Masiongale Electrical-Mechanical, Inc. v. Construction One, Inc.

102 Ohio St. 3d 1
CourtOhio Supreme Court
DecidedApril 21, 2004
DocketNo. 2002-1861
StatusPublished
Cited by11 cases

This text of 102 Ohio St. 3d 1 (Masiongale Electrical-Mechanical, Inc. v. Construction One, Inc.) is published on Counsel Stack Legal Research, covering Ohio Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Masiongale Electrical-Mechanical, Inc. v. Construction One, Inc., 102 Ohio St. 3d 1 (Ohio 2004).

Opinions

O’Donnell, J.

{¶ 1} In this ease, we are called upon to interpret R.C. 4113.61, known as the Prompt-Payment Act, with respect to a contractor’s right to withhold payment from a subcontractor. Construction One, Inc. appeals from a judgment of the Franklin County Court of Appeals, which affirmed the judgment of the common pleas court to award Masiongale Electrical-Mechanical, Inc. attorney fees and prejudgment interest as a result of Construction One’s noncompliance with R.C. 4113.61. Because Masiongale’s breaches of the lien-waiver and forum-selection clauses in the subcontract did not create “disputed liens or claims involving the work or labor performed or material furnished by the subcontractor,” it was improper for Construction One to withhold payment relating to those disputes, and, therefore, we affirm the judgment of the court of appeals.

I

{¶ 2} Construction One, a general contractor, subcontracted with Masiongale for electrical, plumbing, heating, ventilating, and air-conditioning work on a construction project involving an American Eagle Outfitters store in Muncie, [2]*2Indiana. After Masiongale requested payment for its completed work, Construction One sought a $7,021 reduction of the contract price from $36,124 to $29,103, claiming that Masiongale had untimely and improperly performed its work.

{¶ 3} In response, Masiongale, in violation of a specific contractual provision, filed a lien on the property, thereby forcing Construction One to remove the lien by posting a bond pursuant to its contract with American Eagle Outfitters. Masiongale also sued Construction One in the Superior Court of Delaware County, Indiana, alleging breach of contract and seeking to foreclose on its lien. The Indiana court dismissed the breach-of-contract claim, finding that Masiongale had breached a forum-selection clause in the contract requiring all litigation to occur in Franklin County, Ohio, but the court held the foreclosure action in abeyance.

{¶ 4} Thereafter, Masiongale filed a complaint in the Franklin County Court of Common Pleas, alleging breach of contract for nonpayment. Construction One counterclaimed, asserting that Masiongale had breached the contract by failing to timely and adequately perform the work and by violating the lien-waiver and forum-selection clauses.

{¶ 5} The court referred the matter to a magistrate, who found that Construction One owed Masiongale $35,349.05, after deducting back charges of $774.95. The magistrate also determined that Construction One had violated the PrompfiPayment Act, R.C. 4113.61, by improperly withholding $29,103 and, therefore, awarded Masiongale prejudgment interest on that amount as well as $31,624.62 in attorney fees.

{¶ 6} Regarding Construction One’s counterclaims, the magistrate found that Masiongale had breached the lien-waiver and forum-selection clauses and awarded Construction One $9,470 in damages for the premiums paid for the bond and the attorney fees expended to defend against the Indiana lawsuit, plus interest.

{¶ 7} After overruling both parties’ objections, the trial court adopted the magistrate’s decision. Masiongale did not appeal from the judgment that it had violated the lien-waiver and forum-selection clauses. Construction One appealed from the trial court’s judgment that it could not withhold the amounts of anticipated bond premiums and litigation costs directly related to resolving the improperly filed lien and Indiana lawsuit. In rejecting the argument, the appellate court held that “only direct, tangible amounts relating to disputes involving alleged faulty labor, work or materials are retainable by the contractor under R.C. 4113.61(A)(1).” After rejecting Construction One’s arguments on other issues, the appellate court affirmed the judgment.

{¶ 8} The cause is now before this court pursuant to the acceptance of a discretionary appeal.

