Doral Steel, Inc. v. Gray Metal Products, Inc.

672 F. Supp. 2d 798, 2009 U.S. Dist. LEXIS 116730, 2009 WL 4546724
CourtDistrict Court, N.D. Ohio
DecidedDecember 4, 2009
DocketCase 3:09 CV 996
StatusPublished

This text of 672 F. Supp. 2d 798 (Doral Steel, Inc. v. Gray Metal Products, Inc.) is published on Counsel Stack Legal Research, covering District Court, N.D. Ohio primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Doral Steel, Inc. v. Gray Metal Products, Inc., 672 F. Supp. 2d 798, 2009 U.S. Dist. LEXIS 116730, 2009 WL 4546724 (N.D. Ohio 2009).

Opinion

MEMORANDUM OPINION AND ORDER

JACK ZOUHARY, District Judge.

Introduction

The issue before the Court is the amount of damages arising out of an admitted breach of contract for the sale of steel (Doc. No. 29 ¶ 1). The Court held an evidentiary hearing on September 3, 2009 (Doc. No. 22). Both parties submitted pre-hearing and post-hearing Memoranda (Doc. Nos. 18-19, 26-27).

Findings of Fact

On July 1, 2008, Defendant Gray Metal Products (“Gray”) submitted to Plaintiff Doral Steel, Inc. (“Doral”) a Purchase Order for hot dip galvanized steel of various widths and gauges (Ex. A). The purchase order called for 875 metric tons of steel to be delivered at the “end of July 2008” for a total purchase price of $1.24 million. On July 29, 2008, Richard Gray (Purchasing Manager for Gray) sent an email to John Spoerl (Sales Rep for Doral) asking Doral to “move a couple hundred tons of steel to another customer,” presumably because it was not needed (Ex. P). Spoerl refused to reduce the tons from Gray’s order, but did agree to “work a little longer on the time frame and spread [the shipments] out in August” (Ex. P). Starting in August 2008, Gray issued a number of partial releases on the July Purchase Order authorizing Doral to ship some of the steel (Tr. 27). Gray accepted and paid for all shipments of this released steel (Tr. 25-26).

On August 8, 2008, Richard Gray sent another email to Spoerl stating “you are going to need to work with us on this, or we will be forced to cancel some of the tonnage” (Ex. P). During this time, the price of steel was declining dramatically (Tr. 33). One month later, Gray placed an order for steel with a different vendor; this order was substantially the same as Gray’s previous order from Doral (Ex. CC; Tr. 96-97). Conversely, on September 26, 2008, Doral shipped to another customer coils of steel originally designated for Gray (Ex. X; Tr. 41-42).

On September 30, 2008, Richard Gray sent another email to Spoerl stating that Gray “will not be able to take any more of this material unless the pricing is adjusted drastically” (Ex. R; Tr. 30). Spoerl replied that Doral might be able to adjust the pricing if Gray were willing to take more tons than specified in the July Purchase Order (Ex. S; Tr. 30-31). However, the parties never reached an agreement to modify the price or quantity (Tr. 36-37).

Richard Gray sent another email to Spoerl on October 22, 2008 (Ex. R):

John, after reviewing the new proposal from you and looking at what we have in inventory along with the price of steel in the low .50 a pound range we can not bring in anymore material from Doral. I am sorry but this is the position we have to take to protect our companies. If the pricing was closer to current market conditions we would be able to probably do something but with the current drop we are being forced to adjust our pricing in several markets.

Gray did not issue any more releases and refused to accept any more steel after *800 October 2008 (Tr. 40, 101). There was no further contact between Doral and Gray until February 2009 (Tr. 100-01).

In early February 2009, Mike Crooks (Vice President of Doral) called Richard Gray who confirmed he would not take any more steel (Tr. 49-50). On February 17, Doral’s legal counsel sent Gray a letter demanding reasonable assurance that Gray would accept and pay for the remaining steel under the July Purchase Order (Ex. 12; Tr. 113-14). Gray did not respond to the letter (Tr. 113-14) and this lawsuit followed on April 1 (Doc. No. 1). Doral’s legal counsel sent Gray a notice of private sale on May 26, indicating that Doral had an opportunity to sell most or all of the .012 gauge steel that Gray had refused to accept (Ex. T), but that private sale fell through. Doral eventually sold some of the steel but never gave Gray notice of those sales (Ex. Y).

The parties agree on the type and quantity of steel that Gray refused to accept (Ex. Y; Doc. No. 26, p. 9; Doc. No. 27, p. 2h_

Purchase Order Gauge_Quantity (pounds')_Price ($/lb)
.012 x 48 264,554.7 0.6695
.012 x 41.25 661,368.8 0.6695
.016 x 48 244,933.6 0.6395
.016 x 60 99,208.0 0.7195
.019 x 60_440,924.5_0.6795

Conclusions of Law

This dispute is governed by the Ohio Uniform Commercial Code (“UCC”) and, specifically, the application of the UCC damages provisions. This Court must determine (1) when did Gray cancel (or repudiate) the contract, and (2) what is the appropriate measure of damages based on that cancellation date. Doral argues that Gray did not unequivocally cancel the contract until March 2009, when it failed to answer Doral’s written demand for adequate assurance of performance. Gray argues the contract was cancelled earlier in September, or at the latest October, by virtue of Richard Gray’s email exchanges with Spoerl, when Gray refused to accept any more shipments of steel.

Time of Cancellation

To cancel a contract, there must be a clear expression of intent not to perform. Anticipatory repudiation “centers upon an overt communication of intention or an action which renders performance impossible or demonstrates a clear determination not to continue with performance.” R.C. § 1302.68, Comment 1 (UCC § 2-708); see also Am. Bronze Corp. v. Streamway Prods., 8 Ohio App.3d 223, 228, 456 N.E.2d 1295 (1982) (anticipatory repudiation “must be a definite and unequivocal refusal to perform”).

Based on a combination of Gray’s statements and actions, this Court concludes that Gray unequivocally cancelled the contract in mid-November 2008. Richard Gray’s email to Spoerl on October 22, 2008 is strong evidence that Gray did not intend to accept any more steel from Doral:

After reviewing the new proposal from you and looking at what we have in inventory along with the price of steel in the low .50 a pound range we can not bring in anymore material from Doral. I am sorry but this is the position we have to take to protect our companies. If the pricing was closer to current market conditions we would be able to probably do something but with the current drop we are being forced to adjust our pricing in several markets.

(Ex. R) (emphasis added). Doral argues this email is not a cancellation because the email suggests Gray could “probably do something” if Doral dropped its price. But one month earlier, Doral had offered to reduce the price slightly—though nowhere near “current market” value—if Gray agreed to take more steel. Gray declined, choosing instead to cancel the remaining steel. Given this series of communications, the last sentence of the Octo *801 ber 22 email is not a counter-offer. Rather, it is a confirmation of its earlier desire to cancel and a repeated explanation of why Doral would not “bring in anymore material from Doral.” And even if a counter-offer, Doral never took steps to negotiate, let alone accept, lower pricing.

While Gray’s communications

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
672 F. Supp. 2d 798, 2009 U.S. Dist. LEXIS 116730, 2009 WL 4546724, Counsel Stack Legal Research, https://law.counselstack.com/opinion/doral-steel-inc-v-gray-metal-products-inc-ohnd-2009.