Jatsek Constr., Co., Inc. v. Burton Scot Contrs., L.L.C.

2012 Ohio 3966
CourtOhio Court of Appeals
DecidedAugust 30, 2012
Docket98142
StatusPublished
Cited by6 cases

This text of 2012 Ohio 3966 (Jatsek Constr., Co., Inc. v. Burton Scot Contrs., L.L.C.) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Jatsek Constr., Co., Inc. v. Burton Scot Contrs., L.L.C., 2012 Ohio 3966 (Ohio Ct. App. 2012).

Opinion

[Cite as Jatsek Constr., Co., Inc. v. Burton Scot Contrs., L.L.C., 2012-Ohio-3966.]

Court of Appeals of Ohio EIGHTH APPELLATE DISTRICT COUNTY OF CUYAHOGA

JOURNAL ENTRY AND OPINION No. 98142

JATSEK CONSTRUCTION CO., INC. PLAINTIFF-APPELLEE

vs.

BURTON SCOT CONTRACTORS, LLC, ET AL. DEFENDANTS-APPELLANTS

JUDGMENT: REVERSED AND REMANDED

Civil Appeal from the Cuyahoga County Court of Common Pleas Case No. CV-758171

BEFORE: Jones, J., Blackmon, A.J., and Boyle, J.

RELEASED AND JOURNALIZED: August 30, 2012

ATTORNEYS FOR APPELLANTS Andrew J. Natale Philip J. Truax Frantz Ward LLP 2500 Key Center 127 Public Square Cleveland, Ohio 44114

ATTORNEYS FOR APPELLEES

For Jatsek Construction Co.

John R. Christie Stafanik & Christie 1375 East Ninth Street, Suite 2450 Cleveland, Ohio 44114

City of Warren

James A. Climer Mazanec, Raskin & Ryder Co, L.P.A. 100 Franklin’s Row 34305 Solon Road Solon, Ohio 44139

For Cuyahoga County

Colleen Majeski Assistant County Prosecutor Justice Center, 9th Floor 1200 Ontario Street Cleveland, Ohio 44113

For Lorain County

Daniel F. Petticord Lorain County Prosecutors Office 225 Court Street, 3rd Floor Elyria, Ohio 44035 LARRY A. JONES, SR., J.:

{¶1} This case came to be heard upon the accelerated calendar pursuant to App.R.

11.1 and Loc.R. 11.1.

{¶2} Defendants-appellants, Burton Scot Contractors, L.L.C. and Westfield

Insurance Company (collectively “Burton Scot”) appeal from the trial court’s judgment

denying Burton Scot’s motion to stay proceedings pending arbitration. We reverse and

remand.

I. Procedural History and Facts

{¶3} In June 2011, plaintiff-appellee Jatsek Construction Company, Inc. initiated

this action against the Burton Scot defendants and three other defendants: Cuyahoga

County, Lorain County, and the city of Warren. According to the complaint, Burton Scot

was the general contractor for three separate public improvement projects. The first

project was for the resurfacing of Russia Road in Lorain County; the second project was

for the resurfacing of Usher Road in Cuyahoga County; and the third project was for work

to be completed for the Greenway bike trail (“Greenway project”) in the city of Warren.

The Greenway project is the subject of this appeal.

A. Jatsek’s Complaint Against Burton Scot Relative to the Greenway Project

{¶4} According to Jatsek’s complaint, it was contacted by Burton Scot to submit a

subcontractor bid for the Greenway project. Jatsek submitted a bid, but Burton Scot

informed the company that it was attempting to find a different contractor for the work.

Jatsek’s complaint further alleged that Burton Scot contacted Jatsek again and submitted a proposed subcontract agreement for some, but not all, of the work previously bid on by

Jatsek.

