Craver v. Tomsic

2014 Ohio 2603
CourtOhio Court of Appeals
DecidedJune 16, 2014
Docket13 CAE 11 0078
StatusPublished
Cited by1 cases

This text of 2014 Ohio 2603 (Craver v. Tomsic) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Craver v. Tomsic, 2014 Ohio 2603 (Ohio Ct. App. 2014).

Opinion

[Cite as Craver v. Tomsic, 2014-Ohio-2603.]

COURT OF APPEALS DELAWARE COUNTY, OHIO FIFTH APPELLATE DISTRICT

PAUL L. CRAVER, DBA JUDGES: PAUL L. CRAVER, HOUSEWRIGHT Hon. William B. Hoffman, P.J. Hon. Sheila G. Farmer, J. Plaintiff-Appellee Hon. Patricia A. Delaney, J.

-vs- Case No. 13 CAE 11 0078

RICK R. TOMSIC, ET AL. OPINION Defendants-Appellants

CHARACTER OF PROCEEDING: Appeal from the Delaware County Court of Common Pleas, Case No. 13 CV H 03 0207

JUDGMENT: Affirmed

DATE OF JUDGMENT ENTRY: June 16, 2014

APPEARANCES:

For Plaintiff-Appellee For Defendants-Appellants

BEAU K. RYMERS MARK SKAKUN 140 E. Town Street, Suite 1015 JUSTIN S. GREENFELDER Columbus, Ohio 43215 Buckingham, Doolittle & Burroughs, LLC 4518 Fulton Drive, N.W., Suite 200 And P.O. Box 35548 Canton, Ohio 44735-5548 THOMAS L. HART Isaac, Wiles, Burkholder & Teetor, LLC Two Miranova Place, Suite 700 Columbus, Ohio 43215 Delaware County, Case No. 13 CAE 11 0078 2

Hoffman, P.J.

{¶1} Defendants-appellants Rick R. Tomsic, et al. appeal the October 23, 2013

Judgment Entry entered by the Delaware County Court of Common Pleas, which

granted, in part, the petition for an order directing arbitration and for stay of litigation

filed by plaintiff-appellee Paul Craver, dba Paul L. Craver Housewright (“Craver”).

STATEMENT OF THE FACTS AND CASE

{¶2} In February, 2010, Appellants entered into a contract with Craver for the

construction of a new home (“the Contract”). The Contract price for the home was

$2,491,300. The parties agreed the home would be constructed within 445 working

days from the time construction commenced.

{¶3} The Contract included a dispute resolution provision, which reads:

Any claim or controversy between the parties arising out of or

relating to this agreement or the breach thereof will be resolved as follows:

23.1 The parties will meet and confer in good faith in an attempt to

resolve the dispute or problem.

23.2 In the event that the parties are unable to resolve the claim or

controversy, either party may notify the other that the matter must be

submitted to mediation or binding arbitration in Columbus, Delaware

County, Ohio in accordance with the applicable provisions of Chapter

2711 of the Ohio Revised Code, excepting that the following terms and

conditions will control and supersede and/or supplement the provisions of

Chapter 2711: Delaware County, Case No. 13 CAE 11 0078 3

23.2.1 The mediation and/or arbitration will be conducted within 60

days of the selection of the mediator and/or arbitrator(s).

23.2.2 In the event a party fails or refuses to select a mediator or

arbitrator, the provisions of Ohio Revised Code Section 2711.03 apply.

***

23.2.6 In the event of any claim or controversy necessitating

dispute resolution, the Work of the Contractor will continue, as time is of

the essence, and with respect to any such claim or controversy, the

parties will be bound by the determination reached as a result of the

dispute resolution procedures.

23.3 Nothing herein contained shall bar the right of either party to

obtain injunctive relief against threatened conduct that will cause loss or

damages, under the usual equity rules, including the applicable rules for

obtaining preliminary injunctions.

