greenway project, Burton Scot accepted the bid on August 5, 2010, and issued the written contract for the project to Jatsek on September 17, 2010.
{¶8} The vice president further averred that Jatsek began working at the Greenway project on October 18, 2010, and on October 30, 2010, issued its first invoice for work performed on the project. According to the vice president, on November 7, 2010, Jatsek executed and returned the written contract. In executing the contract, however, Jatsek made handwritten modifications to certain provisions in the contract. The vice president averred that those modifications were not acceptable to Burton Scot and Burton Scot did not consent in writing to them.
{¶9} Burton Scot also submitted the written contract in support of its motion to stay. Paragraph 31 of the contract provided in relevant part as follows:
At the sole option of Contractor, any and all claims, disputes, controversies, demands, and causes of action of whatever nature, kind or description arising from or relating to this Agreement, including without limitation contract, equity, tort or legal claims, and further including without limitation claims relating to rights of payment or interpretations hereof, shall be submitted to mandatory and binding arbitration in the Cleveland Tribunal of the American Arbitration Association in accordance with the Construction Industry Arbitration Rules of the American Arbitration Association. The decision and Award of the Arbitrator(s) shall be final and binding on Contractor and Subcontractor, and the decision and Award may be reduced to judgment and enforced in any Court of competent jurisdiction.
{¶10} The contract was signed and dated (November 7, 2010) by Jatsek’s vice president, but was not signed by a Burton Scot representative. The contract had handwritten changes, but not to the arbitration provision.
{¶11} Jatsek opposed the motion to stay. The company argued that Burton Scot never executed the agreement, but even if a contract was formed, Jatsek was entitled to judgment because there was no dispute that it performed the work agreed to under the contract, but had not been paid.
{¶12} The trial court ruled that no contract existed for the Greenway project. The motion for stay was therefore denied as it related to that project.1 For its sole assigned error, Burton Scot contends that: “The trial court erred as a matter of law in denying Appellant Burton Scot Contractors, LLC’s Motion to Stay Proceedings Pending Arbitration as it relates to the City of Warren Greenway Bike Trail public improvement project in Warren, Ohio.”
II. Law and Analysis
{¶13} Burton Scot notes that there is a split of authority on whether this court’s standard of review is abuse of discretion or de novo. Burton Scot contends that the split is “immaterial” to this case because reversal is required under either standard. Jatsek, on the other hand, contends that this court has “consistently reviewed the denial of a motion to stay proceedings under an abuse of discretion standard.”
{¶14} In McCaskey v. Sanford-Brown College, 8th Dist. No. 97261, 2012-Ohio-1543, this court recently held that the standard of review in these type of cases depends on the type of question raised regarding the applicability of the arbitration
1 A stay was granted, however, relative to the other two projects. Jatsek had also filed a motion for partial summary judgment relative to the Greenway project, which the trial court granted. That portion of the trial court’s judgment is not a final appealable order and therefore is not now before this court.
Free access — add to your briefcase to read the full text and ask questions with AI
2012 Ohio 3966 (Jatsek Constr., Co., Inc. v. Burton Scot Contrs., L.L.C.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.