Mid Am. Constr., L.L.C. v. Univ. of Akron

2019 Ohio 3863
CourtOhio Court of Appeals
DecidedSeptember 24, 2019
Docket18AP-846
StatusPublished
Cited by9 cases

This text of 2019 Ohio 3863 (Mid Am. Constr., L.L.C. v. Univ. of Akron) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Mid Am. Constr., L.L.C. v. Univ. of Akron, 2019 Ohio 3863 (Ohio Ct. App. 2019).

Opinion

[Cite as Mid Am. Constr., L.L.C. v. Univ. of Akron, 2019-Ohio-3863.]

IN THE COURT OF APPEALS OF OHIO

TENTH APPELLATE DISTRICT

Mid American Construction, LLC, :

Plaintiff/Counter : Defendant-Appellee, : v. : The University of Akron, : No. 18AP-846 Defendant/Counter Plaintiff/ (Ct. of Cl. No. 2016-00685JD) Third-Party Plaintiff-Appellant, : (REGULAR CALENDAR) v. :

The Fidelity and Deposit Company : of Maryland, : Third-Party Defendant-Appellee, :

D E C I S I O N

Rendered on September 24, 2019

On brief: Roetzel & Andress, LPA, Thomas L. Rosenberg, Stephen W. Funk, and Nathan Pangrace, for appellees. Argued: Thomas L. Rosenberg.

On brief: Dave Yost, Attorney General, William C. Becker, James E. Rook, and Howard H. Harcha, IV, for appellant. Argued: William C. Becker.

APPEAL from the Court of Claims of Ohio SADLER, J. {¶ 1} Defendant/counter plaintiff/third-party plaintiff-appellant, The University of Akron ("University"), appeals from a judgment of the Court of Claims of Ohio in favor of No. 18AP-846 2

plaintiff/counter defendant-appellee, Mid American Construction, LLC ("MAC"), and third-party defendant-appellee, Fidelity and Deposit Company of Maryland ("Fidelity"). For the reasons that follow, we affirm. I. FACTS AND PROCEDURAL HISTORY {¶ 2} MAC and the University executed a contract on December 12, 2014 ("original agreement"), whereby the University agreed to pay MAC a total of $5,137,700 to act as the general trades contractor for the Zook Hall Renovation Project Phase 2B ("project"). (MAC's Ex. 2.) MAC was not involved with the project's previous phases, which involved demolition and asbestos abatement work along with work on another site to be used as transitional space. MAC's work included, among other items, patching, painting, framing and other carpentry work, tile work, and drywall work. (MAC's Ex. 2.) In accordance with the parties' statutory obligations, MAC executed a surety bond in favor of the University and issued by Fidelity in the penal amount of $5,137,700. {¶ 3} The project was a multi-prime project, which meant the University executed separate agreements with several other contractors including Didado for mechanical, electric, and plumbing ("MEP"), Hampton for fire protection, and S.A. Comunale for HVAC. The scope of MAC's work as general trades contractor included many of the interior finishes in Zook Hall, including the lecture hall/auditorium, classrooms, the science laboratory, the mail room, and various staff offices. MAC's work on the exterior of the building was extensive including the construction of a glass storefront addition on the ground floor and a glass curtain wall addition for the first and second floors with a third floor terrace. MAC's scope of work also included the exterior doors, windows, and a new roof. {¶ 4} MAC did not self-perform any of its construction work on the project. Rather, MAC completed its work through the use of subcontractors and suppliers. Dan Trinetti, MAC's senior project manager, handled day-to-day operations on the project. Chad Zumkehr is MAC's owner and president. {¶ 5} The University also executed separate contracts with a construction manager ("CM"), Thomarios, and a project architect ("A/E"), Stantec. Thomarios employed George Brkich as its project manager. In addition to coordinating the day-to-day activities of the prime contractors, Thomarios drafted the baseline schedule, the conformed schedule, and No. 18AP-846 3

