United States v. Elliott Truck Parts, Inc.

149 F. Supp. 52, 1957 U.S. Dist. LEXIS 3820
CourtDistrict Court, E.D. Michigan
DecidedFebruary 18, 1957
DocketCiv. A. 14870
StatusPublished
Cited by5 cases

This text of 149 F. Supp. 52 (United States v. Elliott Truck Parts, Inc.) is published on Counsel Stack Legal Research, covering District Court, E.D. Michigan primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States v. Elliott Truck Parts, Inc., 149 F. Supp. 52, 1957 U.S. Dist. LEXIS 3820 (E.D. Mich. 1957).

Opinion

PICARD, District Judge.

Action by plaintiff to recover excess costs allegedly suffered and resulting from defendant’s breach of three contracts. Execution of the contracts and .failure to perform is admitted but defendant contends failure justified and that plaintiff has not suffered damages alleged.

Parties have submitted exhibits and a stipulation.

Findings of Fact

On June 20, 1950 plaintiff awarded defendant, as low competitive bidder, three contracts numbered 8373, 8434 and 8549 providing for delivery of items described therein (154 truck axles and 1,-881 propeller shafts) within 120 to 180 days for a total price of $133,419.40. Other pertinent provisions of these contracts are:

“11. Default
“(a) The Government may, subject to the provisions of paragraph (b) below, by written Notice of Default to the Contractor terminate the whole or any part of this contract in any one of the following circumstances :
“(i) if the Contractor fails to make delivery of the supplies or to perform the services within the time specified herein or any extension thereof; or
“(ii) if the Contractor fails to perform any of the other provisions of this contract, or so fails to make progress as to endanger performance of this contract in accordance with its terms, and in either of these two circumstances does not cure such failure within a period of 10 days (or such longer period as the Contracting Officer may authorize in writing) after receipt of notice from the Contracting Officer specifying such failure.
“(b) The Contractor shall not be liable for any excess costs if any failure to perform the contract arises out of causes beyond the control and without the fault or negligence of the contractor. Such causes include, but are not restricted to, acts of God or the public enemy, acts of the government, fires, floods, epidemics, quarantine restrictions, strikes, freight embargoes, unusually severe weather, and defaults of subcontractors due to any of such causes unless the Contracting Officer shall determine that the supplies or services to be furnished by the subcontractor were obtainable from other sources in sufficient time to permit the Contractor to meet the required delivery schedule.
“(c) In the event the Government terminates this contract in whole or in part as provided in paragraph (a) of this clause, the Government may procure, upon such terms and in such manner as the Contracting Officer may deem appropriate, supplies or services similar to those so terminated, and the Contractor shall be liable to the Government for any excess costs for such similar supplies or services, Provided, That the Contractor shall continue the performance of this contract to the extent not terminated under the provisions of this clause.
“12. Disputes
“Except as otherwise provided in this contract, any dispute concerning a question of fact arising under this contract which is not disposed of by agreement shall be decided by the Contracting Officer, who shall reduce his decision to writing and mail or otherwise furnish a copy thereof to the Contractor. Within 30 days from the date of receipt of such copy, the Contractor may appeal by mailing or otherwise furnishing to the Contracting Officer a written appeal addressed to the Sec *54 retary, and the decision of the Secretary or his duly authorized representative for the hearing of such appeals shall be final and conclusive: Provided, That if no such appeal is taken, the decision of the Contracting Officer shall be final and conclusive * * * ”

By February 9, 1951, defendant Elliott was in default on all three contracts and plaintiff Government, through its Contracting Officer, gave notice of its intention “to terminate” unless Elliott either

(a) performed within ten days or

(b) made showing that failure to perform was without fault or negligence.

To this Elliott made no reply and on March 15, 1951, the contracts were terminated. In its notice to defendant plaintiff informed defendant that it had been determined that failure to make delivery was not attributable to any of the causes specified in Section 11(b) supra and that the Government intended to hold defendant liable for any damages or excess costs sustained in securing the contracted for truck axles and propeller shafts from others.

On May 18, 1951, after Elliott had received the above notice it informed plaintiff’s “Contracting Officer” that it, Elliott, had arranged to deliver 87 axles (contract 8373) 40 units being then at Ben’s Truck Parts, Tacoma, Washington, 20 at Mutual Truck Parts, Chicago, Illinois and the remainder at a location not specifically stated. Upon investigation plaintiff learned—

(a) that while Mutual Truck Parts denied having offered to sell any units to defendant Elliott, it had agreed to sell 20 of them to “Elliott’s President”, claiming to be unaware of the fact that he represented defendant. However, since defendant had represented that it was “to make delivery” plaintiff's agents made no attempt to purchase the axles directly from Mutual; and

(b) that of the 40 axles allegedly available at Tacoma 36 had already been sold and shipped to Portland, Oregon and the four remaining were rejected because of possible defects. Plaintiff was also informed that seller refused to crate the axles it still had in preparation for shipment.

There was no delivery of any kind made by Elliott and so the Government relet the contracts as follows: 8373, May 31; 8549, June 1; and 8434, August 22, all in 1951. Inserted therein was a provision that the equipment (axles and shafts) must be located in the United States and available for inspection.

The original contracts did not contain this provision, a point stressed by defendant, plus the admitted fact that the-provision greatly enhanced the price under the relet contracts. We find nevertheless that such provision, limiting the source of supply to the continental United States, was consistent with the policy of the Government against importation of surplus property. 1

Accordingly, plaintiff’s Contracting Officer, having determined that the cost to plaintiff Government of securing the equipment from others totals $45,680.23. in excess of the amount for which Elliott. *55 had promised to perform, assessed damages against the latter in this amount.

Defendant Elliott then appealed, both as to the “assessment” of damages and the “finding” that Elliott’s failure to perform was inexcusable on the theory that:

(a) defendant’s failure to perform was excusable under section 11(b) of the contracts because plaintiff government had prevented performance by freezing all surplus property in Europe knowing that this was defendant’s source of supply;

(b) the Government could not hold defendant liable for damages or excess costs since those relet contracts differed in a material respect from the original ones, to-wit: bids were unacceptable unless property was located in the United States; and

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
149 F. Supp. 52, 1957 U.S. Dist. LEXIS 3820, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-v-elliott-truck-parts-inc-mied-1957.