City of Bridgeport v. United States Fidelity & Guaranty Co.

134 A. 252, 105 Conn. 11, 1926 Conn. LEXIS 2
CourtSupreme Court of Connecticut
DecidedJuly 30, 1926
StatusPublished
Cited by13 cases

This text of 134 A. 252 (City of Bridgeport v. United States Fidelity & Guaranty Co.) is published on Counsel Stack Legal Research, covering Supreme Court of Connecticut primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
City of Bridgeport v. United States Fidelity & Guaranty Co., 134 A. 252, 105 Conn. 11, 1926 Conn. LEXIS 2 (Colo. 1926).

Opinion

Wheeler, C. J.

We consider first the denial of the motion to set aside the verdict. The following facts are either admitted or undisputed: In August, 1915, the city of Bridgeport caused to be prepared plans and specifications for a completed drawbridge to be constructed across the Pequonnock River in Bridgeport. Its six parts comprised substructure, fixed span substructures, movable span substructures, operators’ and comfort houses, approaches, removal of existing structures, and dredging channel. These plans and specifications were submitted to Empire Construction Company, hereinafter called the Empire Company, and it submitted a bid for the completed bridge. The Holbrook, Cabot and Rollins Corporation, hereinafter called the Holbrook Corporation, submitted a bid for all parts of the bridge except the movable span superstructure, and plaintiff, on October 5th, 1915, entered into a written contract to build the bridge with the exception of the movable span superstructure, and to complete the work on or before October 31st, 1916. The Empire Company also submitted its bid to build the movable span superstructure, and on October 19th, *15 1915, entered into a written contract with the plaintiff for the construction of the movable span superstructure. It at this time had full knowledge of the contract with the Holbrook Corporation.

Before the new bridge was undertaken, there was a bridge at this point. In order to keep the traffic moving it was necessary that the old bridge remain in operation until a part of the new bridge be in operation. Accordingly, the construction of the bridge was divided into two parts, a northern and a southern half; the northern was to be, and was, built first, and after its completion traffic was turned over it, thus enabling the old bridge to be removed and the southern half of the new bridge to be built. When this half was completed, the two units made a completed structure.

The substructure of the bridge is the part from the foundations to the lower part of what is called the superstructure, that is, it is the piers upon which rests the upper part of the bridge. The fixed span of the superstructure was the traffic carrying part. It is lo-cated on each side of the bascule span. This was the draw part of the bridge; this kind of a drawbridge is called a jack-knife bridge. It opens and shuts to let boats pass through. This bridge is composed of four parts, two on its east and two on its west side, and each separated from the other, and when down makes a level and uniform highway surface. In both the Holbrook Corporation and the Empire Company contracts it was provided that the old bridge should be maintained for traffic until the north half of the proposed bridge should be completed and open for traffic, and that thereafter the old bridge should be demolished and the new bridge completed within the time limited by these contracts.

The Empire Company submitted its bid and entered into its contract with the full knowledge of the Hoi *16 'brook Corporation contract, and that the execution and completion of the latter contract was dependent upon the full performance by the Empire Company of its contract. The contract of the Empire Company required it to commence the work thereunder within ten days of the date thereof, and furnish all anchorages, supports, grillages, etc., which were to be built up with masonry, within sixty days from the agreement, and to complete the north half of the bridge and place the same in operation within ninety days after receiving notice that the north half of both bascule piers was ready for the movable span superstructure. The Holbrook Corporation got the north piers ready for the .superstructure on December 1st, 1916; the Empire Company having notice of this a month before. The superstructure, which was to be completed in ninety days, was completed August 17th, 1917. Until this was completed the Holbrook Corporation was not able to proceed with the substructure for the south half, and traffic could not be diverted from the old bridge until the north half of the bascule span was ready for it. The delay in completing the north half until August 17th, compelled the Holbrook Corporation to carry on the building of the substructure into the severe winter months. Doing the work in these months after August 17th made the work harder and slower than if done in the spring, summer or fall, and the cost of the work much more. The cost of the work under the contract with the Holbrook Corporation was increased to the amount of $98,305.05 beyond the contract price, which increase was due to the excess cost of labor and materials and the expense of maintenance of plant and equipment, and the plaintiff has been obliged to pay to the Holbrook Corporation this excess cost for the construction of the bridge.