{¶5} Jatsek alleged that it informed Burton Scot that, because of the lapse of time

from the initial discussions to the proposed amended contract, it was “unable to perform

the tasks as originally bid.” Complaint, ¶ 40. According to Jatsek’s complaint, “Burton

Scot requested that Jatsek perform whatever duties it was able to, with the understanding

that the bid prices for the work performed would be honored.” Id. at ¶ 41.

{¶6} The complaint alleged that Jatsek modified the proposed subcontract and

submitted it to Burton Scot. “Jatsek did complete the tasks it agreed to in the modified

subcontract agreement, although Burton Scot never executed the document and thus no

contract was ever formed.” Id. at ¶ 43. Jatsek further alleged that it was not paid for

its work. According to Jatsek, it “understood, by the acts, words, and deeds of Burton

Scot that it would be paid the unit prices as set forth in the original bid and in the various

proposed subcontracts.” Id. at ¶ 44.

B. Burton Scot’s Answer and Motion to Stay

{¶7} Burton Scot answered, and relative to the Greenway project, admitted that

Jatsek performed work on the project, but had not been paid. In its motion to stay

proceedings pending arbitration, Burton Scot contended that the subcontract agreement

required mandatory and binding arbitration. Burton Scot submitted the affidavit of its

vice president in support of the motion to stay. The vice president averred that on May

26, 2010, Jatsek submitted a bid proposal for the Greenway project, Burton Scot accepted the bid on August 5, 2010, and issued the written contract for the project to Jatsek on

September 17, 2010.

{¶8} The vice president further averred that Jatsek began working at the Greenway

project on October 18, 2010, and on October 30, 2010, issued its first invoice for work

performed on the project. According to the vice president, on November 7, 2010, Jatsek

executed and returned the written contract. In executing the contract, however, Jatsek

made handwritten modifications to certain provisions in the contract. The vice president

averred that those modifications were not acceptable to Burton Scot and Burton Scot did

not consent in writing to them.

{¶9} Burton Scot also submitted the written contract in support of its motion to

stay. Paragraph 31 of the contract provided in relevant part as follows:

At the sole option of Contractor, any and all claims, disputes, controversies, demands, and causes of action of whatever nature, kind or description arising from or relating to this Agreement, including without limitation contract, equity, tort or legal claims, and further including without limitation claims relating to rights of payment or interpretations hereof, shall be submitted to mandatory and binding arbitration in the Cleveland Tribunal of the American Arbitration Association in accordance with the Construction Industry Arbitration Rules of the American Arbitration Association. The decision and Award of the Arbitrator(s) shall be final and binding on Contractor and Subcontractor, and the decision and Award may be reduced to judgment and enforced in any Court of competent jurisdiction.

{¶10} The contract was signed and dated (November 7, 2010) by Jatsek’s vice

president, but was not signed by a Burton Scot representative. The contract had

handwritten changes, but not to the arbitration provision.

{¶11} Jatsek opposed the motion to stay. The company argued that Burton Scot never executed the agreement, but even if a contract was formed, Jatsek was entitled to

judgment because there was no dispute that it performed the work agreed to under the

contract, but had not been paid.

{¶12} The trial court ruled that no contract existed for the Greenway project. The

motion for stay was therefore denied as it related to that project.1 For its sole assigned

error, Burton Scot contends that: “The trial court erred as a matter of law in denying

Appellant Burton Scot Contractors, LLC’s Motion to Stay Proceedings Pending

Arbitration as it relates to the City of Warren Greenway Bike Trail public improvement

project in Warren, Ohio.”

II. Law and Analysis

{¶13} Burton Scot notes that there is a split of authority on whether this court’s

standard of review is abuse of discretion or de novo. Burton Scot contends that the split

is “immaterial” to this case because reversal is required under either standard. Jatsek, on

the other hand, contends that this court has “consistently reviewed the denial of a motion

to stay proceedings under an abuse of discretion standard.”

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
2012 Ohio 3966, Counsel Stack Legal Research, https://law.counselstack.com/opinion/jatsek-constr-co-inc-v-burton-scot-contrs-llc-ohioctapp-2012.