H & H Glass, Inc. v. Empire Bldg. Co., L.L.C.
Opinion
IN THE COURT OF APPEALS
FIRST APPELLATE DISTRICT OF OHIO HAMILTON COUNTY, OHIO
H&H GLASS, INC., : APPEAL NOS. C-150059 C-150227
Plaintiff-Appellee/Cross- : TRIAL NO. A-1307118 Appellant, :
vs. O P I N I O N.
:
EMPIRE BUILDING CO., LLC., :
and :
TRAVELERS INSURANCE CO., :
Defendants-Appellants/Cross-
Appellees. :
Civil Appeals From: Hamilton County Court of Common Pleas Judgment Appealed From Is: Affirmed Date of Judgment Entry on Appeal: May 18, 2016
Benjamin, Yocum, & Heather, LLC, and Thomas R. Yocum, for Plaintiff- Appellee/Cross-Appellant,
Lindhorst & Dreidame, Barry F. Fagel and Matthew C. Curran, for Defendants- Appellants/Cross-Appellees.
Please note: this case has been removed from the accelerated calendar.
S TAUTBERG , Judge.
{¶1} This case involves a contract dispute. Plaintiff-appellee/cross-appellant H&H Glass, Inc., (“H&H”) entered into a contract with defendant-appellant/cross- appellee Empire Building Co. (“Empire”) to perform construction work on Sayler Park School, a Cincinnati Public Schools building. Empire was the general contractor on the project. H&H was a subcontractor that contracted with Empire to supply materials and services related to the installation of aluminum window systems, as well as window and door frames. Defendant-appellant/cross-appellee Travelers Insurance Co., a.k.a. Travelers Casualty & Surety Co. of America, (“Travelers”) was the surety for Empire.
{¶2} During the course of its work on the project, H&H submitted monthly pay applications to Empire. Empire, in turn, submitted those applications to Turner Construction, the project manager, for payment. From the start of the project, disputes arose between H&H and Empire regarding whether H&H had properly billed for work performed, the timeliness of payments from Empire to H&H, and retainage amounts withheld by Empire. These differences ultimately culminated in H&H walking off of the job. As a result, Empire had to hire another contractor, Andy’s Glass, to complete H&H’s work on the project.
{¶3} H&H later sued Empire for breach of contract, asserting that Empire had failed to pay H&H $27,084.80. Included in this amount was $11,095.01 for custom-made “storefront materials” that H&H had had in its possession at the time that it quit working on the project. H&H also claimed that Travelers had breached its obligation as a surety when, after H&H had demanded payment under the terms of its contract with Empire, Travelers had refused to pay. H&H contended that Empire and Travelers were jointly liable for its damages. H&H also asserted a prompt-pay claim under R.C. 4113.61, which included a request for attorney fees.
{¶4} Empire counterclaimed. It asserted, in part, that H&H had breached its contract with Empire when it walked off of the job before completing it, and that Empire had suffered $25,000 in damages as a result.
{¶5} Following a bench trial, the trial court determined that Empire had materially breached its contract with H&H by failing to pay in accordance with the contract, and that, following the breach, H&H had been excused from further performance. The court awarded H&H $27,084.80. This amount included the cost of the custom-made storefront materials. Neither side was awarded attorney fees. The court further held that the Prompt Pay Act did not apply. Empire and Travelers appealed, and H&H cross-appealed.
Empire and Travelers’ Appeal
{¶6} In Empire and Travelers’ first assignment of error, they contend that the trial court erred when it held that Empire’s breach was “material,” thereby excusing H&H from further performance under the contract.
