Council of Smaller Enterprises v. Gates, McDonald & Co.

687 N.E.2d 1352, 80 Ohio St. 3d 661
Ohio Supreme Court·Decided January 14, 1998·No. No. 96-1302·Published·Cited by 180 cases

Opinions

Alice Robie Resnick, J.

The issue for resolution is whether, in the circumstances presented here, a court or an arbitrator determines the construction and consequences of the ninety-day demand provision in the parties’ Service Agree[664]*664ment. For the reasons that follow, we find that a presumption in favor of the arbitrability of the parties’ dispute over the interpretation of Section 7.7(a)(i) of the agreement applies in the circumstances of this case, and that COSE, the party resisting arbitration, has failed to overcome the presumption. We affirm the judgment of the court of appeals.

The parties do not disagree that the underlying issues regarding fees are matters clearly within the scope of the agreement to arbitrate. The parties’ disagreement centers on the interpretation to be given to the section of the agreement setting forth the ninety-day provision. COSE asserts that the ninety-day arbitration demand provision is a “condition precedent” that qualifies the agreement to arbitrate, and that indicates the parties’ intent to have a court, not an arbitrator, construe Section 7.7(a)(i) of the agreement. Adoption of COSE’s position would lead to the conclusion that the trial court therefore properly undertook to construe Section 7.7(a)(i), and properly determined that Gates McDonald’s claim for the fees was untimely, so that arbitration is unwarranted.

Gates McDonald, on the other hand, asserts that the parties intended to have an arbitrator construe the meaning of Section 7.7(a)(i), and that, even if that section would operate as a “condition precedent” to the arbitration of the fee disputes, it is up to the arbitrator to make that determination. Adoption of Gates McDonald’s position would lead to the conclusion that the parties must submit the “dispute” or “controversy” over the ninety-day demand provision to arbitration, with the arbitrator ruling on the implications of the ninety-day demand provision as a threshold matter requisite to any consideration of the fee disputes on the merits.

Initially, our consideration of this case recognizes that the arbitration clause agreed to by the parties in Section 7.7(a) of the Service Agreement is extremely broad. That clause begins with the language that “[a]ll disputes and controversies of every kind” shall be submitted to arbitration. The unqualified breadth of this language supports Gates McDonald’s preferred construction of the parties’ intent regarding the overall arbitration provision. At the same time, the employment by the parties of this opening broad language lessens the strength of COSE’s position regarding the parties’ intent to have the subsequent ninety-day demand provision specifically qualify the earlier language of the clause.

Our consideration is further influenced by the decision of the United States Supreme Court in John Wiley & Sons, Inc. v. Livingston (1964), 376 U.S. 543, 556-557, 84 S.Ct. 909, 918, 11 L.Ed.2d 898, 908-909, in which the court stated:

“Questions concerning the procedural prerequisites to arbitration do not arise in a vacuum; they develop in the context of an actual dispute about the rights of the parties to the contract or those covered by it.

« jfc $ %

[665]*665“Doubt whether grievance procedures or some part of them apply to a particular dispute, whether such procedures have been followed or excused, or whether the unexcused failure to follow them avoids the duty to arbitrate cannot ordinarily be answered without consideration of the merits of the dispute which is presented for arbitration.

« * * *

“Once it is determined * * * that the parties are obligated to submit the subject matter of a dispute to arbitration, ‘procedural’ questions which grow out of the dispute and bear on its final disposition would be left to the arbitrator.”

Although our decision is affected by the above concerns, the telling question in this case concerns what the parties agreed to empower an arbitrator to decide, as revealed by an examination of the parties’ agreement. The answer to this question will resolve whether the disagreement over the ninety-day demand provision is a “procedural question” growing out of the dispute and bearing on its final disposition, so that it should be referred to the arbitrator in the sense discussed in John Wiley & Sons.

