Gary Moderalli Excavating, Inc. v. Trimat Constr., Inc.

2013 Ohio 1701
Ohio Court of Appeals·Decided April 25, 2013·No. 12 AP 03 0022, 12 AP 03 0023·Published·Cited by 5 cases

Opinion

COURT OF APPEALS

TUSCARAWAS COUNTY, OHIO

FIFTH APPELLATE DISTRICT

GARY MODERALLI EXCAVATING, JUDGES: INC. Hon. W. Scott Gwin, P. J.

Hon. William B. Hoffman, J.

Plaintiff-Appellant Hon. John W. Wise, J.

-vs-

Case Nos. 2012 AP 03 0022 and TRIMAT CONSTRUCTION, 2012 AP 03 0023 INC., et al.

Defendants-Appellees OPINION

CHARACTER OF PROCEEDING: Civil Appeal from the Court of Common Pleas, Case No. 2009 CV 05 0419

JUDGMENT: Affirmed in Part; Reversed in Part and Remanded

DATE OF JUDGMENT ENTRY: April 25, 2013

APPEARANCES: For Plaintiff-Appellant For Defendants-Appellees

SHIRLEY J. SMITH WILLIAM H. WOODS 1399 E. Western Reserve Road, Suite 2 JONATHAN M. BRYAN Poland, Ohio 44514 MCNAMARA AND MCNAMARA 88 East Broad Street

TRACEY A. LASLO Suite 1250 325 East Main Street Columbus, Ohio 43215 Alliance, Ohio 44601

Tuscarawas County, Case Nos. 2012 AP 03 0022 and 2012 AP 03 0023 2 Wise, J.

{¶1} Plaintiff-Appellant Gary Moderalli Excavating, Inc. appeals the post-verdict decisions of the Tuscarawas County Court of Common Pleas made following a jury trial.

{¶2} Defendant-Appellee in this appeal is Fidelity and Deposit Company of Maryland.

STATEMENT OF THE FACTS AND CASE

{¶3} Moderalli Excavating, Inc. and Trimat Construction, Inc. are construction contractors in the State of Ohio.

{¶4} Moderalli was interested in bidding a public works job known as the Newcomerstown Landfill Cap Project. The landfill cap project required the layer of topsoil to be stripped down to the base, take the trash and place it over the center of the landfill area so that it sloped away from the center, spread dirt across the base thereby creating a sub-base, then cover the sub-base with a two-foot cap of clay material, followed by six inches of topsoil and seeding. (T. at 35-36, 417-418).

{¶5} Upon discussion with its insurance agent, Jerry Kernan, about the possibility of getting a bond for the project, Kernan suggested that Moderalli and Trimat work together to bid the project, with Trimat putting up the bond. (T. at 36, 412-413).

{¶6} On April 14, 2008, Moderalli submitted the bid under Trimat’s name and the City of Newcomerstown awarded a line item bid contract of $932,814.70 to Trimat. Trimat entered into a contract with Moderalli to be the main subcontractor on the job, with a fixed price of $841,849.70. The difference between the two figures, $90,965.00, is the result of a $10,965.00 bond premium to be paid to the bonding company, Fidelity and Deposit Company of Maryland, which provided both a payment bond and a surety

Tuscarawas County, Case Nos. 2012 AP 03 0022 and 2012 AP 03 0023 3

bond on the project; a $50,000.00 fee to Trimat for supplying the bond for the job; and $30,000.00 payment to Trimat for doing the seeding work on the project.

{¶7} On June 23, 2008, Trimat entered into a written contract with the Village of Newcomerstown to complete the project consisting of capping the landfill. The contract provided that time was of the essence and "[t]he Work will be substantially completed within 120 days after the Village issues a Notice to Proceed. It further provided Trimat would pay liquidated damages to the Village of $400.00 for each day that expires after the time specified ... for Substantial Completion until the Work is substantially complete.”

{¶8} The contract also provided that Trimat would pay Moderalli within five (5)

days of having received progress payments from the city on the contract. (T. at 39-41).

{¶9} On August 4, 2008, the Village issued the Notice to Proceed stating the work “will commence to run on August 14, 2008” and “the date of Substantial Completion is December 14, 2008 ...”

{¶10} At this time, Trimat and Moderalli had not yet executed a written subcontract. Moderalli continued to work without a signed subcontract until September 26, 2008. (T. at 58-60). It was around this time that Trimat’s president Matt Toler contacted Moderalli and explained to him that Moderalli had to hire Trimat to provide supervision on the job at the cost of $20,000.00. (T. at 15, 230, 430-31, 737-38, 1486). That supervision was provided by Maurice Toler. Id.

