O’Donnell, J.
{¶ 1} In this ease, we are called upon to interpret R.C. 4113.61, known as the Prompt-Payment Act, with respect to a contractor’s right to withhold payment from a subcontractor. Construction One, Inc. appeals from a judgment of the Franklin County Court of Appeals, which affirmed the judgment of the common pleas court to award Masiongale Electrical-Mechanical, Inc. attorney fees and prejudgment interest as a result of Construction One’s noncompliance with R.C. 4113.61. Because Masiongale’s breaches of the lien-waiver and forum-selection clauses in the subcontract did not create “disputed liens or claims involving the work or labor performed or material furnished by the subcontractor,” it was improper for Construction One to withhold payment relating to those disputes, and, therefore, we affirm the judgment of the court of appeals.
I
{¶ 2} Construction One, a general contractor, subcontracted with Masiongale for electrical, plumbing, heating, ventilating, and air-conditioning work on a construction project involving an American Eagle Outfitters store in Muncie, [2]*2Indiana. After Masiongale requested payment for its completed work, Construction One sought a $7,021 reduction of the contract price from $36,124 to $29,103, claiming that Masiongale had untimely and improperly performed its work.
{¶ 3} In response, Masiongale, in violation of a specific contractual provision, filed a lien on the property, thereby forcing Construction One to remove the lien by posting a bond pursuant to its contract with American Eagle Outfitters. Masiongale also sued Construction One in the Superior Court of Delaware County, Indiana, alleging breach of contract and seeking to foreclose on its lien. The Indiana court dismissed the breach-of-contract claim, finding that Masiongale had breached a forum-selection clause in the contract requiring all litigation to occur in Franklin County, Ohio, but the court held the foreclosure action in abeyance.
{¶ 4} Thereafter, Masiongale filed a complaint in the Franklin County Court of Common Pleas, alleging breach of contract for nonpayment. Construction One counterclaimed, asserting that Masiongale had breached the contract by failing to timely and adequately perform the work and by violating the lien-waiver and forum-selection clauses.
{¶ 5} The court referred the matter to a magistrate, who found that Construction One owed Masiongale $35,349.05, after deducting back charges of $774.95. The magistrate also determined that Construction One had violated the PrompfiPayment Act, R.C. 4113.61, by improperly withholding $29,103 and, therefore, awarded Masiongale prejudgment interest on that amount as well as $31,624.62 in attorney fees.
{¶ 6} Regarding Construction One’s counterclaims, the magistrate found that Masiongale had breached the lien-waiver and forum-selection clauses and awarded Construction One $9,470 in damages for the premiums paid for the bond and the attorney fees expended to defend against the Indiana lawsuit, plus interest.
{¶ 7} After overruling both parties’ objections, the trial court adopted the magistrate’s decision. Masiongale did not appeal from the judgment that it had violated the lien-waiver and forum-selection clauses. Construction One appealed from the trial court’s judgment that it could not withhold the amounts of anticipated bond premiums and litigation costs directly related to resolving the improperly filed lien and Indiana lawsuit. In rejecting the argument, the appellate court held that “only direct, tangible amounts relating to disputes involving alleged faulty labor, work or materials are retainable by the contractor under R.C. 4113.61(A)(1).” After rejecting Construction One’s arguments on other issues, the appellate court affirmed the judgment.
{¶ 8} The cause is now before this court pursuant to the acceptance of a discretionary appeal.
[3]*3II
{¶ 9} The issues for this court to decide are, first, whether a breach of a lien-waiver or forum-selection clause of a construction contract creates a “disputed lien[ ] or claim[ ] involving the work or labor performed or material furnished by the subcontractor,” pursuant to R.C. 4113.61(A)(1), and, second, if they do, whether a contractor may withhold the amounts of bond premiums and attorney fees reasonably anticipated to be incurred in resolving the improperly filed lien and lawsuit.1
{¶ 10} In 1990, the Ohio General Assembly enacted prompt-payment legislation, codified at R.C. 4113.61(A)(1), which became effective on April 10, 1991.2 Am.Sub.H.B. No. 238, 143 Ohio Laws, Part III, 3676, 3723. The legislation essentially requires a contractor to timely pay its subcontractor or materialmen undisputed amounts under a contract and sets forth penalties for noncompliance. See, generally, John W. Hays, Prompt Payment Acts: Recent Developments and Trends (2002), 22 Construction Lawyer 29; Jenkins, Inc. v. Walsh Bros., Inc., 2001 ME 98, 776 A.2d 1229, ¶ 31.