In AT & T Technologies, Inc. v. Communications Workers of Am. (1986), 475 U.S. 643, 106 S.Ct. 1415, 89 L.Ed.2d 648, the United States Supreme Court summarized four general principles, developed in prior decisions of that court, to be applied when considering the reach of an arbitration clause. The essence of these general principles, set out primarily in the “Steelworkers Trilogy” (Steelworkers v. Am. Mfg. Co. [1960], 363 U.S. 564, 80 S.Ct. 1343, 4 L.Ed.2d 1403; Steelworkers v. Warrior & Gulf Navigation Co. [1960], 363 U.S. 574, 80 S.Ct. 1347, 4 L.Ed.2d 1409; Steelworkers v. Enterprise Wheel & Car Corp. [1960], 363 U.S. 593, 80 S.Ct. 1358, 4 L.Ed.2d 1424) is pertinent to our review, and provides a framework for our inquiry.1

The first principle is that “ ‘arbitration is a matter of contract and a party cannot be required to submit to arbitration any dispute which he has not agreed so to submit.’ * * * This axiom recognizes the fact that arbitrators derive their authority to resolve disputes only because the parties have agreed to submit such grievances to arbitration.” AT & T Technologies, 475 U.S. at 648-649, 106 S.Ct. at 1418, 89 L.Ed.2d at 655, quoting Warrior & Gulf, supra, 363 U.S. at 582, 80 S.Ct. at 1353, 4 L.Ed.2d at 1417.

[666]*666The second principle is that “the question of arbitrability — whether a[n] * * * agreement creates a duty for the parties to arbitrate the particular grievance — is undeniably an issue for judicial determination. Unless the parties clearly and unmistakably provide otherwise, the question of whether the parties agreed to arbitrate is to be decided by the court, not the arbitrator.” Id., 475 U.S. at 649, 106 S.Ct. at 1418, 89 L.Ed.2d at 656.

The third rule is, “in deciding whether the parties have agreed to submit a particular grievance to arbitration, a court is not to rule on the potential merits of the underlying claims.” Id., 475 U.S. at 649, 106 S.Ct. at 1419, 89 L.Ed.2d at 656.

The fourth principle is that “where the contract contains an arbitration clause, there is a presumption of arbitrability in the sense that ‘[a]n order to arbitrate the particular grievance should not be denied unless it may be said with positive assurance that the arbitration clause is not susceptible of an interpretation that covers the asserted dispute. Doubts should be resolved in favor of coverage.’ ” Id.,Id., 475 U.S. at 650, 106 S.Ct. at 1419, 89 L.Ed.2d at 656, quoting Warrior & Gulf, supra, 363 U.S. at 582-583, 80 S.Ct. at 1353, 4 L.Ed.2d at 1417.

Free access — add to your briefcase to read the full text and ask questions with AI

Council of Smaller Enterprises v. Gates, McDonald & Co., 687 N.E.2d 1352, 80 Ohio St. 3d 661 (Ohio 1998).

687 N.E.2d 1352 (Council of Smaller Enterprises v. Gates, McDonald & Co.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Larsen Medina, L.L.C. v. Echelon Senior Living Group, L.L.C.
2025 Ohio 2282 (Ohio Court of Appeals, 2025)
Fetzer v. Miley
2019 Ohio 4578 (Ohio Court of Appeals, 2019)
Kaminsky v. New Horizons Computer Learning Ctr. of Cleveland
2016 Ohio 1468 (Ohio Court of Appeals, 2016)
Ohio Council 8 v. Marion
2016 Ohio 1144 (Ohio Court of Appeals, 2016)
Arnold v. Burger King
2015 Ohio 4485 (Ohio Court of Appeals, 2015)
Toledo Police Command Officers' Assn. v. Toledo
2014 Ohio 4119 (Ohio Court of Appeals, 2014)
Doe v. Vineyard Columbus
2014 Ohio 2617 (Ohio Court of Appeals, 2014)
Craver v. Tomsic
2014 Ohio 2603 (Ohio Court of Appeals, 2014)
Kettering Health Network v. Caresource
2014 Ohio 956 (Ohio Court of Appeals, 2014)
Sultaana v. Drummond Fin. Servs., L.L.C.
2014 Ohio 938 (Ohio Court of Appeals, 2014)
Villas Di Tuscany Condominium Assn., Inc. v. Villas Di Tuscany
2014 Ohio 776 (Ohio Court of Appeals, 2014)
Fifth Third Bank v. Rowlette
2013 Ohio 5777 (Ohio Court of Appeals, 2013)
McFarren v. Emeritus at Canton
2013 Ohio 3900 (Ohio Court of Appeals, 2013)
Matheny v. Norton
2013 Ohio 3798 (Ohio Court of Appeals, 2013)
Traton News, LLC v. Traton Corp.
528 F. App'x 525 (Sixth Circuit, 2013)
Schneider v. Shafran
2013 Ohio 380 (Ohio Court of Appeals, 2013)
Skerlec v. Ganley Chevrolet, Inc.
2012 Ohio 5748 (Ohio Court of Appeals, 2012)