Saturn Const. v. Dept. of Pub. Works., No. Cv-93-0704690-S (Oct. 19, 1994)

1994 Conn. Super. Ct. 10635
CourtConnecticut Superior Court
DecidedOctober 19, 1994
DocketNo. CV-93-0704690-S
StatusUnpublished

This text of 1994 Conn. Super. Ct. 10635 (Saturn Const. v. Dept. of Pub. Works., No. Cv-93-0704690-S (Oct. 19, 1994)) is published on Counsel Stack Legal Research, covering Connecticut Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Saturn Const. v. Dept. of Pub. Works., No. Cv-93-0704690-S (Oct. 19, 1994), 1994 Conn. Super. Ct. 10635 (Colo. Ct. App. 1994).

Opinion

[EDITOR'S NOTE: This case is unpublished as indicated by the issuing court.] MEMORANDUM OF DECISION This case was instituted by the plaintiff, Saturn Construction Company, Inc. (Saturn), to determine the lawful scope of a pending arbitration proceeding between itself and the defendant State of Connecticut (State) concerning claims which have arisen from work it performed as the prime contractor on Phase II of a five-phase construction project to build a new medium-high security State correctional facility for 700 inmates in Newtown, CT Page 10636 Connecticut (Project). Saturn has asked this Court, more particularly, for a declaratory judgment that two of the State's claims for relief in arbitration — both requests to backcharge Saturn for damages the State claims to have incurred because of Saturn's alleged failure to perform all of its work on the Project on schedule — are barred by a liquidated damages clause in the parties' contract.

Facts

Saturn and the State entered into the subject contract on October 24, 1989. The contract consisted of a series of interrelated contract documents, including "th[e] Contract, the invitation for Bids, the enumerated Plans, Specifications and Amendments thereto, the Addenda, the Proposal as accepted by the Commissioner, Department of Public Works, the General Conditions, the Special Conditions, the Bonds, the Notice to Bidders, the Wage Scales, the supplementary General Conditions, and the Insurance Certificates." Contract, ¶ 1.

Under the contract, Saturn agreed that for the sum of $17,650,000.00, it would perform all of the following work on the Project within 470 days of being notified by the State's chief of construction that it could begin work: construction of the foundation for the new facility; erection of all structural framing for the facility; performance of all masonry work on the Project; construction and installation of all security for the building; and completion of the building envelope. It also agreed that if it failed to perform all the work required of it under the contract within the 470-day contract completion period, it would be assessed "[l]iquidated damages, as stated in the proposal form, for each additional day beyond the time agreed for completion of the contract." General Conditions, Article 8, ¶ 1. According to the Proposal Form, liquidated damages would be assessed at the rate of $1000 per calendar day.

The Newtown facility was to be the first of several new correctional institutions which the State would build to ease overcrowding in the State's jails and prisons, and thus to comply with a strict federal court order and a new state statute, General Statutes § 18-87f, regarding overcrowding. Because of this order and statute the State CT Page 10637 was under extreme pressure to construct new jails and prisons in order to avoid making mandatory releases or transfers of inmates simply to keep the total population of each State correctional facility within legal limits. For that reason, the Project was to be built on a Fast Track, with construction to begin almost immediately after contracts were let.

Though the Project was to be built in five separate phases, each by a different prime contractor under his own separate contract with the State,1 Saturn's contract made it clear that its work on the Project and that of the other prime contractors would proceed simultaneously rather than sequentially. The contract thus obligated Saturn to cooperate fully with all other contractors as they worked together on the Project, and to coordinate its efforts with theirs2 under the general supervision of the Project construction manager.

In anticipation of possible disputes arising among contractors, the contract further provided that all such disputes should be submitted to the Project construction manager, whose "decision shall be complied with by all Contractors involved." General Conditions, Article 6, ¶ 2. The exercise of this responsibility was consistent with the construction manager's overall responsibility to oversee, inspect and coordinate all work on the Project as the agent of the State. General Conditions, Article 26.

