Raymond-Dravo-Langenfelder v. Microdot, Inc.

425 F. Supp. 614, 21 U.C.C. Rep. Serv. (West) 558, 1977 U.S. Dist. LEXIS 17237
CourtDistrict Court, D. Delaware
DecidedFebruary 23, 1977
DocketCiv. A. 74-254
StatusPublished
Cited by30 cases

This text of 425 F. Supp. 614 (Raymond-Dravo-Langenfelder v. Microdot, Inc.) is published on Counsel Stack Legal Research, covering District Court, D. Delaware primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Raymond-Dravo-Langenfelder v. Microdot, Inc., 425 F. Supp. 614, 21 U.C.C. Rep. Serv. (West) 558, 1977 U.S. Dist. LEXIS 17237 (D. Del. 1977).

Opinion

OPINION

STAPLETON, District Judge:

This is a breach of contract action in which jurisdiction is based on diversity. The Court is asked to determine here whether the principal action and/or the third party action is barred by the statute of limitations.

•' Raymond-Dravo-Langenfelder (hereinafter “RDL”), the plaintiff, is a joint venture composed of a New Jersey, a Pennsylvania, and a Maryland corporation. The complaint alleges that RDL was the prime contractor for the construction of a bridge across the Chesapeake Bay in Maryland and that RDL contracted to purchase a number of steel pier forms for the bridge from Maryland Liquidating Company (formerly known as Wiley Manufacturing Company and hereinafter referred to as “MLC”), a Delaware corporation. By a letter dated December 18, 1969, Microdot, also a Delaware corporation and the parent corporation of MLC, guaranteed the performance of MLC. MLC then entered into a sub-contract with third-party defendant Maryland Shipbuilding, a Maryland corporation at the time and now a Michigan corporation, pursuant to which Maryland Shipbuilding fabricated steel pier form ¶ 46 and delivered it to the construction site on November 17, 1970. On November 19th, the pier form was set in position and the next day employees of RDL began pouring concrete into it. Before that process was completed, on or about December 7, 1970, the pier form collapsed into the bay. This event, plaintiff alleges, was the result of faulty workmanship and constituted a breach of MLC’s warranty to RDL. Plaintiff seeks to recover the damages he incurred as a result of the collapse. Microdot and MLC argue that any defect in the pier was caused by Maryland Shipbuilding and they seek recovery from the fabrication for any damages assessed against Microdot or MLC.

The procedural history of the case has bearing on some of the issues presented by the motion of the defendants for judgment on the pleadings that is now before me. Therefore, I will review briefly the course the case has taken thus far. After an abortive attempt to bring this suit in the United States District Court for the Eastern District of Virginia in mid-1973, the plaintiff filed an action in the District of Delaware against Microdot and MLC on November 22, 1974. On December 19, 1974, the defendant filed a third-party complaint against Maryland Shipbuilding. Plaintiff then filed a second action in the District of Connecticut on February 21, 1975, naming only Microdot as defendant. Except for the absence of MLC’s name from the complaint in Connecticut, the complaints in the two actions are identical. Pursuant to 28 U.S.C. § 1404(a), Microdot moved for and was granted a transfer of the Connecticut case to the District of Delaware. The two actions have since been consolidated.

I have concluded that the statute of limitations applicable to MLC expired before the Delaware suit was filed and that, therefore, MLC is entitled to be dismissed. The Connecticut statute applicable to Microdot in the transferred suit has not run and, therefore, Microdot remains in the suit. *617 Microdot may not pursue its third-party action against Maryland Shipbuilding, however, because any possibly applicable limitations period on such an action has past. Because different considerations have led me to these conclusions with respect to each defendant and the third-party defendant, I will discuss the situation of each party separately.

I. MLC

MLC entered into the contract with plaintiff which underlies this. suit. Pursuant to the contract, MLC agreed to sell to RDL pier forms meeting certain detailed specifications which were to be used in the construction of the bridge. There áppears to be no dispute that this was a contract for the sale of goods and that it is covered by the limitations provision in § 2-725 of the Uniform Commercial Code (hereinafter UCC or the Code) which has been enacted in all of the arguably relevant jurisdictions. Accordingly, there is no choice of law difficulty with respect to the claim against MLC. The only issue is when the cause of action against MLC accrued.

Section 2-725 of the UCC reads in pertinent part:

(1) An action for breach of any contract for sale must be commenced within four years after the cause of action has accrued. .
. (2) A cause of action accrues when the breach occurs, regardless of the aggrieved party’s lack of knowledge of the breach. A breach of warranty occurs when tender of delivery is made, except that where a warranty explicitly extends to future performance of the goods and discovery of the breach must await the time of such performance the cause of action accrues when the breach is or should have been discovered.

