Portage Exteriors v. Hein Constr., Inc.

2014 Ohio 2930
CourtOhio Court of Appeals
DecidedJune 20, 2014
Docket13 BE 5
StatusPublished
Cited by1 cases

This text of 2014 Ohio 2930 (Portage Exteriors v. Hein Constr., Inc.) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Portage Exteriors v. Hein Constr., Inc., 2014 Ohio 2930 (Ohio Ct. App. 2014).

Opinion

[Cite as Portage Exteriors v. Hein Constr., Inc., 2014-Ohio-2930.] STATE OF OHIO, BELMONT COUNTY IN THE COURT OF APPEALS

SEVENTH DISTRICT

PORTAGE EXTERIORS, INC., ) ) PLAINTIFF-APPELLANT, ) ) CASE NO. 13 BE 5 V. ) ) OPINION HEIN CONSTRUCTION, INC., ET AL., ) ) DEFENDANTS-APPELLEES. )

CHARACTER OF PROCEEDINGS: Civil Appeal from Court of Common Pleas of Belmont County, Ohio Case No. 10CV0222

JUDGMENT: Reversed and Remanded

APPEARANCES: For Plaintiff-Appellant Attorney Dean S. Hoover Hudson Station, Suite 3 5 Atterbury Boulevard Hudson, Ohio 44236

For Defendant-Appellee Attorney John C. Ross Daily Harpst, Ltd. 2475 Massillon Rd. Akron, Ohio 44312

JUDGES:

Hon. Gene Donofrio Hon. Joseph J. Vukovich Hon. Cheryl L. Waite -2-

Dated: June 20, 2014 [Cite as Portage Exteriors v. Hein Constr., Inc., 2014-Ohio-2930.] DONOFRIO, J.

{¶1} Plaintiff-appellant, Portage Exteriors, Inc., appeals from a Belmont County Common Pleas Court judgment in its favor for $18,350.43 on its claims against defendant-appellee, Hein Construction, Inc., following a bench trial. {¶2} This case involves the renovation of the Union Local School District’s (ULSD) school building. Hein was the general contractor for the job that included replacing the roof, installing and restoring the Exterior Insulation and Finish System (EIFS), and restoring the caulking. Hein subcontracted the EIFS and caulking restoration to Portage, which specializes in EIFS. EIFS is a synthetic stucco that allows a building to move without cracking. {¶3} The parties entered into a subcontract that provided:

Scope of work: Per your quote dated 6-25-09; Remove and replace EIFS, includes metal flashings & flashing tape, replacement of new EMS per plans. Recoat EIFS, blank out and recoat existing EIFS. Painting of existing EIFS. Removal and replacement of caulking at windows, doors and control joints. Clean windows. Remove and replace down spouts. Rubbish removed to on site dumpster. Received and reviewed addendums. Work is to begin July 6th. Total $95,000.00.

(Pt. Ex.1). The parties subsequently entered into a “change order” for additional EIFS and painting work for $14,480.62. This resulted in a total subcontract price of $109,480.62. (Pt. Ex. 3). {¶4} The ULSD project also had Plans and Specifications setting out the job. The parties disputed whether the Plans and Specifications were part of the Hein- Portage subcontract. {¶5} Before beginning work on the school, Portage performed a “mock-up.” A mock-up is a small sample of the work to be done. In the mock-up, Portage used a silicone caulking consistent with the Specifications. But Portage used a urethane compound on the job, which was inconsistent with the Specifications. {¶6} Hein paid Portage’s first payment application in the amount of $19,800. -2-

