Lone Mountain Processing, Inc. v. Bowser Morner, Inc.

94 F. App'x 149
CourtCourt of Appeals for the Fourth Circuit
DecidedApril 8, 2004
Docket02-2392
StatusUnpublished
Cited by5 cases

This text of 94 F. App'x 149 (Lone Mountain Processing, Inc. v. Bowser Morner, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fourth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Lone Mountain Processing, Inc. v. Bowser Morner, Inc., 94 F. App'x 149 (4th Cir. 2004).

Opinions

OPINION

BENNETT, District Judge.

I.

Procedural History

On May 26, 2000, Lone Mountain Processing, Inc. (“Lone Mountain”), which operates a coal preparation facility in St. Charles, Virginia, filed a two-count complaint against Bowser Morner, Inc.; Bowser Morner Associates, Inc. (“Bowser Morner”), an engineering design firm in Dayton, Ohio, alleging breach of contract and negligence in connection with a November 1, 1991 contract between the parties. Pursuant to that contract, Bowser Morner was to design a coal slurry impoundment for Lone Mountain’s facility. On October 24, 2000, Lone Mountain filed an amended complaint, adding a third count for contractual indemnification. In its answer to the amended complaint, Bowser Morner asserted the affirmative defense of the statute of limitations. Subsequently, Bowser Morner moved to dismiss the amended complaint.

The District Court subsequently converted Bowser-Morner’s motion to dismiss into a motion for summary judgment. Lone Mountain then filed its own motion for summary judgment. The District Court limited discovery to the issue of statute of limitations. The motions, both based upon affidavits, were briefed and argued in August of 2001. In February of 2002, the District Judge dismissed both motions without prejudice, advising that the motions should be re-filed based upon additional discovery that had been taken in the interim. In July of 2002, Lone Mountain filed a motion for partial summary judgment on the issue of statute of limitations and repose.1 Bowser-Morner also filed a motion for summary judgment.

The District Court, in a September 13, 2002 memorandum opinion, granted Bowser-Morner’s motion for summary judgment and denied Lone Mountain’s partial motion for summary judgment. The court found that Lone Mountain was time-barred from bringing this action pursuant to a contract statute of limitations, referencing Virginia statutory law applying a five-year limitations period for a written contract.

Pursuant to Rule 59(e) of the Federal Rules of Civil Procedure, Lone Mountain moved to alter or amend its judgment, noting that the District Court had ruled that all claims were controlled by the contract statute of limitations and had not [152]*152addressed the additional claims of negligence, breach of warranty and contractual indemnification. By memorandum opinion dated November 1, 2002, the District Court denied Lone Mountain’s motion to alter or amend its September 13, 2002 decision. The District Court reiterated its position on the negligence and breach of warranty claims as set forth in its earlier order. With respect to the contractual indemnification claim, the District Judge reiterated his holding that there was “no apparent need to address an issue that is, in the minds-eye of this court, constitutionally moot.” (JA 2059). This appeal follows.

II.

Facts

Lone Mountain operates a coal preparation plant in St. Charles, Virginia where it cleans coal in preparation for shipment. On November 5, 1991, Lone Mountain entered into a contract (the “Contract”) with Bowser-Morner, an engineering design firm, for engineering and design services related to a coal slurry impoundment adjacent to the coal preparation plant. Pursuant to the Contract, Bowser-Morner agreed to design the structure in accordance with federal regulations established by the United States Department of Mine Safety and Health Administration (“MSHA”), and state regulations established by the Commonwealth of Virginia’s Division of Mined Land Reclamation (“DMLR”). While Bowser-Morner was not responsible for securing the necessary permits, it was required to answer questions by federal and state regulators during a review of the design.

The Contract provided that any lack of conformance to regulatory standards was to be corrected by Bowser-Morner at no cost to Lone Mountain. The record of this case indicates that a representative of Bowser-Morner acknowledged that Bowser-Morner had an obligation to answer questions raised by federal and state regulators. (JA 1127-28).

After a lengthy period of regulatory review during the permitting process and after initial federal and state approval of the design, the Bowser-Morner design of the coal slurry was approved on March 20, 1995. Consequently, on March 24, 1995, Bowser-Morner issued what it termed its final payment order to Lone Mountain. Under the Contract, “upon acceptance and approval of the work,” Lone Mountain was to retain (10%) and forward the remainder of payment within fifteen days of approval and acceptance. On April 25, 1995, Lone Mountain paid Bowser-Morner’s payment order, not exercising any right of retain-age.2

The question of the completion of the contract is vigorously contested by the parties. Following the acceptance and approval of the design plan, the parties had interactions in August, October, and November of 1995, the legal effect of which are contested by Lone Mountain and Bowser-Morner. In August of 1995, at Lone Mountain’s request, Bowser-Morner provided Lone Mountain with a hydraulics analysis with respect to alternative locations for the impoundment pipe. In October of 1995, representatives of Bowser-Morner visited the impoundment site. In November of 1995, in response to Lone Mountain’s request, Bowser-Morner provided a feasibility study for control of cracking concrete in the area of the pipe.

[153]*153While the ramifications of the above three events in the latter part of 1995 generate a dispute among the parties, it is undisputed that on June 5, 1996, upon filling the impoundment designed by Bowser-Morner with coal slurry, a pipe collapsed allowing contaminated water to escape and leak. This fracturing and cracking along the western wall of the slurry impoundment resulted in the leaking of contaminated water in violation of the National Pollutant Discharge Elimination System permit issued to Lone Mountain. See 33 U.S.C. §§ 1311, 1319.

Subsequently, on August 9, 1996, water flowed through a collapsed wall of the slurry impoundment into an abandoned coal mine. DMLR ordered Lone Mountain to suspend operations until repairs could be made. After performing those repairs, Lone Mountain was allowed to restart its operations on August 16, 1996. One month later, on or about September 20, 1996, Lone Mountain discovered another leak in the slurry impoundment in the western wall. On or about October 9, 1996, Lone Mountain discovered yet another leak in the impoundment.

On or about October 24, 1996, a massive leak resulted in the slurry impoundment allowing approximately three thousand gallons of contaminated water per minute to flow into Gin Creek. This contaminated water flowed approximately eleven miles into the Powell River, causing the pool elevation in the impoundment to drop by three feet and contaminating and destroying an estimated eleven thousand fish.

As a result of the leaks and release of contaminated water into the Powell River, which had been designated by the government as a critical habit area, Lone Mountain pled guilty to a two-count information charging it with negligent discharge of a pollutant in violation of 33 U.S.C. §§ 1311

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Sewell v. Bernardin
50 F. Supp. 3d 204 (E.D. New York, 2014)
Noell Crane Systems GmbH v. Noell Crane & Service, Inc.
677 F. Supp. 2d 852 (E.D. Virginia, 2009)
Goodenough v. Province
78 Va. Cir. 263 (Charlottesville County Circuit Court, 2009)

Cite This Page — Counsel Stack

Bluebook (online)
94 F. App'x 149, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lone-mountain-processing-inc-v-bowser-morner-inc-ca4-2004.