Electrical Engineering & Electronics, Inc. v. E.L. Shea, Inc.

146 F. Supp. 2d 74, 2001 U.S. Dist. LEXIS 7376, 2001 WL 618957
CourtDistrict Court, D. Maine
DecidedJune 5, 2001
DocketCIV. 99-274-B
StatusPublished
Cited by2 cases

This text of 146 F. Supp. 2d 74 (Electrical Engineering & Electronics, Inc. v. E.L. Shea, Inc.) is published on Counsel Stack Legal Research, covering District Court, D. Maine primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Electrical Engineering & Electronics, Inc. v. E.L. Shea, Inc., 146 F. Supp. 2d 74, 2001 U.S. Dist. LEXIS 7376, 2001 WL 618957 (D. Me. 2001).

Opinion

MEMORANDUM OF DECISION AND ORDER

GENE CARTER, District Judge.

The Court now has before it Plaintiff Electrical Engineering and Electronics, Inc.’s (hereinafter “3E”) Motion to Make Additional Findings and to Amend Judgment (Docket No. 37). See Fed.R.Civ.P. 52(b). Defendants E.L. Shea, Inc. (hereinafter “E.L. Shea”) and Fidelity and Deposit Company of Maryland (hereinafter “Fidelity”) oppose 3E’s motion (Docket Nos. 38 and 40).

*76 This case was tried without a jury. The Court issued a Memorandum of Decision and Order on January 15, 2001. See Docket No. 35. Subsequently, Judgment was entered. See Docket No. 36. In its pretrial and post-trial briefs, 3E focused on the issues relating to additional compensation for the cost of materials and labor related to the substitution of electrical metallic tubing (“EMT”) and building wire for metal clad cable (“MC cable”). See Plaintiffs Trial Brief (Docket No. 30) and Brief of Plaintiff (Docket No. 32). Plaintiff 3E did not address certain claims in its pretrial and post-trial briefs, and the Court did not address those claims in its Memorandum of Decision and Order. Specifically, the Court did not take up Plaintiffs claims, asserted in Counts I and II, to recover unpaid amounts under the contract for the temporary power, the television mounting brackets, and the costs associated with additional testing of the elevator. In addition, the Court did not address Plaintiffs claim, asserted in Count III under the prompt payment statute, 10 M.R.S.A. § 1111 et seq., for statutory interest and attorneys’ fees on the unpaid contract balance, for a $4,600 payment made on March 30, 2000, and for a $30,000 payment made on March 20, 1999. Plaintiff now requests that the Court address these issues, make additional findings of fact, and amend its Judgment.

Briefly, the facts relevant to Plaintiffs motion are as follows. 1 This action arises out of the construction of the Squadron Operations Building for the Maine Air National Guard in Bangor, Maine. The owner of the project was the Maine National Guard. The general contractor for the project was Defendant E.L. Shea, and Defendant Fidelity issued the project performance and payment bonds for E.L. Shea. E.L. Shea entered into a contract with 3E, the terms of which provided that 3E would be the electrical subcontractor for the Squadron Operations Building. See Defendants’ Ex. 1, Subcontract. 2 The electrical subcontract incorporated the electrical specifications of the Project Manual for the Squadron Operations Building. See Plaintiffs Ex. 1, Project Manual.

I. UNPAID CONTRACT BALANCES

In addition to the claims addressed by the Court in its Memorandum of Decision and Order, Plaintiff asserts entitlement under the contract to $7,505.81 in unpaid amounts for the temporary power, the television mounting brackets, and costs associated with elevator retests. See Amended Complaint Counts I and II (Docket No. 9). Defendants dispute that these amounts are due and owing under the contract.

A. Temporary Power

The parties agree that E.L. Shea withheld $4,017.30 from 3E for the cost of *77 temporary power that was provided to the site. 3 In addition, 3E contends that it is owed $1,068.03 for temporary power costs it paid in error. The Subcontract between Shea and 3E provides in part:

The Subcontractor shall perform all the Work required by the Contract Documents for
Division 16-ELECTRIC
Division 16-ELECTRIC INCLUDES: BASE BID
ADDENDUMS NO. 1 & 2 ABI # 1-4

Defendants’ Ex. 1, Subcontract at 2. Division 16 of the Project Manual provides the electrical specifications for the project. With respect to temporary electrical power, division 16 of the Project Manual provides “Arrange for, obtain permits, and provide, temporary lighting and power for the duration of the project. Electric energy consumed under this provision will be paid for by the Contractor.” Plaintiffs Ex. 1, Project Manual § 16010, 1.12(A). At issue is the meaning of the word “Contractor” in the electrical specifications of the Project Manual. Plaintiff asserts that the word “Contractor” in the electrical specifications of the Project Manual is a reference to E.L. Shea and, thus, that E.L. Shea was responsible for the cost of temporary power. Defendants counter that “Contractor” in the electrical specifications refers to 3E.

In division 16 of the Project Manual, the Court has identified references to both “electrical subcontractor” and “Contractor.” See Plaintiffs Ex. 1, Project Manual § 16010, 1.7 (“Electrical submittals shall be reviewed by, and carry the approval stamp of, the electrical subcontractor and be initialed and dated by the reviewer.”); id. § 16010, 1.12(A) (“Arrange for, obtain permits, and provide, temporary lighting and power for the duration of the project. Electric energy consumed under this provision will be paid for by the Contractor.”); id. § 16320, 3.6(C) (“Contractor to provide inrush current curves for each transformer.”); id. § 16400, 3.2(G) (“Pan-elboard circuiting has been worked out with breakers numbered and increasing in size and number of poles from top to bottom. If this is not retained, the Contractor shall be responsible for revising contract drawings and paying to have it done.”); id. § 16500, 1.3(1) (“Transportation charges for samples shall be paid by Contractor.”); id. § 16500 2.13(E)(1) (“Occupant sensor calibration shall be performed by the Contractor prior to system turnover and rechecked and recalibrated three months later .... Contractor shall first arrange for and receive on-site training by a representative of the system manufacturer in a number of spaces ... on the project.”); id. § 16725, 1.4(A) (“Pri- or to installation [of security alarm system] submit data showing that the Contractor is a factory approved installer and has at least five years experience installing security alarm systems ....”); id. § 16740, 3.1(H) (“Contractor shall repair and replace all defective cables and/or connectors as necessary [in the telephone and data wiring system].”). After studying division 16, it is arguable that because the electrical specifications make use of the designation “electrical subcontractor” and “Contractor,” those terms necessarily denote different entities. However, the language of division 16 does not support this interpretation.

*78 The parties provided no testimony as to whether the charges for temporary electrical power are customarily the responsibility of the general contractor or the electrical subcontractor.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
146 F. Supp. 2d 74, 2001 U.S. Dist. LEXIS 7376, 2001 WL 618957, Counsel Stack Legal Research, https://law.counselstack.com/opinion/electrical-engineering-electronics-inc-v-el-shea-inc-med-2001.