Defendant MLC argues that the four-year time bar applies and that if there was any breach, it occurred on November 17, 1970, when MLC delivered the pier forms to RDL through its sub-contractor Maryland Shipbuilding. According to this theory, the suit filed on November 22, 1974 was not timely and must be dismissed.

RDL counters with two arguments. First, it contends that plaintiff accepted the pier forms for towing only and that it reserved the right to conduct later inspections and to reject the goods if they did not conform to the specifications of the contract. While this may be so, it is irrelevant to the statute of limitations question. The Code clearly states that a cause of action for breach of warranty accrues when tender of delivery is made. Whether or not the buyer at that time “accepts” the goods, as that term is used in the Code, 1 or, on the other hand, withholds acceptance until he or she has had an opportunity to fully inspect for defects, does not affect when the buyer must institute suit for breach of warranty. This is so even if the defect does not appear until after the limitations period has run. 2 Once the seller tenders the goods, the limitations period begins to run unless the contract is covered by the exception in Section 2-725(2), a question I will now turn to.

RDL more earnestly argues this second point, that the contract in this case falls within the exception to the tender of delivery rule in Section 2-725 for warranties “which explicitly exten[d] to future performance of the goods. . . . ” I am not persuaded that the warranty in this case is of that nature.

RDL’s contract with MLC expressly incorporated by reference a manual entitled “Special Provisions and Proposal Form for Substructures” issued by the State Roads Commission of Maryland. That manual sets standards for construction materials to be used on Maryland highways and bridges. It includes detailed standards for pier forms such as the one involved in this lawsuit specifying in pertinent part:

The permanent pier forms shall be sufficiently watertight to prevent the loss of grout, and shall be thoroughly braced to *618 withstand all stresses and pressures produced by handling and pouring concrete continuously between the limits of construction joints shown on the Plans.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Forbes v. General Motors Corp.
993 So. 2d 822 (Mississippi Supreme Court, 2008)
Hoyt Forbes v. General Motors Corporation
Mississippi Supreme Court, 2007
Washington Freightliner, Inc. v. Shantytown Pier, Inc.
719 A.2d 541 (Court of Appeals of Maryland, 1998)
Salt Lake City Corp. v. Kasler Corp.
842 F. Supp. 1380 (D. Utah, 1994)
ST. ANNE-NACKAWIC PULP, CO. v. Research-Cottrell, Inc.
788 F. Supp. 729 (S.D. New York, 1992)
H. Sand & Co., Inc. v. Airtemp Corporation
934 F.2d 450 (Second Circuit, 1991)
H. Sand & Co., Inc. v. Airtemp Corp.
738 F. Supp. 760 (S.D. New York, 1990)
Shewbrooks v. AC AND S. INC.
529 So. 2d 557 (Mississippi Supreme Court, 1988)
Safeway Stores, Inc. v. Certainteed Corp.
710 S.W.2d 544 (Texas Supreme Court, 1986)
City of Cincinnati, Ohio v. Dorr-Oliver, Inc.
659 F. Supp. 259 (D. Connecticut, 1986)
Pack & Process, Inc. v. Celotex Corp.
503 A.2d 646 (Superior Court of Delaware, 1985)
New England Power Co. v. Riley Stoker Corp.
477 N.E.2d 1054 (Massachusetts Appeals Court, 1985)
Sellon v. General Motors Corp.
571 F. Supp. 1094 (D. Delaware, 1983)
Tolen v. AH Robins Co., Inc.
570 F. Supp. 1146 (N.D. Indiana, 1983)
Dart Industries, Inc. v. Adell Plastics, Inc.
517 F. Supp. 9 (S.D. Indiana, 1980)
Uchitel v. F. R. Tripler & Co.
107 Misc. 2d 310 (Appellate Terms of the Supreme Court of New York, 1980)
United States Fidelity & Guaranty Co. v. DiMassa
496 F. Supp. 71 (E.D. Pennsylvania, 1980)
Walker Manufacturing Co. v. Dickerson, Inc.
619 F.2d 305 (Fourth Circuit, 1980)

Cite This Page — Counsel Stack

Bluebook (online)
425 F. Supp. 614, 21 U.C.C. Rep. Serv. (West) 558, 1977 U.S. Dist. LEXIS 17237, Counsel Stack Legal Research, https://law.counselstack.com/opinion/raymond-dravo-langenfelder-v-microdot-inc-ded-1977.