(Pt. Exs. 14, 17). Disputes then arose regarding the quality of Portage’s work. Hein did not make any further payments to Portage. {¶7} Specifically, on September 30, 2009, a “pull test” was performed on Portage’s caulking work. A pull test involves cutting a portion of the caulking to make a tab and then pulling the tab to check the adherence of the caulking. According to those present, Portage’s work failed the pull test. According to Donovan Hysell, Portage’s owner, the caulking failed the pull test because the caulk had not had sufficient time to cure and because waterproofing material had been applied which prevented the caulk from properly adhering. {¶8} Hein subsequently hired another subcontractor to redo Portage’s work. {¶9} On February 24, 2010, Portage filed a complaint against Hein asserting claims for breach of the subcontract and violation of Ohio’s Prompt Payment Act. Hein filed a counterclaim for breach of contract and also sought a declaratory judgment that Portage’s lien on certain funds be discharged. Portage then amended its complaint adding another count to foreclose on the funds under lien. {¶10} Hein moved for partial summary judgment on Portage’s Prompt Pay claim. Portage responded with its own motion for partial summary judgment on the same issue. The trial court denied Hein’s motion for summary judgment. It granted Portage’s motion only as it related to $2,475 due to Portage and denied it in all other respects. {¶11} The matter proceeded to a bench trial. The trial court found that although Portage completed the work, it did not do so in a manner that complied with the Specifications and Plans applicable to this public project. It found that Portage should have used silicone joint sealant, but instead used polyurethane sealant. It also found that Portage should have cleaned out the joints immediately before installing new sealant, but instead Portage spent over a month cleaning the joints and allowed weeks to pass before the clean joints were sealed. The court further found that the manufacturer would not warrant the work and expert testimony supported Hein’s conclusion that the work had to be redone. The court did find that -3-

Hein’s application of waterproofing material to certain joints may have contributed to the failure of the caulking material to adhere to the joints properly. The court noted it was undisputed that Hein did not pay Portage. {¶12} The court found that Portage did not prove by a preponderance of the evidence that its work was substantially compliant with the contract. It found that the caulking was not performed in compliance with the contract and was not guaranteed in accordance with the contract. It further found that Hein was compelled to redo Portage’s work and Portage refused to assist. The court found Hein owed Portage $18,350.43 as the value of Portage’s work. It stated that the $2,475 already awarded in summary judgment was included in this award and that prejudgment interest was owed on that part of the award. It also found that because a good faith dispute arose in this case, no attorney fees were warranted. Accordingly, the trial court entered judgment for Portage in the amount of $18,350.43. {¶13} Portage filed a timely notice of appeal on March 22, 2013. {¶14} Portage raises four assignments of error, the first of which states:

THE TRIAL COURT ERRED AS A MATTER OF LAW WHEN IT CONSTRUED A CONSTRUCTION CONTRACT TO INCLUDE SEPARATE CONSTRUCTION SPECIFICATIONS NOT MENTIONED IN THE CONTRACT WHERE THE PARTIES AGREE THE CONTRACT WAS A FULL AND FINAL EXPRESSION OF THEIR AGREEMENT.

{¶15} Portage asserts that both parties offered testimony that the subcontract, consisting of a one-page purchase order, along with a “change order” constituted the entire contract between them. It argues that despite this testimony, the trial court construed the contract to include the separate specifications included as part of Hein’s prime contract with ULSD. Portage argues this was error. It claims the court’s stated motivation for doing so, public policy, should not have been a consideration here because the subcontract and change order made up the entire agreement -4-

between the parties. It asserts there was no testimony that the subcontract was ambiguous. Portage argues that if Hein wanted the terms of the prime contract to be included in the subcontract, it should have incorporated it either expressly or by a “flow down” provision, which is common in construction contracts. {¶16} Construing a contract is a matter of law. Monroe Excavating, Inc. v. DJD &C Dev., Inc., 7th Dist. No. 10 MA 12, 2011-Ohio-3169, ¶22, citing Alexander v. Buckeye Pipe Line Co., 53 Ohio St.2d 241, 374 N.E.2d 146 (1978), paragraph one of the syllabus. When a contract’s terms are clear and unambiguous, a court cannot look beyond the plain language of the agreement to determine the rights and obligations of the parties. Cocca Dev. v. Mahoning Cty. Bd. of Commrs., 7th Dist. No.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Xtreme Elements, L.L.C. v. Foti Contracting, L.L.C.
2017 Ohio 254 (Ohio Court of Appeals, 2017)

Cite This Page — Counsel Stack

Bluebook (online)
2014 Ohio 2930, Counsel Stack Legal Research, https://law.counselstack.com/opinion/portage-exteriors-v-hein-constr-inc-ohioctapp-2014.