Warren v. United States

57 Ct. Cl. 576, 1922 U.S. Ct. Cl. LEXIS 280, 1922 WL 1873
United States Court of Claims·Decided November 13, 1922·No. No. 42-A·Published·Cited by 1 cases

Opinion

[580] memorandum by the court.

The contract provided for liquidated damages in the event of delay in the completion of the work, and whether the contractor should be allowed extensions of the contract period was left to the decision of a designated tribunal, whose action is made conclusive upon the parties. It is also controlling upon the court. See Gleason case, 175 U. S. 588, Patricia Corr & Sons case, 55 C. Cls., 7, 23, and cases there cited.

The plaintiff is entitled to recover for the items stated in Finding X the sum of $838.56, and the petition as to other items is dismissed.

Free access — add to your briefcase to read the full text and ask questions with AI

Warren v. United States, 57 Ct. Cl. 576, 1922 U.S. Ct. Cl. LEXIS 280, 1922 WL 1873 (cc 1922).

57 Ct. Cl. 576 (Warren v. United States) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Electric Boat Co. v. United States
81 Ct. Cl. 361 (Court of Claims, 1935)