Xtreme Elements, L.L.C. v. Foti Contracting, L.L.C.

2018 Ohio 3323, 118 N.E.3d 930
CourtOhio Court of Appeals
DecidedAugust 20, 2018
DocketNO. 2017-L-099
StatusPublished
Cited by1 cases

This text of 2018 Ohio 3323 (Xtreme Elements, L.L.C. v. Foti Contracting, L.L.C.) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Xtreme Elements, L.L.C. v. Foti Contracting, L.L.C., 2018 Ohio 3323, 118 N.E.3d 930 (Ohio Ct. App. 2018).

Opinion

DIANE V. GRENDELL, J.

{¶ 1} Plaintiff-appellant, Xtreme Elements, LLC, appeals from the Judgment Entry of the Lake County Court of Common Pleas, denying Xtreme's request for attorney's fees. The issue to be determined in this case is whether a trial court errs by failing to award attorney's fees in an action under the Prompt Payment Act when such an award would be inequitable given the excessive amount requested and that the attorneys' work was duplicative. For the following reasons, we affirm the decision of the lower court.

{¶ 2} On March 18, 2014, Xtreme filed a Complaint against defendant-appellee, Foti Contracting, LLC, and Associated Associates in the Lake County Court of Common Pleas. Foti had a contract with Southington Local School District for the construction of a school facility and Xtreme entered into three subcontracts with Foti in 2009 to perform concrete work for the project. Xtreme stated that it had completed all work and that Foti had raised baseless complaints and withheld partial payment in the amount of $91,230. Count One was for Breach of Contract. Count Two was raised under the Prompt Payment Act, for Foti's failure to pay Xtreme "within 10 days of receipt of funds associated with the subcontractor's work." Count Three was for Breach of Contract against Associated, a concrete supplier, for failing to timely furnish materials and Count Four was for Indemnity against Associated.

{¶ 3} Foti filed its Answer and Counterclaim on April 11, 2014, raising a counterclaim for Breach of Contract.

*932 {¶ 4} A trial to the court was held in 2015. The following pertinent testimony and evidence were presented:

{¶ 5} Xtreme entered into three subcontracts, worth over $800,000, with Foti, the general contractor, in 2009 to perform concrete work on the Southington School District construction project. Work performed included, in part, inside foundation, a back-door entryway with a broom finish, walk-off mats, and sidewalks.

{¶ 6} Hugh Lockhart, Xtreme's owner, testified regarding issues that arose while working on the project. One related to a defect in the sidewalk, and led to a dispute over whether replacement was necessary. A triangular area of concrete completed with a "broom finish" was poured near the back door of the school in the spring of 2011 and was also the subject of a dispute. Lockhart testified that all work was completed adequately. Lockhart believed that Foti owed Xtreme a total balance of $87,650.20.

{¶ 7} Richard Dopatka, a project manager for Scaparotti Construction, testified that approximately $20,000 was initially withheld for the "broom finish" back-door area of concrete due to concerns with its appearance/aesthetics. Paul Gillespie, Foti's project manager, expressed similar concerns. The payment was withheld for roughly a year, with a decision made by several parties to wait during the winter to determine if it would be "structurally sound." It was then decided that the work was acceptable and the funds were released by Southington to Foti.

{¶ 8} Gillespie admitted that money was still owed to Xtreme but expressed concern regarding the dispute between Associated, the concrete supplier, and Xtreme, and questioned the proper party for payment. He admitted that some portion of the money should have been paid to Xtreme but was not sure why it was not, noting that Xtreme may have failed to send a final invoice.

{¶ 9} Testimony was also presented by several parties disputing whether work on walk-off mats and interior concrete was performed correctly by Xtreme. Foti employees contended extra work had to be done to repair defects.

{¶ 10} On March 30, 2016, the trial court issued a Judgment Entry, finding Foti was justified in withholding amounts to repair or replace walk-off mats, aluminum thresholds, interior concrete work, and HVAC filters, totaling approximately $31,000. It found that Foti was unjustified in withholding $19,723.99 for the sidewalk and in removing/replacing it, but denied a request for interest under the Prompt Payment Act.

{¶ 11} Regarding the broom finish/back door concrete work, the court found that Foti was not justified in continuing to withhold the payment. Xtreme was awarded interest under the Prompt Payment Act from November 10, 2012, shortly after the money for that work had been paid by the owner to Foti. Relating to this claim, the court determined that an award of attorney's fees would be inequitable. The court rendered judgment in favor of Xtreme against Foti in the amount of $56,651.30, with applicable interest.

{¶ 12} Xtreme appealed this judgment on several grounds. This court reversed, in part, due to the lower court's failure to hold a hearing on the issue of attorney's fees for the broom finish/back entrance claim as required by R.C. 4113.61(B)(3). Xtreme Elements, LLC v. Foti Contracting, LLC , 11th Dist. Lake No. 2016-L-043, 2017-Ohio-254 , 2017 WL 283382 , ¶ 42.

{¶ 13} A hearing on attorney's fees was held on March 3, 2017. The following pertinent testimony was presented:

*933 {¶ 14} Thomas Crist, a partner at Benesch, Friedlander, Coplan, & Aronoff, testified in relation to the representation of Xtreme in this matter. He testified that, even taking into account amounts under dispute, Xtreme was not paid approximately $26,000 for the broom-finish work, even after it had been accepted by Foti. He believed the amount was not in dispute and was held with "zero justification." Thus, recovery of interest and attorney's fees under the Prompt Payment Act was justified, especially given that the attorney's fees expended far exceeded the amount sought for Foti's breach.

{¶ 15} Crist testified that it was necessary for his firm to perform research to demonstrate that Foti had been paid by Southington for the concrete work because Foti's answers to this question provided in discovery and during mediation were inaccurate and/or misleading. He determined that Foti had been paid by the owner for the broom finish work as of October 30, 2012, but that money was not paid to Xtreme. Total fees billed by the firm for the entire litigation were approximately $250,000. Crist believed that, taking into account amounts billed for items unrelated to the work giving rise to the application of the Prompt Payment Act, the court should award reasonable fees in the range of $130,000 to $150,000. He testified that a significant amount of work took place on this case over a five-year period.

{¶ 16} On July 13, 2017, the trial court denied the request for attorney's fees. It found an award of attorney's fees would be inequitable since: there was a dispute as to the amount of money owed to Xtreme, the amount of the judgment subject to the Prompt Payment Act was less than a third of the amount in controversy, and the attorney's fees incurred in prosecuting the claim at issue "likely would have been incurred even if the $25,921.62 had been paid because the remaining funds were subject to disputes." The court also noted litigating the broom finish claim "likely involved little, if any additional work."

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Atlas Piers NEO v. Summit Constr. Co., Inc.
2021 Ohio 2024 (Ohio Court of Appeals, 2021)

Cite This Page — Counsel Stack

Bluebook (online)
2018 Ohio 3323, 118 N.E.3d 930, Counsel Stack Legal Research, https://law.counselstack.com/opinion/xtreme-elements-llc-v-foti-contracting-llc-ohioctapp-2018.