Finally, in the event any dispute among contractors progressed to the point that a claim for damages arose, the contract provided that:

3. The Contractor shall assume all liability, financial or otherwise, in connection with this contract and shall protect and save harmless the Owner and Construction Manager from any and all damages or claims that may arise because of inconvenience or delay which he may cause other Contractors. If the Contractor experiences a loss because of the presence and operations of other Contractors working adjacent to or CT Page 10638 within the limits of the same project, then as between the Owner and the Contractor, the Contractor shall bear such loss.

General Conditions, Article 6, ¶ 3. (Emphasis added.) This provision obviously assigned ultimate responsibility for all damages or claims for damages arising between contractors working on the Project to the individual contractors who caused those damages. It indicated, however, that different claims for damages might be pursued in different ways.

If the claim was for damage to the person or property of one contractor, allegedly caused by the presence of operations of another contractor at or near the construction site, then under the second sentence of Article 6, paragraph 3 of the General Conditions, such claim was to be presented directly to the offending contractor, who would be solely responsible for paying it. To ensure that each contractor could meet this responsibility before work on the Project began, Article 35, paragraph 1(b) of the General Conditions required each contractor

to take out and maintain during the life of the contract such public liability and property damage insurance as shall protect him, the State of Connecticut, the Construction Manager, the Architect, and any subcontractor performing work covered by this contract from claims for damages for personal injury, including accidental death, and from claims for property damage which may arise from operations under this contract, whether such operations be by himself or by any subcontractor or by any employee unless such employees are covered by the protection afforded by the Contractor.

If, by contrast, the claim of one contractor against another was for damages suffered as a result of delay or CT Page 10639 inconvenience which the latter had caused the former while working on the Project, then under the first sentence of Article 6, Paragraph 3, the complaining contractor could present his claim directly to the State, which could pay it, if appropriate, with the full expectation that it would later be "protect[ed] and save[d] harmless" by the offending contractor. Id. This procedure, in fact, was implemented by Article 13, paragraph 7 of the General Conditions, which provided as follows:

7. If the Contractor wishes to make a claim for an increase in the contract sum or for any damages sustained as a result of changes in the work, he shall give the Construction Manager and the Owner written notice thereof within seven (7) calendar days after the occurrence of the event giving rise to such claims. No such claim shall be valid unless the notice is in writing. In addition, the Contractor shall file with the Construction Manager and the Owner daily or weekly itemized statements of the details and cost of such work performed or damage sustained as may be required by the Owner.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

McHugh v. McHugh
436 A.2d 8 (Supreme Court of Connecticut, 1980)
Berger v. Shanahan
118 A.2d 311 (Supreme Court of Connecticut, 1955)
Camp v. Cohn
201 A.2d 187 (Supreme Court of Connecticut, 1964)
Heyman v. CBS, INC.
423 A.2d 887 (Supreme Court of Connecticut, 1979)
Baker v. Baker
445 A.2d 912 (Supreme Court of Connecticut, 1982)
A. M. Larson Co. v. Lawlor Insurance Agency, Inc.
220 A.2d 32 (Supreme Court of Connecticut, 1966)
Norwalk Door Closer Co. v. Eagle Lock & Screw Co.
220 A.2d 263 (Supreme Court of Connecticut, 1966)
Kaplan v. Merberg Wrecking Corporation
207 A.2d 732 (Supreme Court of Connecticut, 1965)
City of Bridgeport v. United States Fidelity & Guaranty Co.
134 A. 252 (Supreme Court of Connecticut, 1926)
Hatcho Corp. v. Della Pietra
485 A.2d 1285 (Supreme Court of Connecticut, 1985)
Hanson Development Co. v. East Great Plains Shopping Center, Inc.
485 A.2d 1296 (Supreme Court of Connecticut, 1985)
Mack Financial Corp. v. Crossley
550 A.2d 303 (Supreme Court of Connecticut, 1988)
Game-A-Tron Corp. v. Gordon
483 A.2d 620 (Connecticut Appellate Court, 1984)

Cite This Page — Counsel Stack

Bluebook (online)
1994 Conn. Super. Ct. 10635, Counsel Stack Legal Research, https://law.counselstack.com/opinion/saturn-const-v-dept-of-pub-works-no-cv-93-0704690-s-oct-19-1994-connsuperct-1994.