{¶11} At this point, the project schedule called for the Project to be “[c]omplete within next 30 days except for final top soil and seeding and mulching.”

Tuscarawas County, Case Nos. 2012 AP 03 0022 and 2012 AP 03 0023 4

{¶12} As progress was made on the project, Trimat made several applications, for payment for the portion of work that had been completed. Upon approval of the first application for payment, Trimat received $277,242.24 on September 18, 2008, and deposited the same the following day. (T. at 16, 72-74, 80, 103-104, 119, 126, 399, 402). Of that amount, Trimat paid $102,534.77 to Moderalli on October 8, 2008. (T. at 16, 76-77, 80, 126, 150, 211, 452). Trimat claimed that the amount withheld was for payment of the $50,000 bond, the $10,965 premium, $46,377.00 which it stated was to pay Fred Boyd, who provided dirt and clay for the Project from his nearby property. Id.

{¶13} Fred Boyd testified that Trimat actually only paid him $20,000 at that time and $17,000 in February, 2009. (T. at 17, 242-43). He claims he is still owed $5,377 due under the agreement. (T. at 247, 453-454).

{¶14} Trimat's second application for payment covered the work completed between August 25th and September 25th of 2008, requesting payment of $216,184.00. (T. at 17). At this point, the Project was 55.1% complete. Payment on this application was issued to Trimat on November 10, 2008. Id. Of this amount, Trimat paid Moderalli $84,839.64 in two-party checks to Moderalli and its subcontractors. (T. at 131-138).

{¶15} The third application for payment covered the period from September 25 to October 24, 2008. (T. at 18, 146-148). Trimat received payment on this application in the amount of $236,601.60 on March 26, 2009. Id. Trimat did not pay Moderalli Excavating any money from pay application number three. (T. at 18).

{¶16} The fourth application, for October 25 to November 25, 2008, was submitted when completion of the project reached 83%. (T. at 18, 160-161). During this period, the EPA determined that certain soils and product that was being hauled in from

Tuscarawas County, Case Nos. 2012 AP 03 0022 and 2012 AP 03 0023 5

outside landowners did not meet their certification requirements. (T. at 18). As a result, Moderalli was directed by Trimat to do extra work burying the tainted topsoil. Id. This extra work, along with the delays resulting from the EPA issues and inclement weather, resulted in the filing of multiple change orders, i.e. applications for payment for the extra work beyond the contract specifications. (T. at 18-19).

{¶17} The first two change orders resulted in additional payments of $139,596.18.25. (T. at 169-170).

{¶18} Payment applications five and six resulted in payments to Trimat of $26,031.96 received on July 9, 2009 and $113,041.02, respectively, with no payment remitted to Moderalli. (T. at 19, 162, 166-170).

{¶19} On December 9, 2008, Moderalli gave Fidelity notice that they were not receiving payments from Trimat as agreed and were thus seeking claim on the bond. (T. at 475-76).

{¶20} Moderalli also filed an attested account in order to freeze payment from the Village of Newcomerstown to Trimat due to non-payment. (T. at 390-395).

{¶21} Fidelity issued a surety bond to Trimat for release of the funds. At the end of the year, W.E. Quicksall, the engineer on the job, certified that the cap had been completed. (T. at 21, 197-198, 272).

{¶22} Altogether, Trimat was paid $1,130,627.42 on the Project. Moderalli received $187,000.31. (T. at 19).

{¶23} After the job had been certified complete by W.E. Quicksall, Trimat contacted them to suggest that the job was not actually complete, claiming that Moderalli was roughly one acre short on the landfill cap. (T. at 20).

Tuscarawas County, Case Nos. 2012 AP 03 0022 and 2012 AP 03 0023 6

Free access — add to your briefcase to read the full text and ask questions with AI

Gary Moderalli Excavating, Inc. v. Trimat Constr., Inc., 2013 Ohio 1701 (Ohio Ct. App. 2013).

2013 Ohio 1701 (Gary Moderalli Excavating, Inc. v. Trimat Constr., Inc.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

State v. Dukes
2026 Ohio 2028 (Ohio Court of Appeals, 2026)
State v. Simmons
2017 Ohio 1348 (Ohio Court of Appeals, 2017)
H & H Glass, Inc. v. Empire Bldg. Co., L.L.C.
2016 Ohio 3029 (Ohio Court of Appeals, 2016)
Frank Novak & Sons, Inc. v. A-Team, L.L.C.
2014 Ohio 922 (Ohio Court of Appeals, 2014)
Short v. Resource Title Agency, Inc.
2014 Ohio 830 (Ohio Court of Appeals, 2014)
In re N.L.
2013 Ohio 3983 (Ohio Court of Appeals, 2013)