H & H Glass, Inc. v. Empire Bldg. Co., L.L.C.

2016 Ohio 3029
CourtOhio Court of Appeals
DecidedMay 18, 2016
DocketC-150059, C-150227
StatusPublished
Cited by5 cases

This text of 2016 Ohio 3029 (H & H Glass, Inc. v. Empire Bldg. Co., L.L.C.) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
H & H Glass, Inc. v. Empire Bldg. Co., L.L.C., 2016 Ohio 3029 (Ohio Ct. App. 2016).

Opinion

[Cite as H & H Glass, Inc. v. Empire Bldg. Co., L.L.C., 2016-Ohio-3029.] IN THE COURT OF APPEALS FIRST APPELLATE DISTRICT OF OHIO HAMILTON COUNTY, OHIO

H&H GLASS, INC., : APPEAL NOS. C-150059 C-150227 Plaintiff-Appellee/Cross- : TRIAL NO. A-1307118 Appellant, : vs. O P I N I O N. : EMPIRE BUILDING CO., LLC., : and : TRAVELERS INSURANCE CO., : Defendants-Appellants/Cross- Appellees. :

Civil Appeals From: Hamilton County Court of Common Pleas

Judgment Appealed From Is: Affirmed

Date of Judgment Entry on Appeal: May 18, 2016

Benjamin, Yocum, & Heather, LLC, and Thomas R. Yocum, for Plaintiff- Appellee/Cross-Appellant,

Lindhorst & Dreidame, Barry F. Fagel and Matthew C. Curran, for Defendants- Appellants/Cross-Appellees.

Please note: this case has been removed from the accelerated calendar. OHIO FIRST DISTRICT COURT OF APPEALS

S TAUTBERG , Judge.

{¶1} This case involves a contract dispute. Plaintiff-appellee/cross-appellant

H&H Glass, Inc., (“H&H”) entered into a contract with defendant-appellant/cross-

appellee Empire Building Co. (“Empire”) to perform construction work on Sayler Park

School, a Cincinnati Public Schools building. Empire was the general contractor on the

project. H&H was a subcontractor that contracted with Empire to supply materials and

services related to the installation of aluminum window systems, as well as window

and door frames. Defendant-appellant/cross-appellee Travelers Insurance Co., a.k.a.

Travelers Casualty & Surety Co. of America, (“Travelers”) was the surety for Empire.

{¶2} During the course of its work on the project, H&H submitted monthly

pay applications to Empire. Empire, in turn, submitted those applications to Turner

Construction, the project manager, for payment. From the start of the project,

disputes arose between H&H and Empire regarding whether H&H had properly billed

for work performed, the timeliness of payments from Empire to H&H, and retainage

amounts withheld by Empire. These differences ultimately culminated in H&H

walking off of the job. As a result, Empire had to hire another contractor, Andy’s

Glass, to complete H&H’s work on the project.

{¶3} H&H later sued Empire for breach of contract, asserting that Empire

had failed to pay H&H $27,084.80. Included in this amount was $11,095.01 for

custom-made “storefront materials” that H&H had had in its possession at the time

that it quit working on the project. H&H also claimed that Travelers had breached its

obligation as a surety when, after H&H had demanded payment under the terms of its

contract with Empire, Travelers had refused to pay. H&H contended that Empire and

Travelers were jointly liable for its damages. H&H also asserted a prompt-pay claim

under R.C. 4113.61, which included a request for attorney fees.

2 OHIO FIRST DISTRICT COURT OF APPEALS

{¶4} Empire counterclaimed. It asserted, in part, that H&H had breached its

contract with Empire when it walked off of the job before completing it, and that

Empire had suffered $25,000 in damages as a result.

{¶5} Following a bench trial, the trial court determined that Empire had

materially breached its contract with H&H by failing to pay in accordance with the

contract, and that, following the breach, H&H had been excused from further

performance. The court awarded H&H $27,084.80. This amount included the cost of

the custom-made storefront materials. Neither side was awarded attorney fees. The

court further held that the Prompt Pay Act did not apply. Empire and Travelers

appealed, and H&H cross-appealed.

