Warren v. United States

57 Ct. Cl. 576, 1922 U.S. Ct. Cl. LEXIS 280, 1922 WL 1873
CourtUnited States Court of Claims
DecidedNovember 13, 1922
DocketNo. 42-A
StatusPublished
Cited by1 cases

This text of 57 Ct. Cl. 576 (Warren v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Warren v. United States, 57 Ct. Cl. 576, 1922 U.S. Ct. Cl. LEXIS 280, 1922 WL 1873 (cc 1922).

Opinion

[580]*580memorandum by the court.

The contract provided for liquidated damages in the event of delay in the completion of the work, and whether the contractor should be allowed extensions of the contract period was left to the decision of a designated tribunal, whose action is made conclusive upon the parties. It is also controlling upon the court. See Gleason case, 175 U. S. 588, Patricia Corr & Sons case, 55 C. Cls., 7, 23, and cases there cited.

The plaintiff is entitled to recover for the items stated in Finding X the sum of $838.56, and the petition as to other items is dismissed.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Electric Boat Co. v. United States
81 Ct. Cl. 361 (Court of Claims, 1935)

Cite This Page — Counsel Stack

Bluebook (online)
57 Ct. Cl. 576, 1922 U.S. Ct. Cl. LEXIS 280, 1922 WL 1873, Counsel Stack Legal Research, https://law.counselstack.com/opinion/warren-v-united-states-cc-1922.