{¶ 11} R.C. 4113.61(A)(1) provides:
{¶ 12} “If a subcontractor or materialman submits an application or request for payment or an invoice for materials to a contractor in sufficient time to allow the contractor to include the application, request, or invoice in his own pay request submitted to an owner, the contractor, within ten calendar days after receipt of payment from the owner for improvements to property, shall pay to the:
{¶ 13} “(a) Subcontractor, an amount that is equal to the percentage of completion of the subcontractor’s contract allowed by the owner for the amount of labor or work performed.
{¶ 14} “* * *
{¶ 15} “The contractor may reduce the amount paid by any retainage provision contained in the contract, invoice, or purchase order between the contractor and the subcontractor or materialman, and may withhold amounts that may be necessary to resolve disputed liens or claims involving the work or labor performed or material furnished by the subcontractor or materialman.”
[4]*4{¶ 16} Therefore, pursuant to R.C. 4113.61(A)(1), if a subcontractor makes a timely request for payment, a contractor must pay the subcontractor in proportion to the work completed within ten calendar days of receiving payment from the owner. A contractor, however, is permitted to withhold “amounts that may be necessary to resolve disputed liens or claims involving the work or labor performed or material furnished by the subcontractor.”
{¶ 17} Failure to comply with these provisions obligates a contractor to pay interest on the overdue payment at a rate of 18 percent per annum. R.C. 4113.61(A)(1) and (B)(1). A subcontractor also may file a civil action to recover the amount due and the statutory interest. R.C. 4113.61(B)(1). If the court determines that the contractor has not complied with the prompt-payment statute, the court must award the subcontractor the statutorily prescribed interest. Id. In addition, the prevailing party is entitled to recover reasonable attorney fees, unless such an award would be inequitable, together with court costs. R.C. 4113.61(B)(1) and (B)(3).
{¶ 18} In the present case, Construction One argues that R.C. 4113.61 permits it to withhold estimated costs of securing a lien substitute, i.e., bond premiums, and anticipated attorney fees directly relating to resolving Masiongale’s breaches of the lien-waiver and forum-selection clauses. These breaches, however, did not create “disputed liens or claims
Free access — add to your briefcase to read the full text and ask questions with AI
O’Donnell, J.
{¶ 1} In this ease, we are called upon to interpret R.C. 4113.61, known as the Prompt-Payment Act, with respect to a contractor’s right to withhold payment from a subcontractor. Construction One, Inc. appeals from a judgment of the Franklin County Court of Appeals, which affirmed the judgment of the common pleas court to award Masiongale Electrical-Mechanical, Inc. attorney fees and prejudgment interest as a result of Construction One’s noncompliance with R.C. 4113.61. Because Masiongale’s breaches of the lien-waiver and forum-selection clauses in the subcontract did not create “disputed liens or claims involving the work or labor performed or material furnished by the subcontractor,” it was improper for Construction One to withhold payment relating to those disputes, and, therefore, we affirm the judgment of the court of appeals.
I
{¶ 2} Construction One, a general contractor, subcontracted with Masiongale for electrical, plumbing, heating, ventilating, and air-conditioning work on a construction project involving an American Eagle Outfitters store in Muncie, [2]*2Indiana. After Masiongale requested payment for its completed work, Construction One sought a $7,021 reduction of the contract price from $36,124 to $29,103, claiming that Masiongale had untimely and improperly performed its work.
{¶ 3} In response, Masiongale, in violation of a specific contractual provision, filed a lien on the property, thereby forcing Construction One to remove the lien by posting a bond pursuant to its contract with American Eagle Outfitters. Masiongale also sued Construction One in the Superior Court of Delaware County, Indiana, alleging breach of contract and seeking to foreclose on its lien. The Indiana court dismissed the breach-of-contract claim, finding that Masiongale had breached a forum-selection clause in the contract requiring all litigation to occur in Franklin County, Ohio, but the court held the foreclosure action in abeyance.
