Klausing v. Chef Solutions, 1-07-34 (11-13-2007)

2007 Ohio 6014
CourtOhio Court of Appeals
DecidedNovember 13, 2007
DocketNo. 1-07-34
StatusPublished
Cited by2 cases

This text of 2007 Ohio 6014 (Klausing v. Chef Solutions, 1-07-34 (11-13-2007)) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Klausing v. Chef Solutions, 1-07-34 (11-13-2007), 2007 Ohio 6014 (Ohio Ct. App. 2007).

Opinion

OPINION *Page 2
{¶ 1} Plaintiff-appellant, Ronald J. Klausing ("Klausing") brings this appeal from the judgment of the Court of Common Pleas of Allen County staying the case while arbitration is completed.

{¶ 2} On November 1, 2000, Klausing and defendant-appellee Chef Solutions, Inc. ("SCIS") entered into a merger agreement. Part of the agreement concerned the "Potato Line Payment," which was the repayment of $3.5 million contingent upon increased potato production and earnings levels beyond the benchmark. Other contingencies were included in the contract which required immediate repayment plus interest regardless of whether the benchmark was reached. To calculate performance in a fiscal year, SCIS was required to submit a "Potato Line Certificate" by the deadline. This certificate was not submitted by *Page 3 the deadline. Anticipating a dispute over the calculations, the parties provided a dispute resolution procedure in which an accounting firm would be hired to arbitrate the disputed calculations.

{¶ 3} On May 18, 2005, Klausing filed a complaint alleging that SCIS owes him $3.5 million plus interest. Klausing claimed, among other things, that one of the contingencies had occurred, thus causing the loan to become due and owing immediately. SCIS claimed that the matter could not be brought in the trial court because the contract required the matter be taken to the arbitrator. On August 23, 2005, the trial court dismissed the complaint with prejudice. Klausing appealed the dismissal to this court. On May 1, 2006, this court reversed the judgment of the trial court and sustained both assignments of error raised by Klausing.

{¶ 4} The basis for the prior ruling of this court was the unequivocal provisions of the contract which stated as follows.

Within twenty (20) business days after receipt of a Potato Line Certificate, Klausing shall notify SCIS of his agreement or disagreement with SCIS's Potato Line Calculations, Klausing shall provide SCIS with a certificate containing Klausing's calculation of production levels and EBITDA from the beginning of the applicable fiscal year end calculated in accordance with Section 2.8(c) and the amount of the Potato Line Payment, if any, to which Klausing asserts he is entitled pursuant to Section 2.8(a), 2.8(b), or 2.8(d) (collectively "Klausing's Potato Line Calculations"). * * * If Klausing and SCIS do not resolve such differences within ten (10) days after the date of delivery by Klausing of Klausing's Potato Line Calculations, Klausing and *Page 4 SCIS shall select (or, absent agreement of Klausing and SCIS, the American Arbitration Association in New York City shall designate) an accounting firm of recognized national standing with substantial experience in the food business (the "Potato Line Arbitrator") to resolve the disputed matters (the "Potato Line Disputed Matters") and to calculate the amount of the Potato Line Payment, if any to which Klausing is entitled pursuant to Section 2.8(a), 2.8(b) or 2.8(d); provided that the Potato Line Arbitrator's determination of such amounts shall not be less that SCIS's Potato Line Calculations or more than Klausing's Potato Line Calculations; provided further that the Potato Line Disputed Matters shall be the only items to be determined by the Potato Line Arbitrator.

Contract, 18. After reviewing the contract, this court determined that the above section was the only portion of the contract that set forth a provision for arbitration. This court then continued to find that since SCIS, by its own admission, had denied Klausing access to the financial records necessary for Klausing to calculate and deliver his own Potato Line Certificate, the arbitration clause had not yet been triggered. The dismissal was reversed and the matter was remanded for further proceedings.

{¶ 5} On January 31, 2006, Klausing filed a motion for default judgment based upon SCIS's failure to file an answer to the complaint. SCIS filed its response to the motion for default judgment on February 23, 2007, claiming that it did not have to file an answer because all of the provisions were subject to arbitration. On March 5, 2007, the trial court denied the motion for default judgment and ordered Klausing to provide its Potato Line Certificate which would *Page 5 permit arbitration to proceed. On March 28, 2007, SCIS filed a motion to dismiss. On April 17, 2007, the trial court granted a stay of the case pending arbitration since Klausing had filed his Potato Line Certificate. Klausing appeals from this judgment and raises the following assignments of error.

The [trial court] erred in staying this case in favor of arbitration because [SCIS] materially breached the arbitration clause upon which they rely, rendering it unenforceable, and because [SCIS has] still failed to satisfy the conditions precedent required to invoke the arbitration clause.

The [trial court] erred in staying this case in favor of arbitration because [Klausing's] claims fall outside the scope of the limited arbitration clause at issue.

The [trial court] erred in ruling that [SCIS was] not in default.

{¶ 6} Klausing first claims that the trial court erred in granting the stay in favor of arbitration because the arbitration clause is unenforceable and the required conditions precedent still have not been filed. The contract provides as follows.

(e) SCIS shall, as soon as reasonably practicable after the applicable fiscal year end, but in any event by February 5 following such fiscal year end, prepare and deliver to Klausing a certificate (a "Potato Line Certificate") of SCIS stating potato production levels and EBITDA from the beginning of the applicable fiscal year until the applicable fiscal year end, calculated in accordance with Section 2.8(c), and the amount of the Potato Line Payment, if any, to which Klausing is entitled pursuant to Section 2.8(a), 2.8(b) or 2.8(d) ("SCIS's Potato Line Calculation").

*Page 6

(f) Following delivery of a Potato Line Certificate by SCIS, SCIS shall cooperate with

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Kellogg v. Griffiths Health Care Group
2011 Ohio 1733 (Ohio Court of Appeals, 2011)
Marion v. Hoffman
2010 Ohio 4821 (Ohio Court of Appeals, 2010)

Cite This Page — Counsel Stack

Bluebook (online)
2007 Ohio 6014, Counsel Stack Legal Research, https://law.counselstack.com/opinion/klausing-v-chef-solutions-1-07-34-11-13-2007-ohioctapp-2007.