Xtreme Elements, L.L.C. v. Foti Contracting, L.L.C.

2017 Ohio 254
CourtOhio Court of Appeals
DecidedJanuary 23, 2017
Docket2016-L-043
StatusPublished
Cited by4 cases

This text of 2017 Ohio 254 (Xtreme Elements, L.L.C. v. Foti Contracting, L.L.C.) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Xtreme Elements, L.L.C. v. Foti Contracting, L.L.C., 2017 Ohio 254 (Ohio Ct. App. 2017).

Opinion

[Cite as Xtreme Elements, L.L.C. v. Foti Contracting, L.L.C., 2017-Ohio-254.]

IN THE COURT OF APPEALS

ELEVENTH APPELLATE DISTRICT

LAKE COUNTY, OHIO

XTREME ELEMENTS, LLC, : OPINION

Plaintiff-Appellant, : CASE NO. 2016-L-043 - vs - :

FOTI CONTRACTING, LLC, et al., :

Defendant-Appellee. :

Civil Appeal from the Lake County Court of Common Pleas, Case No. 2014 CV 000639.

Judgment: Affirmed in part, reversed in part, and remanded.

Matthew D. Gurbach, Thomas O. Crist, and Anthony C. Sallah, Benesch, Friedlander, Coplan & Aronoff LLP, 200 Public Square, Suite 2300, Cleveland, OH 44114 (For Plaintiff-Appellant).

John K. Lind, Jr., 3185 Belvoir Boulevard, Shaker Heights, OH 44122 (For Defendant- Appellee).

DIANE V. GRENDELL, J.

{¶1} Plaintiff-appellant, Xtreme Elements, LLC, appeals from the Judgment

Entry of the Lake County Court of Common Pleas, ruling in favor of defendant-appellee,

Foti Contracting, LLC, on various claims following a trial. The issues to be determined

in this case are whether prejudgment interest must be paid under the Prompt Payment

Act when the parties present conflicting testimony about the soundness of certain

construction work and there is a dispute over whether payment was withheld in good faith, and whether the court erred by failing to hold a hearing on attorney’s fees when

awarding prejudgment interest for a claim pursuant to the Prompt Payment Act. For the

following reasons, we affirm in part and reverse in part the decision of the lower court

and remand for further proceedings consistent with this opinion.

{¶2} On March 18, 2014, Xtreme filed a Complaint against Foti and Associated

Associates in the Lake County Court of Common Pleas, which was a refiling of a 2012

Complaint. The Complaint stated that Foti had a contract with Southington Local

School District for the construction of a school facility and that Xtreme had entered into

three subcontracts with Foti in August and October 2009 to perform concrete work for

that project. Xtreme stated that it had completed all work under the subcontracts and

that Foti had raised baseless complaints for some work and withheld partial payment in

the amount of $91,230. Count One was for Breach of Contract for Foti’s failure to pay

the amount owed. Count Two was raised under the Prompt Payment Act, for Foti’s

failure to pay Xtreme “within 10 days of receipt of funds associated with the

subcontractor’s work.” Count Three was for Breach of Contract against Associated, a

concrete supplier, for failing to timely furnish materials and Count Four was for

Indemnity against Associated.

{¶3} Foti filed its Answer and Counterclaim on April 11, 2014, and raised a

counterclaim for Breach of Contract.

{¶4} On May 8, 2014, Xtreme filed its Answer to Counterclaim.

{¶5} Following the filing of an unsuccessful Motion to Dismiss, Associated filed

its Answer, Counterclaim, Cross-claim and Third-Party Complaint.

2 {¶6} A trial to the court was held on multiple dates in February through

November of 2015. The following pertinent testimony and evidence were presented:

{¶7} Xtreme entered into three subcontracts with Foti, the general contractor, in

September and October of 2009 to perform concrete work on the Southington School

District construction project, the value of which totaled over $800,000. Work performed

included, in part, inside foundation, a back door entryway, and sidewalks.