Empire and Travelers’ Appeal

{¶6} In Empire and Travelers’ first assignment of error, they contend that the

trial court erred when it held that Empire’s breach was “material,” thereby excusing

H&H from further performance under the contract.

{¶7} A breach of contract exits where, without legal justification, a party fails

to perform any promise that forms a whole or part of a contract. Natl. City Bank of

Cleveland v. Erskine & Sons, 158 Ohio St. 450, 110 N.E.2d 598 (1953), paragraph one

of the syllabus. However, not all breaches are created equal. A failure to perform a

promise that is nominal, trifling, technical, or slight does not excuse performance

under the contract by the nonbreaching party. Kichler’s, Inc. v. Persinger, 24 Ohio

App.2d 124, 128, 265 N.E.2d 319 (1st Dist.1970). In other words, “[a] breach of a

portion of the terms of a contract does not discharge the obligations of the parties to

the contract, unless performance of those terms is essential to the purpose of the

agreement.” Software Clearing House, Inc. v. Intrak, Inc., 66 Ohio App.3d 163, 170,

3 OHIO FIRST DISTRICT COURT OF APPEALS

538 N.E.2d 1056 (1st Dist.1990); see Thomas D. Reynolds & Assoc., Inc. v. Feeks, 1st

Dist. Hamilton No. C-890695, 1991 Ohio App. LEXIS 451, *4-5 (Feb. 6, 1991).

{¶8} The determination of whether a party’s failure was “essential to the

purpose” of the agreement—meaning whether a breach was “material”—is a question

of fact. O’Brien v. Ohio State Univ., 10th Dist. Franklin No. 06AP-946, 2007-Ohio-

4833, ¶ 11. It requires “an examination of the parties’ injuries, whether and how much

the injured parties would or could have been compensated, and whether the parties

acted in good faith.” Id. Here, Empire claims that the trial court’s decision finding that

its breach was material was against the manifest weight of the evidence. It was not.

{¶9} The contract between Empire and H&H allowed Empire to withhold ten

percent of payments, “unless specific provisions to the contrary are indicated in the

Contract Documents.” Indeed, one such contract document was the agreement

between the owner and the general contractor, which did contain different retainage

procedures. That agreement specified a retainage of eight percent of labor costs billed

by H&H until 50 percent of the project was completed. After 50 percent of the project

had been completed, the contract did not allow for any retainage for labor. The

contract provided different retainage rates for materials, depending on whether the

materials had been installed. Installed materials were not subject to any retainage.

{¶10} During the course of its work on the project, H&H submitted seven pay

applications to Empire. H&H experienced payment problems from the start. Empire

consistently, and over H&H’s objection, withheld more retainage than was allowed by

contract on H&H’s labor costs. The evidence presented at trial established that the

maximum amount of retainage that Empire should have withheld on labor was $2,120.

Empire withheld $9,696.80. At trial, Empire president Joe Haehnle admitted that it

paid H&H less on its labor costs than what was due under the contract.

4 OHIO FIRST DISTRICT COURT OF APPEALS

{¶11} In addition to failing to pay H&H’s labor costs as required, H&H

submitted evidence that that Empire had not paid any of its $8,695.30 June pay

application by the end of July when H&H walked off of the job.

{¶12} Based on the record before us, we hold that the trial court’s decision that

Empire’s breach was material was not against the manifest weight of the evidence. See

Eastley v. Volkman, 132 Ohio St.3d 328, 2012-Ohio-2179, 972 N.E.2d 517. Over the

course of six pay applications, Empire had failed to pay approximately $7,500 in labor

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Loyalty 360, Inc. v. Empirical Edge, Inc.
2025 Ohio 2134 (Ohio Court of Appeals, 2025)
Finn v. Seiser
2024 Ohio 5288 (Ohio Court of Appeals, 2024)
Crutcher v. Oncology/Hematology Care, Inc.
2022 Ohio 4105 (Ohio Court of Appeals, 2022)
Walters v. Goddard
2018 Ohio 5184 (Ohio Court of Appeals, 2018)

Cite This Page — Counsel Stack

Bluebook (online)
2016 Ohio 3029, Counsel Stack Legal Research, https://law.counselstack.com/opinion/h-h-glass-inc-v-empire-bldg-co-llc-ohioctapp-2016.