J.J.O. Constr., Inc. v. Baljak, 06ap-1300 (8-14-2007)

2007 Ohio 4126
CourtOhio Court of Appeals
DecidedAugust 14, 2007
DocketNo. 06AP-1300.
StatusPublished
Cited by1 cases

This text of 2007 Ohio 4126 (J.J.O. Constr., Inc. v. Baljak, 06ap-1300 (8-14-2007)) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
J.J.O. Constr., Inc. v. Baljak, 06ap-1300 (8-14-2007), 2007 Ohio 4126 (Ohio Ct. App. 2007).

Opinion

OPINION
{¶ 1} Joseph Baljak (individually "Baljak") and J.R.B. Concrete and Masonry, Inc. (individually "JRB"), defendants-appellants, appeal from a judgment of the Franklin County Court of Common Pleas, in which the court granted summary judgment to J.J.O. Construction, Inc. ("JJO"), plaintiff-appellee.

{¶ 2} JRB is a concrete and masonry contractor. JRB was incorporated in September 1993, but its articles of incorporation were cancelled in February 1999. Baljak is the owner of JRB. JJO is a general construction contractor. WXZ/Retail Group, L.L.C., *Page 2 hired JJO to construct a retail building. In August 2004, JJO subcontracted with JRB for JRB to perform various masonry tasks associated with construction of the retail building, and JRB issued a warranty guaranteeing its work in December 2004. The superintendent for JJO "approved" the work performed by JRB, and JRB was paid for such work.

{¶ 3} On March 30, 2005, the city of Columbus ("City") issued to JJO a notice of non-compliance of construction, which mandated that the concrete installed by JRB be replaced. On June 3 and 15, 2005, JJO informed JRB in writing that it must replace the non-compliant concrete because the concrete contained excess water, and JRB failed to obtain the necessary inspections and approvals from the City for the construction of the sidewalks and aprons. After JRB did not remedy the defects, JJO contracted with another masonry company, which completed the concrete replacement for $35,301.11, plus $6,789.12 for travel, lodging, and supervision expenses.

{¶ 4} On October 26, 2005, JJO filed the present action against Baljak and JRB, alleging breach of contract and breach of warranty. On September 6, 2006, JJO filed a motion for summary judgment. In its motion, JJO contended that JRB and Baljak breached their contract by failing to obtain the necessary permits and inspections from the City, contrary to the provisions in the contract that required JRB to do so, and breached its warranty to repair any defects or reimburse JJO for any defective work repaired by third parties. On October 24, 2006, the trial court granted summary judgment to JJO, finding Baljak and JRB jointly and severally liable for the replacement costs of the concrete based upon both breach of contract and breach of warranty. On December 6, 2006, the trial court entered a judgment against JRB and Baljak for $42,090.23. JRB and *Page 3 Baljak (hereafter collectively "appellants") appeal the judgment of the trial court, asserting the following assignment of error:

The Trial Court Committed Prejudicial Error When It Granted Appellee's Motion for Summary Judgment Because The Evidence Established That There Were Genuine Issues Of Material Fact Indicating That Appellant Did Not Breach The Terms Of The Contract Or, In The Alternative, Breach was Legally Excused.

{¶ 5} In their sole assignment of error, appellants argue that the trial court erred in granting summary judgment to JJO based upon breach of contract. When reviewing a motion for summary judgment, courts must proceed cautiously and award summary judgment only when appropriate.Franks v. The Lima News (1996), 109 Ohio App.3d 408. Civ.R. 56(C) provides that, before summary judgment may be granted, it must be determined that: (1) no genuine issue as to any material fact remains to be litigated; (2) the moving party is entitled to judgment as a matter of law; and (3) it appears from the evidence that reasonable minds can come to but one conclusion, and viewing the evidence most strongly in favor of the non-moving party, that conclusion is adverse to the non-moving party. State ex rel. Howard v. Ferreri (1994),70 Ohio St.3d 587, 589. When reviewing the judgment of the trial court, an appellate court reviews the case de novo. Franks, supra.

{¶ 6} Generally, the elements for a breach of contract are that a plaintiff must demonstrate by a preponderance of the evidence: (1) that a contract existed; (2) that the plaintiff fulfilled his obligations; (3) that the defendant failed to fulfill his obligations; and (4) that damages resulted from this failure. Lawrence v. Lorain Cty. CommunityCollege (1998), 127 Ohio App.3d 547, 548-549. "When the facts presented in a case are *Page 4 undisputed, whether they constitute a performance or a breach of the contract, is a question of law for the court." Luntz v. Stern (1939),135 Ohio St. 225, 247.

{¶ 7} Appellants present three arguments under their assignment of error. Appellants first assert that it did not breach its contract with JJO because it was impossible to obtain permits or inspections, as only the owner of the property may secure the permits. Appellants also assert that JJO's actions in approving the work of appellants waived any claim that appellants breached the contract. Further, appellants contend that Baljak cannot be held jointly and severally liable because he did not sign the contract at issue.

{¶ 8} However, the trial court rendered summary judgment to JJO not only based upon appellants' breach of contract, but also their breach of warranty. Appellants' assignment of error does not challenge the trial court's decision with regard to JJO's breach of warranty claim, and appellants do not present any argument addressing the trial court's granting of summary judgment on that ground. After a review of the record, we find summary judgment was proper based upon appellants' breach of warranty. On December 7, 2004, JRB, through Baljak, executed and delivered to JJO a document entitled "ONE YEAR GUARANTY," which provided, in full:

We, JRB. CON., hereby guaranty that the CON. work performed at: Advance Auto Parts 5636-40 Gender Rd. Canal Winchester, OH 43110 has been done in accordance with the Drawings, Specifications and Local Codes and that the work as installed will fulfill the requirements included in the Specifications. We agree to repair or replace any of our work, together with any other adjacent work which may be displaced by so doing, that may prove to be defective in its workmanship or material within a period of one year from the date of acceptance of the above mentioned work by the *Page 5 Owner; ordinary wear, unusual abuse and neglect are excluded.

In the event of our failure to comply with the above mentioned conditions within a reasonable period of time, as determined by and after being notified in writing by J.J.O. Construction, Inc., we do hereby authorize J.J.O. Construction, Inc. to proceed to have said defects repaired at our expense, and we will honor and pay the costs associated with said repair work.

We have also supplied all Manufacturers' Warranties, Submittals, and Final Lien Waivers to J.J.O. Construction, Inc.

Signature /s/ Joe Baljak Date 12-7-04

Print Name Joe Baljak Title. V.P.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Mt. Pleasant Blacktopping Co., Inc. v. Inverness Group, Inc.
2025 Ohio 284 (Ohio Court of Appeals, 2025)

Cite This Page — Counsel Stack

Bluebook (online)
2007 Ohio 4126, Counsel Stack Legal Research, https://law.counselstack.com/opinion/jjo-constr-inc-v-baljak-06ap-1300-8-14-2007-ohioctapp-2007.