Mt. Pleasant Blacktopping Co., Inc. v. Inverness Group, Inc.

2025 Ohio 284
CourtOhio Court of Appeals
DecidedJanuary 31, 2025
DocketC-240134
StatusPublished
Cited by1 cases

This text of 2025 Ohio 284 (Mt. Pleasant Blacktopping Co., Inc. v. Inverness Group, Inc.) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Mt. Pleasant Blacktopping Co., Inc. v. Inverness Group, Inc., 2025 Ohio 284 (Ohio Ct. App. 2025).

Opinion

[Cite as Mt. Pleasant Blacktopping Co., Inc. v. Inverness Group, Inc., 2025-Ohio-284.]

IN THE COURT OF APPEALS FIRST APPELLATE DISTRICT OF OHIO HAMILTON COUNTY, OHIO

MT. PLEASANT BLACKTOPPING CO., : APPEAL NO. C-240134 INC., TRIAL NO. A-2102231 : Plaintiff-Appellee, : vs. OPINION : INVERNESS GROUP, INC., : Defendant-Appellant. :

Civil Appeal From: Hamilton County Court of Common Pleas

Judgment Appealed From Is: Affirmed in Part, Reversed in Part, and Cause Remanded

Date of Judgment Entry on Appeal: January 31, 2025

Dressman Benzinger LaVell PSC, Kevin F. Hoskins, Joseph M. Kramer and Richard G. Meyer, for Plaintiff-Appellee,

Strauss Troy Co., LPA, Brian J. O’Connell, James D. Houston and Stephen E. Schilling, for Defendant-Appellant. OHIO FIRST DISTRICT COURT OF APPEALS

CROUSE, Judge.

{¶1} This case flows from a dispute over a sewage line. The Inverness Group,

Inc. (“Inverness”), the defendant-appellant in this case, is a real estate developer that

engaged plaintiff-appellee Mt. Pleasant Blacktopping Company, Inc. (“MPB”), to

install sewage lines in one of its housing developments. After a surprising regulatory

rejection clogged up the process, the parties sought to determine who had to foot the

bill for the fix. MPB prevailed following a bench trial.

{¶2} Inverness now contends that prior federal litigation estopped MPB from

relitigating the arbitrariness of the regulatory action, that Greene County (“the

County”) should have been joined as a necessary party, and that the trial court

misapplied several contract-law doctrines, including those set forth in Security

Sewage Equip. Co. v. McFerren, 14 Ohio St.2d 251 (1968) (hereinafter “Security

Sewage”). While we reject Inverness’s challenges to the trial court’s collateral-estoppel

and joinder rulings, we agree that the trial court misapplied Security Sewage and the

contract doctrines of substantial performance and impossibility. We therefore reverse

the trial court’s judgment for MPB and remand the cause for consideration under the

proper framework.

I. BACKGROUND

A. The Contract

{¶3} Inverness is a real estate developer responsible for the Landings at

Sugar Creek (“the Landings”), a housing development in Greene County, Ohio. In

2016, Inverness engaged MPB, an infrastructure contractor, to install sewer lines in

Section 3 and Section 4 of the Landings in separate agreements. This case arises out

of MPB’s agreement to install lines in Section 4.

{¶4} In the written agreement, MPB promised to “obtain all permits and

2 OHIO FIRST DISTRICT COURT OF APPEALS

licenses that may be necessary for the proper performance” of its installation duties.

MPB further promised that its work would “conform to the requirements of all

governmental agencies . . . having jurisdiction over the Project” and would be “in

accordance with the specifications” of the same. MPB’s performance would be deemed

complete when it was “to the satisfaction of . . . all government agencies having

jurisdiction.”

{¶5} MPB also agreed that it was “responsible for testing [the sewer] system

and receiving approval and acceptance from the local Sanitary Sewer Department,”

and for providing Inverness with proof of that acceptance. The lines MPB installed

were then to be “dedicated to the appropriate governmental agency.” In return,

Inverness promised to pay MPB roughly $650,000 (subject to agreed-upon additions

and deductions) in installments amounting to 90 percent of the work completed at the

end of each month. Inverness would release the final 10 percent retainage and pay any

balance upon the project’s completion.

B. The Inspection & Falling Out

{¶6} MPB’s work on Section 3 of the Landings was completed and approved

by December 2016. It could not begin its work on Section 4 until June 2017. After

installing the Section 4 line, MPB performed the necessary testing and sought

regulatory approval, just as it had for Section 3.

{¶7} Section 3.9.8 of the County’s regulations regarding sanity sewer lines

required the developer to flush the newly installed sanitary sewer lines with water,

then send a camera through the pipes:

[S]anitary sewers must be cleaned and televised (videotaped) by the

developer or his representative prior to seventy-five percent (75%)

release. The camera shall be set on skids and adjusted so that the bottom

3 OHIO FIRST DISTRICT COURT OF APPEALS

of the lens coincides with twenty-five percent (25%) of the diameter of

the sewer line being televised. All work covered in this section shall be

witnessed by a Greene County Sanitary Engineering Department

Inspector.

...

During the course of the videotaping, should the camera lens

encounter standing water, the sanitary sewer in that area shall be

considered unacceptable and shall be dug up and replaced.

Section 3.8 of the same regulations also permitted the County, after watching the

video, to demand that a contractor remedy “any misalignment, displaced pipe, or any

other defects” discovered in the pipe.

{¶8} MPB hired Tele-Vac to perform this “TV inspection” test (i.e., the video

recording of the pipe). Upon reviewing the TV inspection test, Randy Gilbert, the

Sanitary Engineer and Assistant Director of the Greene County Sanitary Engineering

Department, informed Inverness and MPT that the lines for Section 4 had failed the

inspection. Gilbert testified that the County had rejected the lines because the camera

had captured “multiple bellies”—meaning multiple spans of pipe where standing water

had accumulated. The interested parties discussed the issues in a meeting on January

9, 2018, after which Gilbert agreed that the County would review its determination.

{¶9} On January 26, Inverness sent MPB a notice of default, citing as its

reason the County’s disapproval of “significant portions of the Sanitary Sewer Work.”

The notice gave MPB three days to cure the breach, or else Inverness would rescind

the contract and seek to recover for the cost of substitute performance, as well as any

consequential damages.

{¶10} On February 8, Gilbert sent Inverness a letter reiterating that the

4 OHIO FIRST DISTRICT COURT OF APPEALS

County had inspected “two spans of sewer and found that they do not meet the

required standards for acceptance.” Gilbert’s letter stated that “[u]ntil these two spans

are removed and installed to the design requirements” in the County’s regulations, “no

service permits will be issued for the lots intended to utilize these spans.” Neither party

sought review of the County’s regulatory determination in the court of common pleas

under R.C. 2506.01 within the 30 days allotted by R.C. 2505.07.

C. The Federal Court Litigation

{¶11} Ten months later, MPB filed suit against the County and Ronald

Volkerding (the director of the County’s Sanitary Engineering Department) in the

United States District Court for the Southern District of Ohio, and joined Inverness as

a necessary party. Mt. Pleasant Blacktopping Co. v. Greene Cty. (“MPB I”), 2021 U.S.

Dist. LEXIS 34162, *7 (S.D. Ohio Feb. 21, 2021). In that suit, MPB asserted claims

under 42 U.S.C. 1983, alleging that the County’s regulations were so vague, or else that

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
2025 Ohio 284, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mt-pleasant-blacktopping-co-inc-v-inverness-group-inc-ohioctapp-2025.