Morton Buildings v. Correct Custom Drywall, 06ap-851 (6-7-2007)

2007 Ohio 2788
CourtOhio Court of Appeals
DecidedJune 7, 2007
DocketNo. 06AP-851, (C.P.C. No. 03CVH10-1897).
StatusPublished
Cited by12 cases

This text of 2007 Ohio 2788 (Morton Buildings v. Correct Custom Drywall, 06ap-851 (6-7-2007)) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Morton Buildings v. Correct Custom Drywall, 06ap-851 (6-7-2007), 2007 Ohio 2788 (Ohio Ct. App. 2007).

Opinion

OPINION
{¶ 1} Plaintiff-appellant, Morton Buildings, Inc. ("Morton"), appeals from a judgment in favor of defendant-appellee, Correct Custom Drywall, Inc. ("CCD"). For the following reasons, we affirm.

{¶ 2} In early 2002, James Wade, the CEO of CCD, decided to build a large, free-standing garage in which to store his motor home and collection of automobiles. Wade directed his assistant to contact various contractors, including Morton, to solicit proposals. Because Wade wanted the garage completed as soon as possible, he *Page 2 refused to consider any contractor who could not construct the garage within 90 days. At trial, Wade testified that he told all the contractors about his 90-day time limitation.

{¶ 3} Thomas Taylor, a Morton sales consultant, drafted and submitted a proposal in which he set forth potential architectural features and product specifications for the garage. This proposal indicated that the "[t]ime frame of construction" would be April 15, 2002 through July 31, 2002.

{¶ 4} In his trial testimony, Wade claimed that after receiving Morton's proposal, he met with Taylor to provide Taylor with more details about the qualities he wanted in the garage. During the meeting, Wade chose a particular model of garage, as well as certain features and building materials. Taylor then drafted and submitted a second proposal incorporating Wade's choices and provided that construction would occur from late May to late August 2002.

{¶ 5} On April 26, 2002, the parties executed a contract in which CCD agreed to pay $126,438 for the construction of a 36,000 square-foot garage on Wade's property in Reynoldsburg, Ohio ("City"). The contract did not contain a completion date. However, it did state that July 1, 2002 would be the "approximate delivery date" for the building materials. Also, a third proposal, dated the same day as the contract, provided that construction would begin in late July and end in late August. Wade later testified that he signed the contract because Taylor guaranteed that Morton would complete the garage by September 1, 2002. Taylor, however, denied that he ever guaranteed a particular completion date.

{¶ 6} Morton's engineering department drafted plans for the garage, which Lawrence Cole, a Morton sales consultant, submitted to the City on July 15, 2002. A little *Page 3 over two weeks later, the City notified Cole that it had approved the plans with the condition that Morton strengthen the ceiling truss system.

{¶ 7} Throughout the majority of August and September, the project stalled as Morton redesigned the garage. By early August, Wade became impatient with the delay and questioned Cole about the lack of progress. Cole told Wade of the City's conditional approval, and Wade responded that Cole should "get it done" and "proceed in a hurry."

{¶ 8} Cole submitted the revised plans to the City on September 21, 2002, and the City approved the plans within two days. Morton delivered the building materials to the site on October 15, 2002. Construction began two days later, and Morton finished erecting the shell of the garage on November 7, 2002.

{¶ 9} On November 23, 2002, Cole met with the subcontractor to view the plans and to discuss what plumbing, electrical, and heating work the subcontractor needed to complete. By December 5, 2002, the subcontractor had finished trenching for the interior plumbing. However, construction stalled again as the subcontractor awaited the City's inspection of its competed work. Unhappy with this second delay, Wade telephoned Cole on December 18, 2002 seeking an explanation. Cole told Wade that construction could not go forward without the City's approval, and Wade responded that he wanted the subcontractor off the job if it could not complete its work within a reasonable time.

{¶ 10} On January 8, 2003, the subcontractor returned to the site to work on the garage. Michael Wade, Wade's brother, informed the subcontractor that Morton was no longer on the job and asked the subcontractor to leave.