{¶4} In addition to the Contract with Craver, Appellants also entered into a

verbal agreement with Phyllis Craver (“Architect”), Paul Craver’s wife, for all

architectural services on the design and construction of the home. Architect provided all

architectural drawings, designs, and plans for Appellants’ new residence.

{¶5} The completion date set forth in the Contract passed with construction still

progressing. Appellants continually pushed Craver for a new completion date with

Craver eventually promising the residence would be completed on October 1, 2012.

The October 1, 2012 deadline arrived, and the home was still not complete. Craver

walked off the job on or about November 5, 2012. Delaware County, Case No. 13 CAE 11 0078 4

{¶6} On December 31, 2012, Craver filed a mechanic's lien against the

property in the amount of $133,329.27. Craver was served with Appellants’ R.C.

1311.11 Notice to Commence Suit, which provided:

You are hereby given formal notice pursuant to Ohio Revised Code

Section 1311.11(B) to commence suit as required by the statute upon your

captioned Mechanics [sic] Lien.

Failure to commence suit within 60 days after receipt of this Notice

will result in discharge of the captioned Mechanics [sic] Lien.

{¶7} On March 8, 2013, Craver filed a Complaint against Appellants, alleging

breach of contract and unjust enrichment, and seeking foreclosure on the mechanic’s

lien. In the Complaint, Craver acknowledged the arbitration provision in the Contract,

but asserted R.C. Chapter 1311 required him to file the Complaint in order to preserve

his rights under the mechanic’s lien. Craver also indicated he did not intend to waive

his right to seek arbitration under the Contract.

{¶8} Appellants filed an answer and counterclaim against Craver and Architect

on April 24, 2013. As against Craver, Appellants alleged breach of contract,

negligence, fraud, violations of the Ohio Consumer Sales Practices Act, breach of

warranty, civil conspiracy, breach of oral contract, and unjust enrichment. Appellants

also sought declaratory judgment against Craver, asking the trial court to find Craver

had waived his right to seek mediation or arbitration under the Contract by filing the

mechanic’s lien and subsequently filing his Complaint. As against Architect, Appellants

alleged breach of contract, negligence/malpractice, fraud, violations of the Ohio

Consumer Sales Practices Act, and civil conspiracy. Delaware County, Case No. 13 CAE 11 0078 5

{¶9} On August 27, 2013, Craver and Architect filed a petition for an order

directing arbitration and requesting a stay of litigation pursuant to R.C. 2711.02 and

2711.03. In their petition, Craver and Architect asserted the Contract governed dispute

resolution procedures and they had complied with those procedures. Craver and

Architect claimed the parties had made a good faith attempt to resolve the matter, but

were unable to do so; therefore, pursuant to the Contract, they were allowed to notify

Appellants the dispute must be submitted to mediation or binding arbitration. Although

Craver and Architect notified Appellants of their desire to arbitrate the matter, Appellants

responded with an unwillingness to do so. Craver and Architect requested the trial court

issue an order directing arbitration and stay the action pending arbitration. Craver and

Architect attached to the petition various correspondences between their attorney and

Appellants’ attorney regarding settlement attempts and their desire to arbitrate.

{¶10} In their brief in opposition, Appellants asserted the trial court should deny

Craver and Architect’s petition on several grounds. First, Appellants maintained

arbitration was not the sole method of dispute resolution under the terms of the

Contract. Next, Appellants asserted Craver had waived arbitration for taking action

inconsistent with the right to arbitrate. Appellants also contended their claims against

Architect were not arbitrable as she was not a party to the Contract. Appellants further

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Aljaberi v. Neurocare Ctr., Inc.
2019 Ohio 2181 (Ohio Court of Appeals, 2019)

Cite This Page — Counsel Stack

Bluebook (online)
2014 Ohio 2603, Counsel Stack Legal Research, https://law.counselstack.com/opinion/craver-v-tomsic-ohioctapp-2014.