Voestalpine Rotec LLC v. Sumiriko Ohio, Inc.

CourtDistrict Court, N.D. Ohio
DecidedMarch 28, 2025
Docket3:21-cv-01716
StatusUnknown

This text of Voestalpine Rotec LLC v. Sumiriko Ohio, Inc. (Voestalpine Rotec LLC v. Sumiriko Ohio, Inc.) is published on Counsel Stack Legal Research, covering District Court, N.D. Ohio primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Voestalpine Rotec LLC v. Sumiriko Ohio, Inc., (N.D. Ohio 2025).

Opinion

IN THE UNITED STATES DISTRICT COURT FOR THE NORTHERN DISTRICT OF OHIO WESTERN DIVISION

VOESTALPINE ROTEC LLC, CASE NO. 3:21 CV 1716

Plaintiff,

v. JUDGE JAMES R. KNEPP II

SUMIRIKO OHIO, INC., et al., MEMORANDUM OPINION AND Defendants. ORDER

INTRODUCTION Pending before the Court in this breach of contract case are the parties’ cross-motions for summary judgment. (Docs. 39, 42). Jurisdiction is proper under 28 U.S.C. § 1332. The matter is fully briefed. See Docs. 43, 44, 45, 46. For the reasons discussed below, the Court denies Plaintiff’s Motion; Defendants’ Motion is granted in part as to Plaintiff’s statute of frauds affirmative defense, but is denied as to all other claims. BACKGROUND This action arises out of contracts between Plaintiff Voestalpine Rotec LLC, an Indiana limited liability company, and Defendants Sumiriko Ohio, Inc., and Sumiriko Tennessee, Inc., Delaware corporations. Defendants produce automotive components, requiring specially- manufactured tubular steel parts (“Parts”) which were purchased from suppliers such as Plaintiff. (Doc. 39-1, at 7; Doc. 42-1, at 8). The parties engaged in business transactions for the sale and purchase of Parts for years before the current issue arose. Their relationship dates back to at least 2016, evidenced by early emails. See Doc. 42-4. In 2017, Plaintiff signed an acknowledgment stating it “reviewed and accept[ed] the policies and procedures as outlined in the [Defendants’] Supplier Policy Manual” (“SPM”). (Doc. 39-13, at 2) (Acknowledgment). The SPM contains an array of documents and information concerning Defendants’ policies, goals, and preferences. (Doc. 42-3) (SPM). The parties’ transactions were typically initiated as follows: Defendants intermittently (and irregularly) sent Master Purchase Agreements (“MPA”) setting prices, Part numbers, and payment

terms; Defendants then sent three-month “rolling” forecasts, estimating quantities of each Part they might order for the following months; finally, Defendants sent purchase orders to commence the transactions. (Doc. 42-7, at 3). The transactions appear historically consistent in procedure and substance. Each MPA was identical aside from the item number and price; each stated it incorporated certain “Conditions of Purchase.”1 (Doc. 42-6, at 2–10). Similarly, the purchase orders were nearly identical, barring item numbers and quantities requested, as well as the timing for payment. Id. at 12–14; see also Doc. 39-14. Each purchase order contained a note at the bottom stating written or emailed confirmation was required. Id. Plaintiff appears to have consistently manufactured and delivered Parts to

Defendants by the delivery methods, quantities, and prices outlined in the purchase orders, and invoiced them pursuant to the prices listed in the relevant MPA. See Doc. 39-15; Doc. 39-20; Doc. 42-7, at 5–6. After three years and hundreds of transactions with seemingly no issues, a dispute arose in late 2020. (Doc. 42-7, at 5–6). On August 27, 2020, the Mexican government implemented a

1. As expanded upon in the Court’s discussion of the Motions, the only “Conditions of Purchase” clearly pointed to in the record is a section within the SPM titled as such. (Doc. 42-3, at 57–59). That said, many inconsistencies within the produced documents leave this Court unable to determine whether that section is what the MPAs reference. See Doc. 42-4 (emails indicating the existence of “Conditions of Purchase” is a separate document from the SPM); Doc. 42-3, at 9, 57 (Introduction of the SPM stating the “Conditions of Purchase” are “item [14]”, but the “Conditions of Purchase” section referenced by the parties appears as heading 17). monitoring regime requiring certain steel exporters to verify that requisite value had been added to steel products in Mexico to prove exemption from U.S. anti-dumping tariffs (“Decree”). (Doc. 39-7). Just five days after the Decree’s announcement, exporters had to apply for and obtain a permit from the Mexican government to ship steel products across the border. Id. This posed an issue for Plaintiff’s production, as Yulchon, a company in Mexico, supplied the steel used to make

