Zachry Construction Corporation v. Port of Houston Authority of Harris County, Texas

CourtTexas Supreme Court
DecidedAugust 29, 2014
Docket12-0772
StatusPublished

This text of Zachry Construction Corporation v. Port of Houston Authority of Harris County, Texas (Zachry Construction Corporation v. Port of Houston Authority of Harris County, Texas) is published on Counsel Stack Legal Research, covering Texas Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Zachry Construction Corporation v. Port of Houston Authority of Harris County, Texas, (Tex. 2014).

Opinion

IN THE SUPREME COURT OF TEXAS 444444444444 NO . 12-0772 444444444444

ZACHRY CONSTRUCTION CORPORATION, PETITIONER, v.

PORT OF HOUSTON AUTHORITY OF H ARRIS COUNTY , TEXAS, RESPONDENT

4444444444444444444444444444444444444444444444444444 ON PETITION FOR REVIEW FROM THE COURT OF APPEALS FOR THE FOURTEENTH DISTRICT OF TEXAS 4444444444444444444444444444444444444444444444444444

Argued November 6, 2013

CHIEF JUSTICE HECHT delivered the opinion of the Court, in which JUSTICE GREEN , JUSTICE GUZMAN , JUSTICE DEVINE , and JUSTICE BROWN joined.

JUSTICE BOYD filed a dissenting opinion, in which JUSTICE JOHNSON , JUSTICE WILLETT , and JUSTICE LEHRMANN joined.

The common law permits a contractor to recover damages for construction delays caused by

the owner, but the parties are free to contract differently. A contractor may agree to excuse the owner

from liability for delay damages, even when the owner is at fault. The contractor thereby assumes

the risk of delay from, say, an owner’s change of plans, even if the owner is negligent. But can a no-

damages-for-delay provision shield the owner from liability for deliberately and wrongfully

interfering with the contractor’s work? Before this case, a majority of American jurisdictions—including Texas courts of appeals, courts in all but one jurisdiction to consider the

issue, and five state legislatures—had answered no. We agree with this overwhelming view and also

conclude that the answer is the same if the owner is a local governmental entity for which immunity

from suit is waived by the Local Government Contract Claims Act.1

Contractors are usually paid as work progresses and, in exchange for payment, must waive

liens and claims related to the work paid for. But does such a general waiver release a claim the

contractor has already asserted? Not, we think, unless the claim is specifically mentioned or the

intent to do so is clear.

Our conclusions require us to reverse the judgment of the court of appeals2 and remand the

case to that court for further proceedings.

I3

Petitioner, Zachry Construction Corporation, contracted to construct a wharf on the Bayport

Ship Channel for respondent, the Port of Houston Authority of Harris County, Texas. The wharf

would be a concrete deck supported by piers, extending out over the water. It would be used for

loading and unloading ships carrying containerized goods and would be long enough—1,660

1 T EX . L O C . G O V ’T C O D E §§ 271.151-.160.

2 377 S.W .3d 841 (Tex. App.— Houston [14th Dist.] 2012).

3 The evidence in this case was hotly disputed at almost every turn. W e do not pause in this rehearsal of the proceedings to note each disagreement. In reviewing any case tried to a jury, we must view the evidence “in the light most favorable to the verdict”— in this case a verdict for the petitioner— “crediting favorable evidence if reasonable jurors could, and disregarding contrary evidence unless reasonable jurors could not” and so summarize the evidence in that light. Cruz v. Andrews Restoration, Inc., 364 S.W .3d 817, 819 (Tex. 2012) (citing City of Keller v. Wilson, 168 S.W .3d 802, 807 (Tex. 2005)).

2 feet—for two ships to dock stern to bow. It would be built in five sections, each 135 feet wide and

332 feet long. The channel was to be dredged to a depth of 40 feet beneath the wharf and

surrounding area, and revetment placed along the shore beneath the wharf to prevent erosion. The

total cost was $62,485,733.

The contract made Zachry an independent contractor in sole charge of choosing the manner

in which the work would be conducted. Specifically, Section 5.10 of the contract provided:

The Port Authority shall not have the right to control the manner in which or prescribe the method by which the Contractor [Zachry] performs the Work. As an independent Contractor, the Contractor shall be solely responsible for supervision of and performance of the Work and shall prosecute the Work at such time and seasons, in such order or precedence, and in such manner, using such methods as Contractor shall choose . . . .

The provision benefitted the Port, insulating it from the liability to which it would be exposed were

it exercising control over Zachry’s work.4 Still, the Port was fully engaged in reviewing Zachry’s

plans and overseeing construction.