all schedule updates throughout the project. Thomarios employee Ted Whitcomb drafted the baseline schedule prior to the start of the project and later drafted the conformed schedule, which included addenda. {¶ 6} Stantec provided architectural design services and construction administration services and contracted with another firm for engineering services. Stantec employed certified professional architect Ryan McNutt as its project manager. James Haskell, the University's Director of Campus Planning and Space Utilization, acted as the University's project manager and primary representative on the project. {¶ 7} MAC began work on the project in January 2015. The original agreement provided 401 days for completion of the project. Almost immediately, the project experienced delay. An initial delay occurred when the University Dean objected to the placement of MAC's mixing silos near the southeast corner of Zook Hall, as they could be seen from his office. MAC was required to move its silos to a less advantageous position to accommodate the University, though MAC was compensated for the expense. {¶ 8} Numerous other delays occurred on the project thereafter. MAC has argued that a vast majority of the delays were the result of Stantec's and/or Thomarios' untimely execution and delivery of construction change directives ("CCDs"). In this litigation, the University attributed every day of project delay to MAC and stopped paying MAC and its subcontractors on or about September 30, 2015. On December 18, 2015, the University sent MAC a five-day notice of termination, pursuant Section 11.3.1.1 of the general conditions, claiming that MAC failed "to prosecute the Work with the necessary force or in a timely manner." (MAC's Ex. 2.) The University requested that MAC submit a "recovery plan," pursuant to Section 6.6.13.1 of the original agreement, within 15 days and that MAC and a Fidelity representative meet with representatives of the University, Thomarios, and Stantec on December 22, 2015. {¶ 9} At the December 22, 2015 meeting, MAC, with the assistance of its scheduling consultant, James Dougherty, provided a recovery schedule showing that MAC was just 10 days behind schedule, not 83 days as the University had claimed. MAC concedes it did not provide a "recovery plan," as that term is described in Section 6.6.13.2 of the original agreement, but MAC argues the failure of the University, Thomarios, and/or Stantec to provide Request for Information ("RFI") responses and approve CCDs prevented MAC No. 18AP-846 4

from drafting a recovery plan. At the December 22, 2015 meeting, Trinetti used a copy of the floor plan to highlight the areas of the building where there was an RFI pending or an outstanding CCD holding up MAC's work. {¶ 10} On January 7, 2016, the University issued a Notice of Termination to MAC via email which was copied to Fidelity representative Dennis Walsh, wherein the University stated MAC was in "default of its obligations * * * on this project" and MAC's original agreement with the University is "terminated for cause." (University's Ex. C at 1.) The letter also demanded Fidelity notify the University, within ten days, of its intentions with regard to completion of the contract. {¶ 11} MAC received an original signed Notice of Termination on January 13, 2016, four business days later. On or about January 11, 2016, the University denied MAC's subcontractors access to the project. On this same day, the University sent a letter to MAC informing it that subcontractors should cease work or risk not being paid. (MAC's Ex. 61.) At the time of termination, MAC had an outstanding pay application of approximately $1,200,000 for work completed through October 31, 2015. Adding retainage to that number raises the total to $1,455,998.11. (University's Ex. YYY.) The position of the University, however, was that MAC was not entitled to payment for this work because the University had terminated the original agreement for cause.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Charlie's CDJR, L.L.C. v. Charlie's Toledo, Inc.
2026 Ohio 18 (Ohio Court of Appeals, 2026)
Cirotto v. Am. Self Storage of Pickerington
2025 Ohio 1670 (Ohio Court of Appeals, 2025)
W. Environmental Corp. of Ohio v. Hardy Diagnostics
2024 Ohio 3051 (Ohio Court of Appeals, 2024)
LVNV Funding, L.L.C. v. Altahtamoni
2024 Ohio 2082 (Ohio Court of Appeals, 2024)
N. Side Bank & Trust Co. v. Trinity Aviation, L.L.C.
2024 Ohio 590 (Ohio Court of Appeals, 2024)
D.D. v. B.B.
2022 Ohio 1032 (Ohio Court of Appeals, 2022)
Longmire v. Danaci
2020 Ohio 3704 (Ohio Court of Appeals, 2020)
Allen v. Dept. of Adm. Servs. Office of Risk Mgt.
2020 Ohio 1138 (Ohio Court of Appeals, 2020)
2454 Cleveland, L.L.C. v. TWA, L.L.C.
2020 Ohio 362 (Ohio Court of Appeals, 2020)

Cite This Page — Counsel Stack

Bluebook (online)
2019 Ohio 3863, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mid-am-constr-llc-v-univ-of-akron-ohioctapp-2019.