Frank Novak & Sons, Inc. v. A-Team, L.L.C.

2014 Ohio 922
CourtOhio Court of Appeals
DecidedMarch 13, 2014
Docket99777
StatusPublished
Cited by2 cases

This text of 2014 Ohio 922 (Frank Novak & Sons, Inc. v. A-Team, L.L.C.) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Frank Novak & Sons, Inc. v. A-Team, L.L.C., 2014 Ohio 922 (Ohio Ct. App. 2014).

Opinion

[Cite as Frank Novak & Sons, Inc. v. A-Team, L.L.C., 2014-Ohio-922.]

Court of Appeals of Ohio EIGHTH APPELLATE DISTRICT COUNTY OF CUYAHOGA

JOURNAL ENTRY AND OPINION No. 99777

FRANK NOVAK & SONS, INC. PLAINTIFF-APPELLEE/ CROSS-APPELLANT

vs.

A-TEAM, L.L.C., D.B.A. SERVICEMASTER DEFENDANT-APPELLANT/ CROSS-APPELLEE

JUDGMENT: AFFIRMED IN PART, REVERSED IN PART, AND REMANDED

Civil Appeal from the Cuyahoga County Court of Common Pleas Case No. CV-09-685057

BEFORE: Boyle, A.J., E.A. Gallagher, J., and Blackmon, J.

RELEASED AND JOURNALIZED: March 13, 2014 ATTORNEY FOR APPELLANT

Kevin J. Kelley Porter Wright Morris & Arthur 925 Euclid Avenue Suite 1700 Cleveland, Ohio 44115

ATTORNEYS FOR APPELLEE

Keith R. Kraus Grant J. Keating Dworken & Bernstein Co., L.P.A. 50 South Park Place Painesville, Ohio 44077 MARY J. BOYLE, A.J.:

{¶1} Defendant-appellant, A-Team, L.L.C., d.b.a. ServiceMaster

(“ServiceMaster”) appeals the trial court’s judgment in favor of plaintiff-appellee, Frank

Novak & Sons, Inc. (“Novak”) on Novak’s breach of contract claim and ServiceMaster’s

counterclaims for breach of contract and unjust enrichment. Novak also cross-appeals,

challenging the trial court’s judgment with respect to its claim under R.C. 4113.61 (“Ohio’s

Prompt Payment Act”). We affirm the trial court’s award in favor of Novak on its breach

of contract claim, reverse the trial court on its application of the Prompt Payment Act, and

remand for further proceedings.

Procedural History and Facts

{¶2} This case involves a dispute between a general contractor and subcontractor

related to work performed in the summer of 2007 to restore the Cleveland Browns Stadium

(the “Property”) in time for the Browns’ first pre-season game. On July 14, 2007, during a

concert, the Property sustained severe water damage because of faulty plumbing. The

next day, ServiceMaster was hired as the general contractor to perform cleaning,

restoration, and construction for the Property. ServiceMaster, in turn, hired Novak as a

subcontractor to perform painting, flooring, and wall covering work. While the parties

were performing work related to the July 14th incident, a severe rainstorm occurred on

August 2, 2007, causing further damage to the Property, and resulting in Novak performing

additional work. {¶3} Novak brought the underlying action seeking to recover money allegedly

owed by ServiceMaster in connection with work Novak performed for the August 2, 2007

project. Novak further sought to separately recover prejudgment interest and attorney fees

under R.C. 4113.61, Ohio’s Prompt Payment Act, for ServiceMaster’s alleged failure to

timely pay after having received payment itself.

{¶4} The parties disputed the nature of the contract that governed, and both parties

ultimately changed their respective positions during the course of the litigation. While

Novak initially asserted that the parties entered into a “subcontractor agreement” and

attached a written subcontractor agreement to the complaint, Novak changed its position

and filed an amended complaint, asserting that the parties “entered into an oral agreement.”

Conversely, ServiceMaster initially answered the complaint and responded to requests for

admissions, denying that the subcontractor agreement was the contract between the parties.