{¶ 4} Thereafter, Masiongale filed a complaint in the Franklin County Court of Common Pleas, alleging breach of contract for nonpayment. Construction One counterclaimed, asserting that Masiongale had breached the contract by failing to timely and adequately perform the work and by violating the lien-waiver and forum-selection clauses.
{¶ 5} The court referred the matter to a magistrate, who found that Construction One owed Masiongale $35,349.05, after deducting back charges of $774.95. The magistrate also determined that Construction One had violated the PrompfiPayment Act, R.C. 4113.61, by improperly withholding $29,103 and, therefore, awarded Masiongale prejudgment interest on that amount as well as $31,624.62 in attorney fees.
{¶ 6} Regarding Construction One’s counterclaims, the magistrate found that Masiongale had breached the lien-waiver and forum-selection clauses and awarded Construction One $9,470 in damages for the premiums paid for the bond and the attorney fees expended to defend against the Indiana lawsuit, plus interest.
{¶ 7} After overruling both parties’ objections, the trial court adopted the magistrate’s decision. Masiongale did not appeal from the judgment that it had violated the lien-waiver and forum-selection clauses. Construction One appealed from the trial court’s judgment that it could not withhold the amounts of anticipated bond premiums and litigation costs directly related to resolving the improperly filed lien and Indiana lawsuit. In rejecting the argument, the appellate court held that “only direct, tangible amounts relating to disputes involving alleged faulty labor, work or materials are retainable by the contractor under R.C. 4113.61(A)(1).” After rejecting Construction One’s arguments on other issues, the appellate court affirmed the judgment.
{¶ 8} The cause is now before this court pursuant to the acceptance of a discretionary appeal.
[3]*3II
{¶ 9} The issues for this court to decide are, first, whether a breach of a lien-waiver or forum-selection clause of a construction contract creates a “disputed lien[ ] or claim[ ] involving the work or labor performed or material furnished by the subcontractor,” pursuant to R.C. 4113.61(A)(1), and, second, if they do, whether a contractor may withhold the amounts of bond premiums and attorney fees reasonably anticipated to be incurred in resolving the improperly filed lien and lawsuit.1
{¶ 10} In 1990, the Ohio General Assembly enacted prompt-payment legislation, codified at R.C. 4113.61(A)(1), which became effective on April 10, 1991.2 Am.Sub.H.B. No. 238, 143 Ohio Laws, Part III, 3676, 3723. The legislation essentially requires a contractor to timely pay its subcontractor or materialmen undisputed amounts under a contract and sets forth penalties for noncompliance. See, generally, John W. Hays, Prompt Payment Acts: Recent Developments and Trends (2002), 22 Construction Lawyer 29; Jenkins, Inc. v. Walsh Bros., Inc., 2001 ME 98, 776 A.2d 1229, ¶ 31.
{¶ 11} R.C. 4113.61(A)(1) provides:
{¶ 12} “If a subcontractor or materialman submits an application or request for payment or an invoice for materials to a contractor in sufficient time to allow the contractor to include the application, request, or invoice in his own pay request submitted to an owner, the contractor, within ten calendar days after receipt of payment from the owner for improvements to property, shall pay to the:
{¶ 13} “(a) Subcontractor, an amount that is equal to the percentage of completion of the subcontractor’s contract allowed by the owner for the amount of labor or work performed.
{¶ 14} “* * *
{¶ 15} “The contractor may reduce the amount paid by any retainage provision contained in the contract, invoice, or purchase order between the contractor and the subcontractor or materialman, and may withhold amounts that may be necessary to resolve disputed liens or claims involving the work or labor performed or material furnished by the subcontractor or materialman.”
[4]*4{¶ 16} Therefore, pursuant to R.C. 4113.61(A)(1), if a subcontractor makes a timely request for payment, a contractor must pay the subcontractor in proportion to the work completed within ten calendar days of receiving payment from the owner. A contractor, however, is permitted to withhold “amounts that may be necessary to resolve disputed liens or claims involving the work or labor performed or material furnished by the subcontractor.”