[3]*3II

{¶ 9} The issues for this court to decide are, first, whether a breach of a lien-waiver or forum-selection clause of a construction contract creates a “disputed lien[ ] or claim[ ] involving the work or labor performed or material furnished by the subcontractor,” pursuant to R.C. 4113.61(A)(1), and, second, if they do, whether a contractor may withhold the amounts of bond premiums and attorney fees reasonably anticipated to be incurred in resolving the improperly filed lien and lawsuit.1

{¶ 10} In 1990, the Ohio General Assembly enacted prompt-payment legislation, codified at R.C. 4113.61(A)(1), which became effective on April 10, 1991.2 Am.Sub.H.B. No. 238, 143 Ohio Laws, Part III, 3676, 3723. The legislation essentially requires a contractor to timely pay its subcontractor or materialmen undisputed amounts under a contract and sets forth penalties for noncompliance. See, generally, John W. Hays, Prompt Payment Acts: Recent Developments and Trends (2002), 22 Construction Lawyer 29; Jenkins, Inc. v. Walsh Bros., Inc., 2001 ME 98, 776 A.2d 1229, ¶ 31.

{¶ 11} R.C. 4113.61(A)(1) provides:

{¶ 12} “If a subcontractor or materialman submits an application or request for payment or an invoice for materials to a contractor in sufficient time to allow the contractor to include the application, request, or invoice in his own pay request submitted to an owner, the contractor, within ten calendar days after receipt of payment from the owner for improvements to property, shall pay to the:

{¶ 13} “(a) Subcontractor, an amount that is equal to the percentage of completion of the subcontractor’s contract allowed by the owner for the amount of labor or work performed.

{¶ 14} “* * *

{¶ 15} “The contractor may reduce the amount paid by any retainage provision contained in the contract, invoice, or purchase order between the contractor and the subcontractor or materialman, and may withhold amounts that may be necessary to resolve disputed liens or claims involving the work or labor performed or material furnished by the subcontractor or materialman.”

[4]*4{¶ 16} Therefore, pursuant to R.C. 4113.61(A)(1), if a subcontractor makes a timely request for payment, a contractor must pay the subcontractor in proportion to the work completed within ten calendar days of receiving payment from the owner. A contractor, however, is permitted to withhold “amounts that may be necessary to resolve disputed liens or claims involving the work or labor performed or material furnished by the subcontractor.”

{¶ 17} Failure to comply with these provisions obligates a contractor to pay interest on the overdue payment at a rate of 18 percent per annum. R.C. 4113.61(A)(1) and (B)(1). A subcontractor also may file a civil action to recover the amount due and the statutory interest. R.C. 4113.61(B)(1). If the court determines that the contractor has not complied with the prompt-payment statute, the court must award the subcontractor the statutorily prescribed interest. Id. In addition, the prevailing party is entitled to recover reasonable attorney fees, unless such an award would be inequitable, together with court costs. R.C. 4113.61(B)(1) and (B)(3).

{¶ 18} In the present case, Construction One argues that R.C. 4113.61 permits it to withhold estimated costs of securing a lien substitute, i.e., bond premiums, and anticipated attorney fees directly relating to resolving Masiongale’s breaches of the lien-waiver and forum-selection clauses. These breaches, however, did not create “disputed liens or claims

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Xtreme Elements, L.L.C. v. Foti Contracting, L.L.C.
2018 Ohio 3323 (Ohio Court of Appeals, 2018)
H & H Glass, Inc. v. Empire Bldg. Co., L.L.C.
2016 Ohio 3029 (Ohio Court of Appeals, 2016)
Frank Novak & Sons, Inc. v. A-Team, L.L.C.
2014 Ohio 922 (Ohio Court of Appeals, 2014)
Gary Moderalli Excavating, Inc. v. Trimat Constr., Inc.
2013 Ohio 1701 (Ohio Court of Appeals, 2013)
Graves Lumber Co. v. Borkey
2009 Ohio 2786 (Ohio Court of Appeals, 2009)
Midwest Curtainwalls, Inc. v. Pinnacle 701, 90591 (10-2-2008)
2008 Ohio 5134 (Ohio Court of Appeals, 2008)
Creative Concrete v. Dg Pools, 07 Ma 163 (6-26-2008)
2008 Ohio 3338 (Ohio Court of Appeals, 2008)

Cite This Page — Counsel Stack

Bluebook (online)
102 Ohio St. 3d 1, Counsel Stack Legal Research, https://law.counselstack.com/opinion/masiongale-electrical-mechanical-inc-v-construction-one-inc-ohio-2004.