Stone Excavating v. Newmark Homes, Inc., Unpublished Decision (8-6-2004)

2004 Ohio 4119
Ohio Court of Appeals·Decided August 6, 2004·No. C.A. Case No. 20307.·Unpublished·Cited by 11 cases

Opinion

OPINION
{¶ 1} Defendant, Newmark Homes, Inc. ("Newmark"), appeals froma judgment of the court of common pleas in favor of Plaintiff,Stone Excavating, Inc. ("Stone"), on Stone's claim for breach ofcontract. {¶ 2} Stone agreed to perform certain work to install streets,water and sewer lines, and construction site pads at asubdivision of residential properties being developed by Newmarkin Vandalia. The contract was in several writings, supplementedby oral agreements. {¶ 3} The work to be performed by Stone was identified in aseries of progressive steps, culminating in its installation of asecond, finished layer of asphalt on the streets it hadconstructed. The contract provided the price of each step.Newmark agreed to pay for each when complete, upon Stone'sapplication. Stone agreed that Newmark would retain six per centof each payment dug for repair of any work performed improperly. {¶ 4} Stone began work in 1997 and completed all steps exceptthe last, installation of the second layer of asphalt on thestreets, by March of 1998. Stone applied for payment as each wascompleted. Newmark paid the amount due for each, less the six percent retainage. {¶ 5} Vandalia's building regulations impose a minimum ninemonth period between installation of the first and second layersof asphalt on new streets. It also requires contractors tocomplete all development work within two years, subject toone-year extensions when delays are encountered. {¶ 6} Newmark encountered delays and received severalextensions from Vandalia. The final extension was until Octoberof 2001. Approximately each six months following completion ofits other work in 1998, Stone had asked for permission fromNewmark to place the second layer of asphalt. Each time Newmarkdeclined, citing the need to complete its other work. It isundisputed that performance of the other work could damage thesecond layer of asphalt. {¶ 7} When Stone made its last request to complete its work,Newmark stated that it would likely be ready some months later,in October of 2001. Stone protested that it could not do the workthen, because of other commitments. Newmark stood with itsprojection. {¶ 8} In October of 2001, Newmark requested Stone to place thesecond layer of asphalt. Stone said it could not perform the workthen. Newmark performed the work itself. In the process, Newmarkalso performed the "bond work" repair to the earlier work thatStone had performed and for which it had been paid the contractprice, less retainage. {¶ 9} Stone demanded the retainage Newmark had kept from thepayments it made for the work Stone performed. Newmark declined,citing Stone's failure to complete its work by installing thesecond layer of asphalt. Stone commenced an action for breach ofcontract. After a trial to the bench, the court granted judgmentfor Stone in the amount of the retainage, $31,466.08, less aset-off of $1,099.59 for bond work Newmark had performed. Newmarkappeals.

FIRST ASSIGNMENT OF ERROR
{¶ 10} "The trial court committed reversible error in itsapplication of the substantial performance doctrine."

Free access — add to your briefcase to read the full text and ask questions with AI

Stone Excavating v. Newmark Homes, Inc., Unpublished Decision (8-6-2004), 2004 Ohio 4119 (Ohio Ct. App. 2004).

2004 Ohio 4119 (Stone Excavating v. Newmark Homes, Inc., Unpublished Decision (8-6-2004)) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Mt. Pleasant Blacktopping Co., Inc. v. Inverness Group, Inc.
2025 Ohio 284 (Ohio Court of Appeals, 2025)
Universal Steel Bldgs. Corp. v. Dues
2024 Ohio 698 (Ohio Court of Appeals, 2024)
Meyer Tool, Inc. v. Mikrolar, Inc.
2023 Ohio 704 (Ohio Court of Appeals, 2023)
Lawless v. Lawrence Cty. Bd. of Edn.
2020 Ohio 117 (Ohio Court of Appeals, 2020)
Oberlin v. Lorain Cty. Joint Vocational School Dist. Bd. of Edn.
2019 Ohio 3977 (Ohio Court of Appeals, 2019)
Knighten v. Erie Islands Resort & Marina
2016 Ohio 7108 (Ohio Court of Appeals, 2016)
Seitz v. Harvey
2015 Ohio 122 (Ohio Court of Appeals, 2015)
Gevedon v. Ivey
876 N.E.2d 604 (Ohio Court of Appeals, 2007)
Morton Buildings v. Correct Custom Drywall, 06ap-851 (6-7-2007)
2007 Ohio 2788 (Ohio Court of Appeals, 2007)