{¶ 17} Failure to comply with these provisions obligates a contractor to pay interest on the overdue payment at a rate of 18 percent per annum. R.C. 4113.61(A)(1) and (B)(1). A subcontractor also may file a civil action to recover the amount due and the statutory interest. R.C. 4113.61(B)(1). If the court determines that the contractor has not complied with the prompt-payment statute, the court must award the subcontractor the statutorily prescribed interest. Id. In addition, the prevailing party is entitled to recover reasonable attorney fees, unless such an award would be inequitable, together with court costs. R.C. 4113.61(B)(1) and (B)(3).
{¶ 18} In the present case, Construction One argues that R.C. 4113.61 permits it to withhold estimated costs of securing a lien substitute, i.e., bond premiums, and anticipated attorney fees directly relating to resolving Masiongale’s breaches of the lien-waiver and forum-selection clauses. These breaches, however, did not create “disputed liens or claims involving the work or labor performed or material furnished by the subcontractor,” within the meaning of R.C. 4113.61(A)(1). (Emphasis added.)
{¶ 19} Although these breaches concern disputes arising out of a construction contract, the lien-waiver and forum-selection provisions at issue here are procedural in nature, as they relate either to the right of a party to secure its payment with a lien or to the situs of the tribunal for the adjudication of disputes. They do not, however, concern the substantive aspects of performing the work or labor or providing any material under the contract. Cf. Consortium Communications v. Cleveland Telecommunications, Inc. (Feb. 10, 1998), Franklin App. No. 97APG08-1090, 1998 WL 63538 (permitting a contractor to withhold payment pursuant to R.C. 4113.61 when the parties disputed additional amounts concerning labor-related transportation expenses).
{¶ 20} In R.C. 4113.61, the only justifications for withholding payment relate to disputed liens or claims involving the performance of work or labor or the furnishing of material. If the General Assembly had intended to include other types of disputes, such as those over breaches of lien-waiver and forum-selection clauses, as further justification for a contractor to withhold payment, it could have expanded the statute to include these and other types of disputes. It chose not to do so.
[5]*5{¶ 21} Our holding is in accord with other jurisdictions that allow a contractor to withhold payment from a subcontractor when the dispute concerns the performance of work or labor or the furnishing of material. Cf. Ala.Code 8-29-4 (a contractor may withhold payment for, inter alia, unsatisfactory job progress, defective construction, disputed work, property damage, and if the subcontract cannot be completed for the unpaid balance of the contract sum); 10 Me.Rev.Stat. 1118(1) (a contractor may withhold payment “in an amount equalling the value of any good faith claims * * *, including claims arising from unsatisfactory job progress, defective construction or materials, disputed work or 3rd-party claims”); Elec. Eng. & Electronics, Inc. v. E.L. Shea, Inc. (D.Me.2001), 146 F.Supp.2d 74, 79-82 (holding that the contractor properly withheld payment pursuant to Maine’s prompt-payment statute for amounts relating to the installation of mounting brackets); Independence v. Kerr Constr. Paving Co., Inc. (Mo.App.1997), 957 S.W.2d 315, 323-324 (holding that Missouri’s public-works prompt-payment statute, Mo.Rev.Stat. 34.057, allows a contractor to withhold payment from a subcontractor for a claim of defective work so long as the contractor acts in good faith for reasonable cause).
{¶ 22} Accordingly, we hold that a breach of a lien-waiver or forum-selection clause in a construction contract does not create a disputed lien or claim involving the work or labor performed or material furnished by the subcontractor, within the meaning of R.C. 4113.61(A)(1). Therefore, Construction One could not properly withhold any amounts relating to those disputes.
.{¶ 23} Based on the foregoing, Construction One’s first and second propositions of law are overruled,3 and the judgment of the Court of Appeals for Franklin County is affirmed.
Judgment affirmed.
Moyer, C.J., Pfeifer and O’Connor, JJ., concur.
Resnick, F.E. Sweeney and Lundberg Stratton, JJ., dissent.