ST. ANNE-NACKAWIC PULP, CO. v. Research-Cottrell, Inc.

788 F. Supp. 729, 17 U.C.C. Rep. Serv. 2d (West) 699, 1992 U.S. Dist. LEXIS 5245, 1992 WL 46605
CourtDistrict Court, S.D. New York
DecidedApril 21, 1992
Docket90 Civ. 5369 (MBM)
StatusPublished
Cited by8 cases

This text of 788 F. Supp. 729 (ST. ANNE-NACKAWIC PULP, CO. v. Research-Cottrell, Inc.) is published on Counsel Stack Legal Research, covering District Court, S.D. New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
ST. ANNE-NACKAWIC PULP, CO. v. Research-Cottrell, Inc., 788 F. Supp. 729, 17 U.C.C. Rep. Serv. 2d (West) 699, 1992 U.S. Dist. LEXIS 5245, 1992 WL 46605 (S.D.N.Y. 1992).

Opinion

OPINION AND ORDER

MUKASEY, District Judge.

Plaintiff claims that defendant breached a contract (“the Contract”) to supply a pollution control system. Defendant now moves for summary judgment pursuant to Rule 56, Fed.R.Civ.P. For the reasons set forth .below, defendant’s motion for summary judgment is denied.

I.

Plaintiff, St. Anne-Nackawic Pulp Company, whose principal place of business is in New Brunswick, Canada (Compl. 112), produces wood pulp and related products. (Id. 11 5) Defendant, a New Jersey corporation, engineers, designs, manufactures, and installs air pollution products. (Id. ITU 3, 6) In 1986, defendant purchased the assets of Teller Environmental Systems, Inc. (“TESI”), a company founded and managed by Dr. Aaron J. Teller (“Teller”). Teller is the inventor of numerous patented processes for pollution control. (Teller Aff. 1I1J 3-12; Teller Dep. at 3, 6)

The subject of the Contract between plaintiff and TESI, as defendant’s predecessor, is a system designed by TESI to limit the amount of Total Reduced Sulfur (“TRS”) discharged as a by-product of the pulp making process. The principal objection to TRS is that it generates a strong sulphurous smell, rather like the odor of rotten eggs. Consequently, its discharge is regulated by New Brunswick environmental laws.

In 1980, “after the original Teller equipment was destroyed in a fire,” plaintiff contacted TESI to “design new equipment.” (Compl. 1Í 9) The new system was supposed to bring plaintiff’s plant into compliance with New Brunswick regulations, which had been amended not long before to limit further the acceptable level of TRS discharge. Teller submitted a proposal dated January 26, 1981 for “the supply and installation of a Teller Crossflow Nucleation Scrubber and Roy-Lin Venturi with Expansion Joint and Supply only of Hydro-clones.” (See Raymond Aff.Ex. 2, Proposal at 1)

*731 On February 25, 1981, the parties executed the Contract, which consists of (i) the written proposal dated January 26, 1981, and (ii) a copy of TESI’s general contract terms (“general conditions”). The Contract price for the entire system, including equipment and services, was $2,065,000 (Canadian).

Section 7 of the Contract’s general conditions is titled “Warranty.” Section 7.1 contains a “Performance Warranty,” which provides that seller’s performance is complete once the system satisfies the performance specifications, including the promised TRS level, for a continuous three-day testing period to be conducted within 120 days of “start-up” but “in any event not later than nine (9) months after mechanical completion of the scrubber.” (Id., Gen. Conditions at 4) The performance warranty further provides that: “In the event that the System fails to operate as stated above, Teller shall at its own expense, provide all engineering, drawings and specifications to modify the System as is necessary to make the System operate as warranted herein.” (Id.) The Contract states that plaintiff will retain 10% of purchase price until TESI satisfies its obligations under the performance warranty. (Id., Proposal at 7) In addition to the performance warranty, the Contract also contains a “Warranty Regarding Engineering Services” for any “design error” discovered within one year of start-up (§ 7.2) and a “Warranty Regarding Equipment” (§ 7.3).

The system was completed mechanically 1 on September 22, 1982; start-up occurred 2 on December 16, 1982. (Initial Compl. 1118) An independent consultant tested the system in March 1983, June 1983, and March 1984. Each time TRS emissions exceeded the 10 ppm level specified by the performance guarantee. From the first testing of the system in March 1983 until the time of this suit, the parties have attempted to determine the cause of, and a possible cure for, the system’s failure. The parties agree that the system failed to achieve the promised emission levels although they dispute the cause of the failure.

On February 4, 1986, TESI and defendant entered into an asset purchase agreement under which defendant agreed to purchase the assets of TESI and assume certain of its obligations. Schedule 5.9.1 of the Asset Purchase Agreement listed the Contract as an “Open Contract” that was 98% complete and that had a $3,350 estimated completion cost. (Raymond Ex. 26) Section 5.9.1 of that agreement provides in relevant part:

“Open Contract” means each agreement pursuant to which Seller is, or was, obligated to perform any service or provide any goods and Seller’s performance is not complete, Seller has not received full payment, any warranty made by Seller has not expired or any claim or communication with respect to any warranty has been received by Seller.

(Raymond Aff.Ex. 25, 3425)

Following the sale, Teller became a consultant to defendant; he is now defendant’s Vice President of Technology. (Teller Dep. at 67-68) On October 10, 1986, Teller wrote an internal memorandum captioned “Closeout of Teller Jobs.” He described the Contract as follows: “After the last turnaround the system performance is significantly better than guarantee. It is expected that after official testing information is acquired, the contract can be closed out.” (Raymond Ex. 29, at 3451)

On July 14, 1987, Teller wrote to plaintiff, stating that he had reviewed the latest data on the system (the system operating data and the test column data). He asserted:

*732 We are prepared to meet with you to discuss the analysis of the data and work with you toward the apparent solution. Inasmuch as the system has exhibited oxygenation capacity to neutralize the high TRS inlets when in stable operation, we believe that the job should be closed out from a guarantee aspect.
However, as we have established in our relationship for these many years, we will continue to work with you toward the total solution to the operating problems.

(Raymond Ex. 30, at 0769)

On June 23-25, 1987, one of defendant’s employees went to plaintiff in order “to work with St. Anne personnel and identifying [sic] the operation characteristics in the test column so that the result from this study may be applied to the main scrubber unit.” (Raymond Ex. 31, at 0818)

On August 25, 1987, Teller again wrote plaintiff:

Since receipt of your letter we have received the verbal confirmation of the test column behavior reflecting our hypothesis of two years ago that carryover is related to foam instability.
Although we have worked together to achieve solution to the carryover problem, not present in the first unit, and will continue to work with you in the effective resolution of this problem, it is now established the cause was not the design. Therefore, it is essential that the hold-back be released.

(Raymond Ex. 32)

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Washington Freightliner, Inc. v. Shantytown Pier, Inc.
719 A.2d 541 (Court of Appeals of Maryland, 1998)
Baker v. Dec International
580 N.W.2d 894 (Michigan Supreme Court, 1998)
Coastal Aviation, Inc. v. Commander Aircraft Co.
937 F. Supp. 1051 (S.D. New York, 1996)

Cite This Page — Counsel Stack

Bluebook (online)
788 F. Supp. 729, 17 U.C.C. Rep. Serv. 2d (West) 699, 1992 U.S. Dist. LEXIS 5245, 1992 WL 46605, Counsel Stack Legal Research, https://law.counselstack.com/opinion/st-anne-nackawic-pulp-co-v-research-cottrell-inc-nysd-1992.