Parts. (Doc. 16, at 5–6). Plaintiff’s supplier notified it of the Decree on September 10, 2020, and, in turn, Plaintiff notified Defendants of the Decree and potential delays on September 16, 2020. (Doc. 39-8; Doc. 42-6, at 119, 124). The new permit requirement delayed Plaintiff’s ability to obtain the steel used to make Defendants’ Parts during the last four months of 2020. (Doc. 16, at 8). But the parties maintained constant contact about such delays via email and telephone. In fact, daily meetings took place for months to assist with communication during the ongoing issue. (Doc. 39-3, at 16). Though aware of the delays Plaintiff faced, Defendants continued issuing purchase orders. Id. at 17. But Defendants had orders to fill and clients to please, so they also ordered some Parts

from another supplier to meet demands. Id. at 20. These other goods came at a cost and required freight shipping; Defendants claim to have expended $483,262 to keep up with their customers’ orders during this period. (Doc. 16, at 9). Plaintiff contests its obligation to abide by dates requested in purchase orders, but both parties agree that each Part requested in purchase orders was ultimately delivered to, and accepted by, Defendants. (Doc. 39-1, at 18; Doc. 42-1, at 7). On April 9, 2021, Plaintiff emailed Defendants regarding unpaid balances on the account; Defendants responded that same day indicating “most [were] paid and some [were] ready to be paid.” (Doc. 39-10, at 5–6). Plaintiff’s follow-up messages went unanswered until April 27, 2021, when Defendants responded with questions about tariff refunds and expedite reimbursements. Id. at 2. Plaintiff responded, and the next day Defendants sent a demand-letter style document alleging breach of contract. (Doc. 39-11). Plaintiff’s Complaint for breach of contract alleges that, while there are written documents covering the subject matter, the only “contract” formed was by virtue of the shipment and delivery of goods. (Doc. 1). Plaintiff asserts Defendants breached this contract when they refused to pay

for goods delivered. Id. Defendants’ Counterclaim for breach of contract argues that a conglomeration of written documents formed an overarching “supply agreement,” binding Plaintiff to every term of multiple documents. (Doc. 16). Defendants claim that Plaintiff breached this agreement by failing to reimburse them for expenses incurred by the delays. Id. STANDARD OF REVIEW Summary judgment is appropriate where there is “no genuine dispute as to any material fact” and “the movant is entitled to judgment as a matter of law.” Fed. R. Civ. P. 56(a). When considering a motion for summary judgment, the Court must draw all inferences from the record in the light most favorable to the nonmoving party. Matsushita Elec. Indus. Co. v. Zenith Radio

Corp., 475 U.S. 574, 587 (1986). The Court may not weigh the evidence or determine the truth of any matter in dispute; the Court determines only whether the case contains sufficient evidence from which a jury could reasonably find for the nonmoving party. Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 248–49 (1986). The moving party bears the burden of proof. Celotex Corp. v. Catrett, 477 U.S. 317

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
United States v. Patrick M. Donovan
348 F.3d 509 (Sixth Circuit, 2003)
Reeves v. Columbia Gas of Ohio (In Re Reeves)
265 B.R. 766 (N.D. Ohio, 2001)
Imad Alshaibani v. Litton Loan Servicing LP
528 F. App'x 462 (Sixth Circuit, 2013)
Busler v. D & H Manufacturing, Inc.
611 N.E.2d 352 (Ohio Court of Appeals, 1992)
Tubelite Co. v. Original Sign Studio, Inc.
891 N.E.2d 820 (Ohio Court of Appeals, 2008)
Software Clearing House, Inc. v. Intrak, Inc.
583 N.E.2d 1056 (Ohio Court of Appeals, 1990)
Morton Buildings v. Correct Custom Drywall, 06ap-851 (6-7-2007)
2007 Ohio 2788 (Ohio Court of Appeals, 2007)
American Bronze Corp. v. Streamway Products
456 N.E.2d 1295 (Ohio Court of Appeals, 1982)
Doner v. Snapp
649 N.E.2d 42 (Ohio Court of Appeals, 1994)
Alexander v. Buckeye Pipe Line Co.
374 N.E.2d 146 (Ohio Supreme Court, 1978)
Berjian v. Ohio Bell Telephone Co.
375 N.E.2d 410 (Ohio Supreme Court, 1978)
DuBrul v. Citrosuco North America, Inc.
892 F. Supp. 2d 892 (S.D. Ohio, 2012)
Foremost Pro Color, Inc. v. Eastman Kodak Co.
703 F.2d 534 (Ninth Circuit, 1983)
McJunkin Corp. v. Mechanicals, Inc.
888 F.2d 481 (Sixth Circuit, 1989)

Cite This Page — Counsel Stack

Bluebook (online)
Voestalpine Rotec LLC v. Sumiriko Ohio, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/voestalpine-rotec-llc-v-sumiriko-ohio-inc-ohnd-2025.