{¶7} A breach of contract exits where, without legal justification, a party fails to perform any promise that forms a whole or part of a contract. Natl. City Bank of Cleveland v. Erskine & Sons, 158 Ohio St. 450, 110 N.E.2d 598 (1953), paragraph one of the syllabus. However, not all breaches are created equal. A failure to perform a promise that is nominal, trifling, technical, or slight does not excuse performance under the contract by the nonbreaching party. Kichler’s, Inc. v. Persinger, 24 Ohio App.2d 124, 128, 265 N.E.2d 319 (1st Dist.1970). In other words, “[a] breach of a portion of the terms of a contract does not discharge the obligations of the parties to the contract, unless performance of those terms is essential to the purpose of the agreement.” Software Clearing House, Inc. v. Intrak, Inc., 66 Ohio App.3d 163, 170,
538 N.E.2d 1056 (1st Dist.1990); see Thomas D. Reynolds & Assoc., Inc. v. Feeks, 1st Dist. Hamilton No. C-890695, 1991 Ohio App. LEXIS 451, *4-5 (Feb. 6, 1991).
{¶8} The determination of whether a party’s failure was “essential to the purpose” of the agreement—meaning whether a breach was “material”—is a question of fact. O’Brien v. Ohio State Univ., 10th Dist. Franklin No. 06AP-946, 2007-Ohio- 4833, ¶ 11. It requires “an examination of the parties’ injuries, whether and how much the injured parties would or could have been compensated, and whether the parties acted in good faith.” Id. Here, Empire claims that the trial court’s decision finding that its breach was material was against the manifest weight of the evidence. It was not.
{¶9} The contract between Empire and H&H allowed Empire to withhold ten percent of payments, “unless specific provisions to the contrary are indicated in the Contract Documents.” Indeed, one such contract document was the agreement between the owner and the general contractor, which did contain different retainage procedures. That agreement specified a retainage of eight percent of labor costs billed by H&H until 50 percent of the project was completed. After 50 percent of the project had been completed, the contract did not allow for any retainage for labor. The contract provided different retainage rates for materials, depending on whether the materials had been installed. Installed materials were not subject to any retainage.
{¶10} During the course of its work on the project, H&H submitted seven pay applications to Empire. H&H experienced payment problems from the start. Empire consistently, and over H&H’s objection, withheld more retainage than was allowed by contract on H&H’s labor costs. The evidence presented at trial established that the maximum amount of retainage that Empire should have withheld on labor was $2,120. Empire withheld $9,696.80. At trial, Empire president Joe Haehnle admitted that it paid H&H less on its labor costs than what was due under the contract.
{¶11} In addition to failing to pay H&H’s labor costs as required, H&H submitted evidence that that Empire had not paid any of its $8,695.30 June pay application by the end of July when H&H walked off of the job.
{¶12} Based on the record before us, we hold that the trial court’s decision that Empire’s breach was material was not against the manifest weight of the evidence. See Eastley v. Volkman, 132 Ohio St.3d 328, 2012-Ohio-2179, 972 N.E.2d 517. Over the course of six pay applications, Empire had failed to pay approximately $7,500 in labor costs due under the contract. And at the time that H&H had walked off the job, there was another pay application for $8,695.30 pending with Empire. Wrongfully and consistently withholding payment of labor costs can fairly be characterized as a breach going to the “essence” of the parties’ agreement. Ernst v. Ohio Dept. of Adm. Serv., 69 Ohio App.3d 330, 337, 590 N.E.2d 812 (10th Dist.1990); Olympic Painting and Sheeting Co. v. Danbourne Corp., 7th Dist. Mahoning No. 79 C.A. 69, 1980 Ohio App. LEXIS 14002, *8 (May 5, 1980). Empire and Travelers’ first assignment of error is overruled.
{¶13} In their second assignment of error, Empire and Travelers claim that Empire was entitled to a set-off in damages because it had to pay another contractor to finish the work H&H did not. In their fourth assignment of error, they raise a related argument that Empire should have been allowed to apply the $9,696.80 retainage due to H&H towards paying Andy’s Glass.
Free access — add to your briefcase to read the full text and ask questions with AI
2016 Ohio 3029 (H & H Glass, Inc. v. Empire Bldg. Co., L.L.C.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.