Zachry’s plan was innovative. It would use soil dredged from the channel to construct an 8-

foot-wide earthen berm starting from the shore at either end of the worksite, extending out toward

the center of the channel, then running parallel to the shore, forming a long, flat U-shaped wall in

the channel around the construction area. Zachry would install a refrigerated pipe system in the wall

and down into the channel floor that would carry supercooled brine, freezing the wall to make it

impenetrable to the water in the channel. Zachry would then remove the water from the area between

4 See, e.g., Gen. Elec. Co. v. Moritz, 257 S.W .3d 211, 214 (Tex. 2008) (“Generally, an owner or occupier does not owe a duty to ensure that independent contractors perform their work in a safe manner. But one who retains a right to control the contractor’s work may be held liable for negligence in exercising that right.”) (citations omitted).

3 the wall and the shore. In this way, Zachry could work “in the dry”, using bulldozers and other land

equipment for the excavation and revetment work. Another advantage to this freeze-wall approach

was that it would lower diesel emissions and require fewer nitrous oxide credits under environmental

laws, giving the Port more flexibility in other construction projects. Zachry believed this approach

would make the work less expensive and allow it to be completed more quickly.

And time was of the essence to the Port. Work began in June 2004 and was to be completed

in two years. But two sections of the wharf had to be completed within 20 months—by February

2006—so that a ship from China could dock, delivering cranes to be used on the wharf. Zachry

agreed to pay $20,000 per day as liquidated damages for missing the deadlines.

Nine months into the project, the Port realized that it would need two 1,000-foot berths to

accommodate the ships it ultimately expected to service. A sixth 332-foot section would have to be

added to the wharf. As a practical matter, only Zachry could perform the additional work, and Zachry

and the Port began discussions on a change order. To complete the two sections of the wharf needed

by February 2006, and to continue to work “in the dry”, Zachry proposed to build another freeze-

wall—a cutoff wall—though the middle of the project, perpendicular to the shoreline out to the

existing wall, splitting the project into two parts. Zachry would finish the west end where the ship

from China would dock, remove the wall barricading water from that area, then continue working

on the east end “in the dry”.

The Port had reservations about this plan. Near the shore, the cutoff wall would have to be

built through the area where piers had already been driven into the channel floor. The Port’s

engineers were concerned that freezing the ground near the piers might destabilize them, weakening

4 the wharf and making it unsafe. But the Port was also concerned that if it rejected Zachry’s plan,

Zachry might simply refuse to undertake the addition of a sixth section. So the Port did not raise its

concerns with Zachry. Zachry, for its part, had already identified the issue, but its own engineers had

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States Ex Rel. Wallace v. Flintco Inc.
143 F.3d 955 (Fifth Circuit, 1998)
Chickasaw Nation v. United States
534 U.S. 84 (Supreme Court, 2001)
Newberry Square Dev. Corp. v. Southern Landmark, Inc.
578 So. 2d 750 (District Court of Appeal of Florida, 1991)
Western Engineers, Inc. v. State Ex Rel. Road Commission
437 P.2d 216 (Utah Supreme Court, 1968)
U.S. F/U/B/A Williams Electric Co. v. Metric Constructors, Inc.
480 S.E.2d 447 (Supreme Court of South Carolina, 1997)
Guy M. Cooper, Inc. v. East Penn School District
903 A.2d 608 (Commonwealth Court of Pennsylvania, 2006)
Grant Construction Co. v. Burns
443 P.2d 1005 (Idaho Supreme Court, 1968)
Edwin J. Dobson, Jr., Inc. v. State
526 A.2d 1150 (New Jersey Superior Court App Division, 1987)
Tupelo Redevelopment Agency v. Gray Corp.
972 So. 2d 495 (Mississippi Supreme Court, 2007)
RaCON, Inc. v. Tuscaloosa County
953 So. 2d 321 (Supreme Court of Alabama, 2006)
State Highway Administration v. Greiner Engineering Sciences, Inc.
577 A.2d 363 (Court of Special Appeals of Maryland, 1990)
Wes-Julian Construction Corp. v. Commonwealth
223 N.E.2d 72 (Massachusetts Supreme Judicial Court, 1967)
J&B Steel Contractors, Inc. v. C. Iber & Sons, Inc.
642 N.E.2d 1215 (Illinois Supreme Court, 1994)
Law Co., Inc. v. Mohawk Const. & Supply Co.
702 F. Supp. 2d 1304 (D. Kansas, 2010)
Blake Construction Co. v. C. J. Coakley Co.
431 A.2d 569 (District of Columbia Court of Appeals, 1981)
Pellerin Construction, Inc. v. Witco Corp.
169 F. Supp. 2d 568 (E.D. Louisiana, 2001)
Tricon Kent Co. v. Lafarge North America, Inc.
186 P.3d 155 (Colorado Court of Appeals, 2008)
Steel Co. v. Citizens for a Better Environment
523 U.S. 83 (Supreme Court, 1998)

Cite This Page — Counsel Stack

Bluebook (online)
Zachry Construction Corporation v. Port of Houston Authority of Harris County, Texas, Counsel Stack Legal Research, https://law.counselstack.com/opinion/zachry-construction-corporation-v-port-of-houston--tex-2014.