Patrick Corr & Sons v. United States

55 Ct. Cl. 7, 1919 U.S. Ct. Cl. LEXIS 18, 1919 WL 1047
CourtUnited States Court of Claims
DecidedDecember 1, 1919
DocketNo. 33298
StatusPublished
Cited by2 cases

This text of 55 Ct. Cl. 7 (Patrick Corr & Sons v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Patrick Corr & Sons v. United States, 55 Ct. Cl. 7, 1919 U.S. Ct. Cl. LEXIS 18, 1919 WL 1047 (cc 1919).

Opinion

Downey, Judge,

delivered the opinion of the court:

The plaintiff sues upon a contract made July 8, 1915, with the Panama Canal, for the delivery at Colon of 300,000 pounds of colored cotton waste with option in the latter to order such additional quantities as might be required not exceeding 50 per cent of the estimated quantity. The contract was an annual contract, i. e., for a fiscal year, and the estimated quantity referred to in the contract evidently was to meet the estimated needs for the fiscal year ending June 30,1916.

There were deliveries, acceptances, payments, acceptances without payment, deductions of liquidated damages for delay, rejections and purchases in the open market against the account of the contractor. The case involves a determination of the proper items of debit and credit as between the parties and a statement of account. Details as to the various transactions are set out in the findings and will not be repeated here except as they naturally enter into the discussion of questions involved.

The construction of the contract in one respect is material. it refers in its preamble to “ Circular Invitation No. 922,” and in Article I it recites that the contractor agrees to furnish “in accordance with the requirements of the invitation for proposals and the specifications contained in circular of the Panama Canal No. 922, dated April 26, 1915, which invitation and specifications are made a part hereof,” but in describing what it is that the contractor is to furnish the language used is “ 300,000 pounds, waste, cotton, colored, in accordance with sample ‘A’ submitted by the contractor with proposal.” It is contended by the defendant that the waste to be furnished was. not only to be [22]*22in accordance with the sample submitted but also in accordance with certain specifications; but the specifications mentioned in the. contract are said to be specifications contained in Circular No. 922, and it is shown in the findings that Circular No. 922 is not in evidence. Certain specifications called “ standard specifications for waste ” contained in a small pamphlet numbered 704 are found in the files, and the record shows they were introduced in connection with the testimony of one of the witnesses, but it is not shown that they are the specifications which were contained in Circular No. 922 or were ever submitted to this contractor. It is found as a fact that the parties treated the contract as a.contract to furnish goods according to bid sample and we are of the opinion that it must be so construed.

The inference from the record is that in all these transactions some sort of specifications were probably sent to the bidders for their guidance, but it appears that in every instance with which we have to do in this case the bidders were requested to furnish samples with their bids, and the bids were predicated upon samples furnished by the bidders in every case except one in which the bidder, being then engaged in furnishing waste under a contract, thought it unnecessary to submit another sample. This procedure was the natural one in view of the fact that different grades of waste are not “ standard,” and the best method of determining the quality of the article which the bidder was proposing to furnish was to require him to submit a sample with his bid. The language of the contract in its reference to specifications is not the only respect in which inappropriate phraseology is used, and there is ample ground for the inference that in this case, as in many other instances coming to our attention in connection with governmental contracts, the unfortunate practice prevailed of using a form prescribed for the general purpose without modifications to suit the particular case. There is no question as to the fact that the contract was treated by the parties as a contract to furnish waste in accordance with a bid sample, and it must be so construed.

Several of the transactions under this contract are not for consideration because the goods were delivered, accepted, [23]*23and paid for. The first item as to which there was any controversy was as to a shipment under order No. 62743 in connection with which the plaintiff was charged with liquidated damages in the sum of $32.42 because of 19 days’ delay in delivery which, out of a total delay of 36 days, it was determined by authorized officials of the Panama Canal was chargeable to the plaintiff. Plaintiff returned the voucher because of said deduction, protesting that it was not responsible for the delay, and the amount conceded to be due, namely, $1,673.83, was never paid.

The matter of deductions by way of liquidated damages because of delays in delivery is involved to a greater or less extent in all of these transactions, and the conclusion as to one will suffice as to all. The contract provided that one-tenth of 1 per cent of the contract price of each article should be deducted as liquidated damages for each day’s delay in delivery but that for delays not the fault of the contractor but caused by the Panama Canal or because of other specified causes, the contractor should be allowed an extension of time equivalent to the delays so occasioned, the extent of such delays for which the contractor was to be granted an extension of time to be determined by the governor of the Panama Canal or his authorized representative. The principle applicable has been thoroughly settled in many cases. The parties created a tribunal to determine the responsibility for delays, and in the absence of bad faith or such gross error as justified the inference of bad faith, they were bound by the determination of that tribunal. The principle is so well established that it is not necessary to attempt to cite all the authorities sustaining it. We refer to United States v. Gleason, 175 U. S., 588; Carstens Packing Co. v. United States, 52 C. Cls., 430; Fitzgibbon v. United States, 52 C. Cls., 164; Plumley v. United States, 43 C. Cls., 266; 226 U. S., 545; and cases cited.

Order No. 63475 for 25,000 pounds of waste, on which there was a delivery of 25,922 pounds net, amo.unting at contract price to $1,814.54, and a deduction of $7.26 on account of four days’ delay found to be chargeable to the contractor, is another case in which the deduction because of delay was [24]*24the only question involved. On account of that shipment there was conceded to be due the plaintiff $1,807.28 which was not paid.

The first rejection occurred in connection with order No. 64226, upon which there was a delivery of 25,173 pounds net, the order having been for 25,000 pounds. It was very shortly after the rejection of this shipment that plaintiff received from J. E. Lawton, theretofore connected with the Washington office of the Panama Canal and then associated with Ward & Co., of Washington, the latter set out in Finding VI. This letter probably caused much of the trouble between the parties as to the further performance of this contract, for it reached the plaintiff at about the time they were first informed of the rejection of this shipment, and they were suspicious, probably not without apparent reason, that there was some connection between the rejection of their goods on the Isthmus and the writing of this letter. The writing of such a letter under the circumstances was unquestionably reprehensible for the use against the United States, as too frequently happens, by one formerly connected with the public service, of information acquired therein is certainly .to be condemned.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Warren v. United States
57 Ct. Cl. 576 (Court of Claims, 1922)

Cite This Page — Counsel Stack

Bluebook (online)
55 Ct. Cl. 7, 1919 U.S. Ct. Cl. LEXIS 18, 1919 WL 1047, Counsel Stack Legal Research, https://law.counselstack.com/opinion/patrick-corr-sons-v-united-states-cc-1919.