Walker Manufacturing Co. v. Dickerson, Inc.

619 F.2d 305, 28 U.C.C. Rep. Serv. (West) 1052
CourtCourt of Appeals for the Fourth Circuit
DecidedApril 2, 1980
Docket78-1669, 78-1670 and 78-1698
StatusPublished
Cited by13 cases

This text of 619 F.2d 305 (Walker Manufacturing Co. v. Dickerson, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fourth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Walker Manufacturing Co. v. Dickerson, Inc., 619 F.2d 305, 28 U.C.C. Rep. Serv. (West) 1052 (4th Cir. 1980).

Opinions

THOMSEN, Senior District Judge:

I.

On August 6, 1975, Walker Manufacturing Company (Walker) filed its complaint herein against Dickerson, Incorporated (Dickerson) and its surety, Seaboard Surety Company (Seaboard), alleging that Dickerson had breached a written contract by the improper construction of the roof on a manufacturing and warehouse building at Arden, North Carolina. Walker was the owner of the building and Dickerson was the general contractor for its construction. Dickerson and Seaboard filed third-party complaints for indemnity and contribution against the roofing subcontractor, Edward’s Roofing & Sheet Metal Company (Edwards), the architect, Piedmont Engineering and Architects, Inc. (Piedmont), and the manufacturer of the roofing materials, The Celotex Corporation (Celotex).1 Edwards cross-claimed against both Piedmont and Celotex for indemnity.

Prior to trial all parties filed motions for summary judgment; the court granted Seaboard’s motion and dismissed it from the case. Walker did not appeal from that order. The district judge severed the third-party claims and cross-claims, and the principal case was tried before a jury in July 1976. At the conclusion of the plaintiff’s evidence the court granted Dickerson’s motion for a directed verdict, holding that Walker’s action was barred by the North Carolina three-year statute of limitations. N.C.Gen.Stat. § 1-52(1). In applying the statutory bar, the district court concluded that the evidence was insufficient to permit the jury to consider the application of the doctrine of equitable estoppel. Upon appeal we concluded that upon the facts presented at the trial reasonable men could differ on the issue of equitable estoppel, and, accordingly, that the district court erred in directing a verdict. In remanding the case, we also directed that the court determine whether the ten-year period of limitations for sealed instruments under N.C.Gen.Stat. § 1-47(2) had any application to the case. Walker Manufacturing Co. v. Dickerson, 560 F.2d 1184 (4 Cir. 1977).

Following the remand, on cross-motions for summary judgment, the district judge held that the ten-year statute of limitations for sealed instruments did not apply in this action, and that it was governed by the three-year statute. Walker did not appeal from that ruling. The principal case was re-tried and upon the issues submitted to it the jury found that Dickerson had breached its contract with Walker and was estopped by its conduct from asserting the defense of the statute of limitations. Damages were assessed by the jury in the amount of $194,-000, and judgment was entered against Dickerson in that amount. Dickerson has appealed.

At the trial of the third-party claims, the court submitted twelve issues to the jury, which found that Edwards had breached its subcontract with Dickerson, and that Dickerson was entitled to recover the sum of $194,000 from Edwards. Although the jury [308]*308found that Piedmont and Celotex had been negligent, the jury also found that Dickerson was estopped from asserting any claim against either of them. The jury found, however, that Celotex had breached its warranty with Edwards and that Edwards was entitled to recover $97,000 from Celo-tex; 2 the jury also awarded Edwards $48,-500 from Piedmont. A judgment was entered reflecting the various findings of the jury, and Dickerson, as well as the third-party defendants, Edwards, Piedmont and Celotex, appealed. Piedmont, however, has dismissed its appeal. This opinion deals with all of the appeals still pending.

II.

The factual background, briefly stated, is as follows: On April 21, 1969, Walker entered into a written contract with Dickerson as general contractor for the construction of the subject building. The roofing specifications called for the installation of a “twenty year bonded tar and slag roof” which would be “absolutely water tight” when the installation was completed. Under the contract, which conformed to the model agreement of the American Institute of Architects, Dickerson, as general contractor, was responsible “for the acts and omissions of all [its] employees and all Subcontractors, their agents and employees, and all other persons performing any of the work” under a contract with Dickerson. Construction began in 1969 and was completed in May of 1970. The installation of the roofing was performed by Edwards, as subcontractor, and when the roofing work was completed Edwards gave Dickerson and Walker a one year guaranty or warranty of good workmanship, extending from May 25, 1970, until May 24, 1971.

