Suffolk City School Board v. Conrad Bros.

495 S.E.2d 470, 255 Va. 171, 1998 Va. LEXIS 10
CourtSupreme Court of Virginia
DecidedJanuary 9, 1998
DocketRecord 970414
StatusPublished
Cited by8 cases

This text of 495 S.E.2d 470 (Suffolk City School Board v. Conrad Bros.) is published on Counsel Stack Legal Research, covering Supreme Court of Virginia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Suffolk City School Board v. Conrad Bros., 495 S.E.2d 470, 255 Va. 171, 1998 Va. LEXIS 10 (Va. 1998).

Opinion

JUSTICE KOONTZ delivered the opinion of the Court.

This appeal arises from a suit by the Suffolk City School Board (the Board) against a general contractor engaged to build two high schools. The Board alleges that the contractor, Conrad Brothers, Inc., installed defective roofs in the schools, resulting in damage to both. The trial court ruled that the suit was barred by the applicable five-year statute of limitations. Code § 8.01-246(2). The issue we consider on appeal is whether the trial court erred in this ruling. Specifically, we determine when the Board’s cause of action accrued pursuant to the provisions of Code § 8.01-230.

The essential facts are not in dispute. On February 26, 1986, the Board entered into a contract with Shriver and Holland Associates (the architects) to provide architectural services and representation throughout the various phases of the planned construction of the two high schools (the architects’ contract). For purposes of determining the architects’ obligations and right to compensation, this contract contained a provision that “[t]he Construction Phase . . . will terminate when final payment to the Contractor is due, or in the absence of a final Certificate for Payment or of such due date, sixty days *173 after the Date of Substantial Completion of the Work, whichever occurs first.”

On October 14, 1988, the Board entered into two separate, but substantially similar, contracts with Conrad Brothers as the general contractor for the construction of the two high schools under the direction of the architects (the construction contracts). The construction contracts fixed the time for final completion of construction as the date of issuance of a “final Certificate for Payment” by the architects.

Thereafter, Conrad Brothers commenced work on both schools and the architects issued certificates noting substantial completion for both schools as of September 3, 1990. The architects’ “punch lists” appended to each certificate showing what further work was to be completed by the contractor before final payment would be authorized included references to correction of the defective roofs. On November 27, 1990, and on several occasions thereafter, the Board contacted Conrad Brothers to report leaks in the roofs of both schools. Conrad Brothers received these notices and took steps to remedy the defective condition of the roofs.

On February 4, 1991, Conrad Brothers submitted to the architects an application for final payment with respect to construction of both high schools. The architects issued certifications for payment of Conrad Brothers to the Board on March 13, 1991. The Board filed the present suit against Conrad Brothers on February 13, 1996. 1 Conrad Brothers filed a plea of the statute of limitations, asserting that the Board had notice of the defective conditions of the roofs on or before September 12, 1990.

Following a hearing on Conrad Brothers’ plea, the trial court issued a letter opinion in which it referenced the previously noted provisions of the architects’ contract which specified that the “construction phase” of the projects would expire sixty days after the issuance of the certificates of substantial completion. Determining that this date was November 2, 1990, the trial court set the commencement of the limitations periods at that point. Based upon this determination, the trial court held that the statute of limitations ran *174 on November 2, 1995, more than three months prior to the filing of the Board’s motion for judgment. A final order was entered on December 4, 1996, adopting by reference the reasons stated in the trial court’s initial opinion letter. We awarded the Board this appeal.

We first consider the trial court’s reliance on the terms of the architects’ contract to determine the termination date of the construction contracts. The construction contracts contain express terms addressing their duration and termination, and nothing within the construction contracts links their termination to the termination of the construction phase defined in the architects’ contract. Although using similar terms and related to the same projects, the contracts are independent expressions of the agreements between the Board and the architects, on the one hand, and the Board and Conrad Brothers on the other. Accordingly, the trial court’s determination that the Board’s cause of action against Conrad Brothers accrued on November 2, 1990 pursuant to the architects’ contract was in error. Under the applicable provisions of the construction contracts the construction was complete upon the issuance of a “final Certificate for Payment,” which did not occur here until March 13, 1991, less than five years before the litigation was commenced.

Conrad Brothers asserts, however, that the trial court’s judgment can be sustained under a “right result, wrong reason” analysis. See, e.g., Harrison & Bates, Inc. v. Featherstone Associates Ltd. Partnership, 253 Va. 364, 369, 484 S.E.2d 883, 886 (1997). Conrad Brothers contends that Code § 8.01-230 abrogates the common law rule permitting a party to an indivisible executory contract to elect between pursuing his remedy when an action which would constitute a breach occurs or awaiting the time fixed by the contract for full and final performance. Continuing, Conrad Brothers contends that Code § 8.01-230 provides that the statute of limitations on any cause of action for breach of contract involving damage to property commences upon the occurrence of the breach, regardless of whether the breaching party continues to perform. Thus, in the present case, Conrad Brothers asserts that the statute of limitations began to run at least prior to November 27, 1990 when the Board first acknowledged that the roofs were defective.

Prior to the enactment of Code § 8.01-230, the rule with respect to the running of a statute of limitations for a breach of an indivisible executory contract was clear:

In the case of an indivisible or entire contract, a party seeking to recover for a breach committed while the contract *175 remained executory, or for an anticipatory breach committed before expiration of the time agreed upon for full and final performance, has the election of pursuing his remedy when the breach occurs, or of awaiting the time fixed by the contract for full and final performance. If he elects the latter course, the statute of limitations does not begin to run against his right of action until the time for final performance fixed by the contract has passed. Andrews v. Sams, 233 Va. 55, 58, 353 S.E.2d 735, 738 (1987); County School Bd. v. Beiro, 223 Va. 161, 163, 286 S.E.2d 232, 233 (1982); Simpson v. Scott, 189 Va. 392, 400, 53 S.E.2d 21, 24 (1949).

Roberts v. Coal Processing Corp., 235 Va. 556, 561, 369 S.E.2d 188

Free access — add to your briefcase to read the full text and ask questions with AI

Related

SOMERSETT OWNERS ASS'N VS. SOMERSETT DEV. CO., LTD.
2021 NV 35 (Nevada Supreme Court, 2021)
State Analysis, Inc. v. American Financial Services Assoc.
621 F. Supp. 2d 309 (E.D. Virginia, 2009)
Lone Mountain Processing, Inc. v. Bowser Morner, Inc.
94 F. App'x 149 (Fourth Circuit, 2004)
American Inn, L.P. v. Suntrust Banks, Inc.
28 F. App'x 316 (Fourth Circuit, 2002)
Jackson v. Quantrex Integrated Technology Group, Inc.
57 Va. Cir. 368 (Virginia Circuit Court, 2002)
Wallace v. Zoller
52 Va. Cir. 80 (Winchester County Circuit Court, 2000)
Johnson v. Commonwealth
51 Va. Cir. 311 (Stafford County Circuit Court, 2000)

Cite This Page — Counsel Stack

Bluebook (online)
495 S.E.2d 470, 255 Va. 171, 1998 Va. LEXIS 10, Counsel Stack Legal Research, https://law.counselstack.com/opinion/suffolk-city-school-board-v-conrad-bros-va-1998.