It then, however, amended its answer to state that the parties entered into a written

subcontractor agreement — the same subcontractor agreement attached to Novak’s original

complaint (“subcontractor agreement”).

{¶5} After Novak filed its second amended complaint, ServiceMaster answered

and asserted two counterclaims for breach of contract and unjust enrichment.

ServiceMaster alleges that all the work performed by Novak was governed by the single

written subcontractor agreement, signed by ServiceMaster’s president, Ed Ranieri.

ServiceMaster alleged that the severe rain of August 2, 2007, resulted in an expanded scope

of work but that the parties agreed that Novak would continue to provide flooring and painting services “under the terms of their agreement.” ServiceMaster further alleged that

Novak “breached this agreement as it has been paid substantially more than what is

provided in their agreement.” ServiceMaster’s claim is based on two specific provisions

in the subcontractor agreement — (1) “an administrative fee provision” providing that all

payments are subject to a 20 percent administrative fee, and (2) “a pay when paid

provision” providing that Novak will be paid when ServiceMaster has received payment

from the property owner, the property owner’s agent and/or the relevant insurance

company.

{¶6} In support of its unjust enrichment claim, ServiceMaster alleged that it made

payments to Novak totaling $430,000 and that Novak negotiated an additional payment of

$100,450 directly from the Cleveland Browns, of which it never informed ServiceMaster.

Based on these collective payments, ServiceMaster alleged that Novak has been overpaid

for its work on the Property and that “it would be unjust for [Novak] to retain this benefit.”

{¶7} The case ultimately proceeded to a bench trial.

{¶8} Novak presented documentary evidence establishing that ServiceMaster

entered into separate contracts with the property owner’s agent to perform restoration work

on the Property in response to the pipe–sewer backup of July 14th (“Loss 1”) and the

rainwater intrusion on August 2nd (“Loss 2”).

{¶9} Bradley Pinchot, vice president of Novak, testified that his company was

hired by ServiceMaster to perform services related to both Loss 1 and Loss 2, but that Loss

1 and Loss 2 were two separate projects. Pinchot expressly denied that Loss 2 was an extension of the scope of work under Loss 1. According to Pinchot, ServiceMaster

specifically required Novak to distinguish from the work it performed with respect to Loss

1 and Loss 2 because they were two separate projects.

{¶10} With respect to Loss 2, Pinchot testified that Novak had an oral contract with

ServiceMaster to perform the work. Specifically, Pinchot testified that he entered into an

oral contract with Pete D’Agostino, a project executive from ServiceMaster, for Novak to

perform the work on Loss 2 and that ServiceMaster would pay on a “time and material

basis.”

{¶11} Pinchot further testified that he had received the subcontractor agreement

“two or three weeks after” Novak commenced work at the stadium. Pinchot stated that he

never signed or approved the terms. With respect to the administrative fee provision in

the subcontractor agreement, Pinchot testified that the 20 percent administrative fee “is

actually more than what is in [Novak’s] billing rate for allowable overhead and profit,” and

therefore Novak never agreed to the agreement. Pinchot explained that Novak would

have lost money from day one if it agreed to the subcontractor agreement so “we didn’t

execute it for that reason.” Pinchot further explained that Novak pulled its people from

other jobs to work on Loss 1 and that it never would have pulled labor off other paying jobs

to work on another job that Novak would lose money from the inception.

{¶12} Novak submitted invoices totaling $535,000 for flooring work performed on

Loss 1. It is undisputed that Novak received $430,000 in payment from ServiceMaster.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Atlas Piers NEO v. Summit Constr. Co., Inc.
2021 Ohio 2024 (Ohio Court of Appeals, 2021)
Xtreme Elements, L.L.C. v. Foti Contracting, L.L.C.
2018 Ohio 3323 (Ohio Court of Appeals, 2018)

Cite This Page — Counsel Stack

Bluebook (online)
2014 Ohio 922, Counsel Stack Legal Research, https://law.counselstack.com/opinion/frank-novak-sons-inc-v-a-team-llc-ohioctapp-2014.