Smith Johnson Constr. v. Leohner Co., Unpublished Decision (10-18-2006)

2006 Ohio 5678
CourtOhio Court of Appeals
DecidedOctober 18, 2006
DocketNo. 06CA7.
StatusUnpublished

This text of 2006 Ohio 5678 (Smith Johnson Constr. v. Leohner Co., Unpublished Decision (10-18-2006)) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Smith Johnson Constr. v. Leohner Co., Unpublished Decision (10-18-2006), 2006 Ohio 5678 (Ohio Ct. App. 2006).

Opinions

OPINION
{¶ 1} This case comes to us on the accelerated calendar. App. R. 11.1 which governs accelerated calendar cases, provides in pertinent part:

{¶ 2} "(E) Determination and judgment on appeal. The appeal will be determined as provided by App. R. 11.1. It shall be sufficient compliance with App. R. 12(A) for the statement of the reason for the court's decision as to each error to be in brief and conclusionary form. The decision may be by judgment entry in which case it will not be published in any form."

{¶ 3} This appeal shall be considered in accordance with the aforementioned rule.

STATEMENT OF THE FACTS AND CASE
{¶ 4} Appellant, Smith and John Construction Company, was the general contractor to the Ohio Department of Transportation (ODOT) on Job No. 425-01, with Appellee John K. Leohner Co. Inc. as a subcontractor. Such subcontract required Appellee to provide certain labor and materials on such project in accordance with the ODOT general contract.

{¶ 5} Appellant received payments from ODOT based upon certain numbered and dated estimates but did not issue payment to Appellee within ten days even though the amounts were undisputed.

{¶ 6} Appellee filed suit premised on breach of such subcontract requesting payment of damages, interest, including such arising under the Prompt Payment Act, attorney fees and a declaratory judgment as to retained funds.

{¶ 7} After trial, the court issued findings of fact and conclusions of law and awarded judgment of the principal balances claimed plus interest specifying the amounts and accrual dates on each numbered estimate plus attorney fees.

{¶ 8} The issue in this appeal involves the awarding of continuing interest under R.C. § 4113.61 et seq.

{¶ 9} The Assignment of Error states:

ASSIGNMENT OF ERROR
{¶ 10} "I. THE TRIAL COURT AWARDED CONTINUING INTEREST IMPROPERLY, PURSUANT TO THE PROMPT PAYMENT ACT, AGAINST APPELLANT. (JUDGMENT ENTRY; FINDINGS OF FACT, CONCLUSIONS OF LAW AND DECISION)."

I.
{¶ 11} Revised Code 4113.61 provides in part:

{¶ 12} "(A)(1) If a subcontractor or materialman submits an application or request for payment or an invoice for materials to a contractor in sufficient time to allow the contractor to include the application, request, or invoice in his own pay request submitted to an owner, the contractor, within ten calendar days after receipt of payment from the owner for improvement to property, shall pay to the: (a) Subcontractor, an amount that is equal to the percentage of completion of the subcontractor's contract allowed by the owner for the amount of labor or work performed.

{¶ 13} "* * * * If the contractor fails to comply with division (A)(1) of this section, the contractor shall pay the subcontractor or materialman, in addition to the payment due, interest in the amount of eighteen per cent per annum of the payment due, beginning on the eleventh day following the receipt of payment from the owner and ending on the date of full payment of the payment due plus interest to the subcontractor or materialman.

{¶ 14} "* * * * If a contractor receives any final retainage from the owner for improvements to property, the contractor shall pay from that retainage each subcontractor and materialman his proportion of the retainage, within ten calendar days after receipt of the retainage from the owner, or within the time period provided in a contract, invoice, or purchase order between the contractor and the subcontractor or materialman, whichever time period is shorter, provided that the contractor has determined that the subcontractor's or materialman's work, labor, and materials have been satisfactorily performed or furnished and that the owner has approved the subcontractor's or materialman's work, labor, and materials.