On October 19th, 1915, the Empire Company as *17 principal and the defendant as surety, executed and delivered to the plaintiff a bond in the sum of $109,264.70, conditioned that the Empire Company should in all respects comply with the terms of the contract with plaintiff and save it harmless from all damages or loss to which the plaintiff might be subjected by reason of any default by the Empire Company in the execution of its contract.

The complaint is in two counts; the first alleging delay on the part of the Empire Company in completing the north half, and the second alleging delay in completing the south half. No claim is made that there was evidence tending to support the second count. Further, no evidence was offered in support of the allegations of paragraphs eleven and twelve of the first count alleging delay in furnishing trunnion posts. The case as tried was confined to the claim under the first count, that the Empire Company failed to complete the north half of the movable span within ninety days after receiving notice that the piers were ready for it. It is further alleged in the first count, and these allegations are denied by defendant, that by reason of this delay of the Empire Company the plaintiff could not fulfil its contract with the Holbrook Corporation and was delayed six months before the north half of the bridge was opened for traffic; that in consequence of this default of the Empire Company and the delay to the Holbrook Corporation resulting therefrom, the cost of the work to the Holbrook Corporation was increased the $98,305.05 beyond the contract price, which increase was due to the excess cost of labor and materials, and the expense of maintenance of plant and equipment, and that by reason of the default of the Empire Company the plaintiff was obliged to pay the excess cost of $98,305.05 for the construction of the bridge.

*18 The Holbrook Corporation was to complete the substructure work prior to October 31st, 1916. It did not do this until December 1st, 1916. There was no evidence offered that the Empire Company was responsible for this delay. The only default for which the Empire Company could be held responsible, was for the failure to complete the north half of the movable span within ninety days from December 1st, 1916. It was essential to plaintiff’s case that the payment by the city to the Holbrook Corporation be connected with the Empire Company’s default in such way as to make the Empire Company and, therefore, its surety, the defendant, responsible.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Advest, Inc. v. Wachtel
668 A.2d 367 (Supreme Court of Connecticut, 1995)
Saturn Const. v. Dept. of Pub. Works., No. Cv-93-0704690-S (Oct. 19, 1994)
1994 Conn. Super. Ct. 10635 (Connecticut Superior Court, 1994)
Gilbane Building Co. v. Nemours Foundation
666 F. Supp. 649 (D. Delaware, 1985)
Associated Engineers & Contractors, Inc. v. State
567 P.2d 397 (Hawaii Supreme Court, 1977)
Raymond-Dravo-Langenfelder v. Microdot, Inc.
425 F. Supp. 614 (D. Delaware, 1977)
Kaplan v. Merberg Wrecking Corporation
207 A.2d 732 (Supreme Court of Connecticut, 1965)
MacDonald v. Standard Accident Insurance
111 A.2d 347 (Connecticut Superior Court, 1955)
Beach v. Beach
107 A.2d 629 (Supreme Court of Connecticut, 1954)
Moylan v. Lamothe
30 A.2d 11 (Supreme Court of New Hampshire, 1943)
Town of Milford v. O'Neil Bros., Inc.
8 Conn. Super. Ct. 403 (Connecticut Superior Court, 1940)
Thompson v. United States
80 F.2d 663 (Ninth Circuit, 1935)

Cite This Page — Counsel Stack

Bluebook (online)
134 A. 252, 105 Conn. 11, 1926 Conn. LEXIS 2, Counsel Stack Legal Research, https://law.counselstack.com/opinion/city-of-bridgeport-v-united-states-fidelity-guaranty-co-conn-1926.