{¶ 11} In an attempt to keep the deal together, Morton representatives met with Wade and his brother on February 11, 2003. During that meeting, the participants *Page 4 discussed the work necessary to complete the contract. In the course of reviewing the state of the garage's unfinished plumbing system, Wade discovered that he would have to spend an additional $30,000 to connect the garage to the City sewer. Further, the Morton representatives told the Wades that a "reasonable time frame for completion" of the garage would be April 15, 2003. For Wade, the additional two months of construction were "absolutely the last straw," and he terminated the contract. At the time of termination, CCD had only paid $50,571 of the total purchase price.

{¶ 12} On October 28, 2003, Morton filed suit against CCD, asserting claims for breach of contract and unjust enrichment. CCD filed a counterclaim for breach of contract. A bench trial on the parties' claims commenced on May 16, 2006.

{¶ 13} At trial, Wade, Michael Wade, Taylor, and Cole testified regarding the events set forth above. Additionally, Michael Wade, who works as a general contractor, testified that it would have taken him three to five months to completely construct the garage. Cole testified that Morton could have built the garage within five months under "normal circumstances."

{¶ 14} On August 15, 2006, the trial court issued a decision and entry in which it rendered a verdict against Morton on its claims and against CCD on its counterclaim. Morton now appeals from that judgment and assigns the following errors:

1. The trial court erred in ruling that Defendant CCD, despite demanding and accepting performance by Plaintiff Morton Buildings through January 2003, did not waive any defense regarding time of performance.

2. The trial court erred in ruling that time of performance was an essential term of the contract.

3. The trial court erred in ruling that Morton Buildings failed to perform within a reasonable time.

*Page 5

4. The trial court erred in ruling that Morton Buildings cannot recover under a theory of quantum meruit or unjust enrichment.

5. The trial court erred in ruling that the contract did not contain an integration clause.

{¶ 15} We will address Morton's assignments of error out of order and begin our review with the third assignment of error. By that assignment of error, Morton argues that because it was performing (and would complete its performance) within a reasonable time, it did not materially breach the contract. Without a material breach, Morton contends, CCD did not have grounds to stop performing, and thus, CCD breached the contract in not making full payment.

{¶ 16} When a contract does not specify a time for performance and time is not of the essence, the law implies that performance must take place within a reasonable time. Oil, Chem. Atomic Workers Internatl.Union, Loc. Union No. 3-689 v. Martin Marietta Energy Sys. (1994),97 Ohio App.3d 364, 369; 155 N. High Ltd. v. Cincinnati Ins. Co. (1991),75 Ohio App.3d 253,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

SAI Hospitality, Inc. v. RCVV, Inc.
2025 Ohio 4596 (Ohio Court of Appeals, 2025)
Clark v. Clark
2025 Ohio 159 (Ohio Court of Appeals, 2025)
Quest Wellness Ohio, L.L.C. v. Samuels
2023 Ohio 4450 (Ohio Court of Appeals, 2023)
Treadway Gallery, Inc. v. Baylor
2023 Ohio 3642 (Ohio Court of Appeals, 2023)
Prime Invests., L.L.C. v. Altimate Care, L.L.C.
2022 Ohio 1181 (Ohio Court of Appeals, 2022)
Mid Am. Constr., L.L.C. v. Univ. of Akron
2019 Ohio 3863 (Ohio Court of Appeals, 2019)
Ta v. Chaudhry
2016 Ohio 4944 (Ohio Court of Appeals, 2016)
Marion v. Hoffman
2010 Ohio 4821 (Ohio Court of Appeals, 2010)
Stocker v. Cochran's Decorative Curbing, Inc.
2010 Ohio 1542 (Ohio Court of Appeals, 2010)
Smith v. Vaughn
882 N.E.2d 941 (Ohio Court of Appeals, 2007)
Klausing v. Chef Solutions, 1-07-34 (11-13-2007)
2007 Ohio 6014 (Ohio Court of Appeals, 2007)

Cite This Page — Counsel Stack

Bluebook (online)
2007 Ohio 2788, Counsel Stack Legal Research, https://law.counselstack.com/opinion/morton-buildings-v-correct-custom-drywall-06ap-851-6-7-2007-ohioctapp-2007.