{¶ 15} "If the contractor fails to pay a subcontractor or materialman within the appropriate time period, the contractor shall pay the subcontractor or materialman, in addition to the retainage due, interest in the amount of eighteen per cent per annum of the retainage due, beginning on the eleventh day following the receipt of the retainage from the owner and ending on the date of full payment of the retainage due plus interest to the subcontractor or materialman."

{¶ 16} The following schedule represents the job estimate numbers, the dates payment was received by Appellant from O.D.O.T., the amounts received, the dates payment was made to Appellee, and the court's determination of the accrual dates of interest on each to November 8, 2005, the trial date:

JOB DATE DATE ACCRUED AMOUNT OF EST. NO. AMOUNT RECEIVED PAID DAYS INTEREST --------------------------------------------------------------------------- 11 $ 9,993.60 5/06/02 6/05/02 1270 $ 6,261.10 14 $ 8,607.68 6/16/02 7/08/02 1227 $ 5,214.75 15 $ 8,492.68 7/09/02 7/25/02 1206 $ 5,053.14 21 $22,528.65 10/08/02 10/31/02 1115 $12,387.65 22 $10,207.69 10/21/02 1/29/03 1100 $ 5,544.00 24 $ 1,080.74 11/29/02 1/29/03 1063 $ 563.39 25 $ 1,140.04 12/05/02 1/29/03 1057 $ 602.49 26 $ 5,185.78 12/18/02 1/29/03 1044 $ 2,672.64 27 $ 949.16 1/07/03 1/29/03 1024 $ 481.28 30 $ 7,545.94 2/19/03 3/13/03 981 $ 3,649.32 31 $ 6,237.65 3/06/03 3/27/03 944 $ 2,898.08 33 $ 4,189.11 4/07/03 4/28/03 934 $ 1,933.38 41 $29,226.78 8/02/03 8/27/03 817 $11,772.97 43 $10,155.94 9/03/03 9/18/03 785 $ 3,925.00 51 $26,159.20 12/31/03 2/27/04 666 $ 8,591.40 52 $ 4,285.34 1/20/04 2/27/04 645 $ 1,360.95 57 $ 5,126.65 3/31/04 5/14/04 576 $ 1,457.28 58 $57,682.55 4/18/04 5/14/04 558 $15,869.52 59 $ 8,981.13 5/03/04 5/21/04 543 $ 2,405.49 60 $39,415.78 5/18/04 6/23/04 528 $10,259.04 61 $24,056.29 6/03/04 6/23/04 512 $ 6,072.32 64 $23,630.89 7/19/04 8/18/04 469 $ 5,463.85 65 $21,663.52 7/31/04 9/21/04 454 $ 4,848.72 67 $63,227.19 8/31/04 9/23/05 423 $13,189.14 68 $34,057.55 10/01/04 9/23/05 392 $ 6,581.68 69 $27,660.07 10/07/04 9/23/05 384 $ 5,237.76 70 $ 662.50 10/18/04 9/23/05 377 $ 120.64 ___________ TOTAL: $144,416.98

{¶ 17} It is clear that the trial court's interpretation of the Prompt Payment Act was to the effect that interest at 18% per annum accrues on unjustified withholding of payments beyond the allotted statutory grace period and continues to accrue until the combined total of principal and interest has been paid even though the principal due has been remitted.

{¶ 18}

Free access — add to your briefcase to read the full text and ask questions with AI

Related

State ex rel. Sinay v. Sodders
685 N.E.2d 754 (Ohio Supreme Court, 1997)
State ex rel. Webb v. Bliss
789 N.E.2d 1102 (Ohio Supreme Court, 2003)
Masiongale Electrical-Mechanical, Inc. v. Construction One, Inc.
102 Ohio St. 3d 1 (Ohio Supreme Court, 2004)

Cite This Page — Counsel Stack

Bluebook (online)
2006 Ohio 5678, Counsel Stack Legal Research, https://law.counselstack.com/opinion/smith-johnson-constr-v-leohner-co-unpublished-decision-10-18-2006-ohioctapp-2006.