Shortly after completion of the work blisters and leaks developed in the roof. Edwards made a number of unsuccessful attempts to correct the problem, but ceased its efforts when the warranty expired. Walker then turned to Dickerson for correction of the problem, but Dickerson’s attempts to repair the roof were largely unsuccessful, despite the fact that Dickerson spent over $75,000 in the effort. We need not detail the various steps taken by Dickerson nor the negotiations between Walker and Dickerson covering the period from June 1971 until May 1975. We find sufficient evidence in the record to support the jury’s finding that Dickerson had breached its contract with Walker and was estopped from asserting the defense of the statute of limitations against Walker. Accordingly, the judgment obtained by Walker against Dickerson is affirmed.

With respect to the various third-party claims the indemnity clause in Edwards’ roofing subcontract supports the judgment in favor of Dickerson against Edwards in the full amount of the $194,000 verdict which Walker had obtained against Dickerson in the trial of the principal case. Piedmont has dismissed its appeal from the judgment obtained by Edwards in the cross-claim of Edwards against it. So, the questions remaining for our consideration deal with (A) the propriety of the judgment which Edwards obtained against Celotex in the amount of $97,000 based upon its breach of warranty, and (B), Dickerson’s contention that it was entitled to judgment against Celotex based on the alleged negligence of Celotex.

III.

The involvement of Celotex in this action stems from its sale to Edwards of roofing felt known as Philip Carey 300. The materials were delivered to Edwards during the period September-December 1969. Celotex offered, for a stated premium, to issue bonds on roofs using its materials and installed in accordance with its specifications, but no bond was obtained from it by any of the parties to this controversy. After roofing problems developed, a sales representa[309]*309tive of Celotex met with representatives of the other parties at the job site on September 16, 1971. Thereafter, its representative received copies of two letters directed to Walker by Dickerson, the last letter dated November 16, 1971. None of the parties made a claim or demand against Celotex based upon the sale of the roofing material to Edwards until Dickerson’s third-party complaint was filed in this action on September 8, 1975.

(A)

In challenging Edwards’ judgment against it, the principal contention of Celo-tex is that any claim of Edwards growing out of the sale of the roofing material is time-barred by the provisions of the Uniform Commercial Code, N.C.Gen.Stat. 25-2-725, effective in North Carolina on July 1, 1967, which provides:

(1) An action for breach of any contract for sale must be commenced within four years after the cause of action has accrued.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Lone Mountain Processing, Inc. v. Bowser Morner, Inc.
94 F. App'x 149 (Fourth Circuit, 2004)
Bay Point Condominium Ass'n v. RML Corp.
57 Va. Cir. 295 (Virginia Circuit Court, 2002)
Central Washington Refrigeration, Inc. v. Barbee
946 P.2d 760 (Washington Supreme Court, 1997)
Central Wash. Refrigeration v. Barbee
946 P.2d 760 (Washington Supreme Court, 1997)
Ameron, Inc. v. Chemische Werke Huls AG
760 F. Supp. 1234 (E.D. Michigan, 1991)
Chantilly Partners v. James A. Federline, Inc.
26 Va. Cir. 1 (Fairfax County Circuit Court, 1991)
City of Wood River v. Geer-Melkus Construction Co.
444 N.W.2d 305 (Nebraska Supreme Court, 1989)
Wingo v. Norfolk & Western Railway Co.
638 F. Supp. 107 (W.D. Virginia, 1986)
In Re Fela Asbestos Litigation
638 F. Supp. 107 (W.D. Virginia, 1986)
Bradford v. Indiana & Michigan Electric Co.
588 F. Supp. 708 (S.D. West Virginia, 1984)
City of Clayton v. Grumman Emer. Prod.
576 F. Supp. 1122 (E.D. Missouri, 1983)

Cite This Page — Counsel Stack

Bluebook (online)
619 F.2d 305, 28 U.C.C. Rep. Serv. (West) 1052, Counsel Stack Legal Research, https://law.counselstack.com/opinion/walker-manufacturing-co-v-dickerson-inc-ca4-1980.