{¶8} Hugh Lockhart, Xtreme’s owner, testified regarding issues that arose while

working on this project. In June 2010, Xtreme completed a sidewalk, also referred to as

an island, near the ball field, with ready-mix concrete supplied by Associated

Associates. During the pour, an issue with a cold joint forming arose. Cold joints can

occur when concrete starts to dry or set before additional concrete is added, potentially

causing a separation in the concrete. Lockhart testified that Xtreme was asked by

Scaparotti Construction, Southington’s representative, to fix the cold joint issue by

“rubbing it out,” which was done. On July 5, 2011, Paul Gillespie, the project manager

from Foti, sent an e-mail stating that the sidewalk would need to be replaced. In an e-

mail response sent at his request on July 11, 2011, Lockhart indicated that “if a third-

party testing company core drills the sidewalk and determines that it is not structurally

sound then Xtreme would replace it.” He believed a core drill, taking a sample to show

the inside of the concrete, would demonstrate if there was any separation and indicate

the strength of the concrete. He did not believe the concrete island/sidewalk needed to

be removed since it was structurally sound.

{¶9} A triangular area of concrete completed with a “broom finish” was poured

near the back door of the school in the spring of 2011 and was also the subject of a

3 dispute. Lockhart testified that the broom finish, typically used to give concrete traction,

was completed adequately. On June 15, 2011, he received an e-mail regarding this

area, from Paul Gillespie, a project manager for Foti, asking to “send me something

regarding the concrete that needs to be replaced at the back of the building.” Lockhart

responded “Not going too (sic), thanks,” since he did not believe the work needed to be

replaced. He believed that Foti still owed Xtreme a total balance of $87,650.20.

{¶10} Richard Dopatka, a project manager for Scaparotti Construction, testified

that money was withheld for the “broom finish” area of the concrete. He expressed

concern with the appearance/aesthetics of the concrete work. $20,000 was withheld for

roughly a year, with a joint decision made by several parties to wait during the winter to

determine if it would be “structurally sound.” It was then decided that the work was

acceptable and the funds were released to Foti.

{¶11} Regarding the sidewalk/concrete island by the baseball field, it was

ultimately replaced since, according to Dopatka, cold joints are not acceptable pursuant

to industry standard. The request to take core samples was rejected as there was

already evidence that there was a cold joint, which could cause the concrete to

deteriorate over time.

{¶12} Jason Cheshire, the foreman for Xtreme Elements, testified that the

triangle pour and finish were completed adequately, although he believed Lucio Velotta,

Scaparotti’s superintendent, said something the next day about the area being “a little

rough.” Regarding the ball field sidewalk pour, Cheshire had issues with the concrete

supplier, Associated Associates, being “excessively late,” which led to the formation of

the cold joint. Patching of the sidewalk was subsequently completed by Xtreme, which

4 he believed was an acceptable remedy. He opined that the sidewalk was functional,

sound, and did not need replaced.

{¶13} James Franz, the project superintendent for Foti Contracting, was present

during the pour of the sidewalk and saw that the first layer of concrete started to set

before the second layer was poured, causing the formation of the cold joint. Scaparotti

was adamant that the sidewalk needed to be removed but Xtreme would not replace it

and another subcontractor had to be hired. He did not believe that the concrete was

structurally sound.

{¶14} Regarding the broom finish area, he said it “looked terrible” but there was

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Victor v. Big Sky Energy, Inc.
2018 Ohio 4666 (Ohio Court of Appeals, 2018)
McCormack v. Jefferson Area Local School Dist.
2018 Ohio 3744 (Ohio Court of Appeals, 2018)
Xtreme Elements, L.L.C. v. Foti Contracting, L.L.C.
2018 Ohio 3323 (Ohio Court of Appeals, 2018)
CitiMortgage, Inc. v. Elrod
2017 Ohio 8442 (Ohio Court of Appeals, 2017)

Cite This Page — Counsel Stack

Bluebook (online)
2017 Ohio 254, Counsel Stack Legal Research, https://law.counselstack.com/opinion/xtreme-elements-llc-v-foti-contracting-llc-ohioctapp-2017.