H. Sand & Co., Inc. v. Airtemp Corporation

934 F.2d 450, 14 U.C.C. Rep. Serv. 2d (West) 1111, 1991 U.S. App. LEXIS 11278, 1991 WL 90444
CourtCourt of Appeals for the Second Circuit
DecidedJune 3, 1991
Docket1099, Docket 90-7879
StatusPublished
Cited by110 cases

This text of 934 F.2d 450 (H. Sand & Co., Inc. v. Airtemp Corporation) is published on Counsel Stack Legal Research, covering Court of Appeals for the Second Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
H. Sand & Co., Inc. v. Airtemp Corporation, 934 F.2d 450, 14 U.C.C. Rep. Serv. 2d (West) 1111, 1991 U.S. App. LEXIS 11278, 1991 WL 90444 (2d Cir. 1991).

Opinion

CARDAMONE, Circuit Judge:

This appeal centers on the date of delivery of four chillers used in the air conditioning system at the New York Port Authority Bus Terminal Building in Manhattan. Unlike beauty, the delivery of property is not in the eye of the beholder. That is a subjective notion, while the transfer of goods occurs when the facts of delivery are objectively established.

The appellant, H. Sand & Co., Inc. (Sand), ordered the chillers in 1977 from the appel-lee, Airtemp Corporation, in fulfillment of Sand’s sub-contract with the general contractor, Carlin-Atlas Joint Venture, to install the heating, ventilation, and air conditioning in the reconstruction and expansion of the Bus Terminal at the corner of 8th Avenue and 40th Street in New York City. Sand appeals from a grant of summary judgment dismissing its suit for breach of warranty on the contract calling for delivery of the chillers, from an earlier ruling dismissing Count IV of its amended complaint, and from a denial of its motion for reargument.

Sand sued Airtemp late in 1982 alleging the chillers were defective and that it expended considerable funds repairing them. Sand amended its complaint to include Count IV, which asserts that Airtemp is liable not only in damages to Sand, but also *452 for damages to the Port Authority arising from problems with the defective chillers because, Sand alleged, the Port Authority may hold Sand liable for those same damages. The district court dismissed Count IV sua sponte and granted summary judgment in favor of Airtemp on the other counts in Sand’s complaint, holding that they were all barred by the statute of limitations. Because we think the district court overlooked a genuine issue of material fact that precludes the grant of summary judgment, we reverse and remand the case to it for further proceedings.

FACTS

Sand asserts it entered into the 1977 contract with Airtemp for four motor driven hermetic centrifugal chillers, which constituted a cooling system, and that under the contract accessories and services were also to be provided. Sand sent its purchase order form — dated June 6, 1977 and marked job number 1208-AA — to Airtemp for the four chillers. The order was received by Airtemp a week later, as indicated by a stamp on its face. In reply, Airtemp sent Sand an invoice dated March 1, 1984 for one of the chillers, referencing Sand’s purchase order number 1208-AA. This is the only document acknowledging Sand’s order.

All four chillers were shipped by Airtemp to Sand’s agent, Associated Rigging & Hauling Corp., between January and March, 1978. One of them (chiller # 4) was not tested prior to being shipped because by the time it was ready to be tested Air-temp was in the process of relocating its testing facilities from Kentucky to Edison, New Jersey. In November 1978 chiller # 4 was sent — at Airtemp’s expense and direction — from Associated Rigging & Hauling to Airtemp’s Edison plant for a test run. After testing the chiller, Airtemp shipped it back to Associated Rigging & Hauling in January, 1979.

The general contractor, Carlin-Atlas, did not start up any of the chillers until the middle of 1980. Sand states that shortly after being started the chillers exhibited defects. When it contacted Airtemp regarding these problems, Airtemp refused to perform any repair work without additional payment. As a result, Sand made its own repairs and withheld $10,000 of the purchase price. The Port Authority officially accepted the equipment on May 23, 1981.

PRIOR PROCEEDINGS

On December 16, 1982 Sand sued Air-temp’s parent corporation, Fedders Corp., in the Supreme Court of New York County for damages arising out of the defects in the chillers. The parties agreed to dismiss the action without prejudice to allow Sand to bring its suit in federal court, and further stipulated that the action be deemed to have been commenced on December 16, 1982 for statute of limitations purposes. After Sand brought its suit in the United States District Court for the Southern District of New York (Cooper, J.), Airtemp asserted the limitations bar and counterclaimed for the withheld $10,000.

In December 1983 the Port Authority told Carlin-Atlas it was liable for approximately $650,000 in expenses incurred as a result of the defective chillers. On December 16, 1984 Carlin-Atlas and the Port Authority signed an agreement of settlement and general release under which the Port Authority agreed to limit its claim against Carlin-Atlas for damages to the amount:

if any, finally and unappealably awarded and received by [Carlin-Atlas’] subcontractor, H. Sand & Company, in their pending lawsuit against the centrifugal chiller manufacturer for damages, but only insofar as the award is ... exclusively based upon the claim or potential claim of the Contractor for damages against H. Sand either under a theory of indemnity to the Contractor or otherwise ... minus 25% of the amount of said damages, representing the attorney’s fees of H. Sand & Co. [or 40% of the amount of a settlement in the same suit after 25% for attorney’s fees]. *453 Acknowledged, agreed and accepted this 18 day of January 1985 and further agreed that, except as aforesaid, no other right of [Carlin-Atlas] or H. Sand under their applicable subcontract shall be deemed to be waived or released hereunder and it is further agreed that, as between the Contractor and H. Sand, all of the terms and provisions of this agreement shall be binding upon and shall enure to the benefit of H. Sand.

*452 A copy of the same contract, signed by Sand’s Senior Vice President, bears an additional paragraph stating at the end:

*453 On January 25, 1984 Sand amended its complaint against Airtemp to add a Count IV for the amount of the Port Authority’s damages.

In late 1985, the district court requested legal memoranda setting forth the parties’ legal positions regarding the viability of Sand’s claim on behalf of the Port Authority for damages. Both parties submitted memoranda, and on April 18, 1986 Judge Cooper filed an order dismissing sua sponte Count IV of the complaint. On October 21, 1986 the court denied Sand’s motion for reconsideration.

Airtemp thereafter filed a motion for summary judgment. The district court granted the motion and dismissed Sand’s action as time-barred under the New York Uniform Commercial Code’s (U.C.C.) four-year statute of limitations. 738 F.Supp. 760 (S.D.N.Y.1990). On August 30, 1990 it denied plaintiff’s motion for reargument, which alleged that summary judgment had improperly been granted without regard for a genuine issue of material fact— whether the shipment of chiller # 4 in 1978 was a “tender of delivery” sufficient to trigger the statute of limitations. 743 F.Supp. 279 (S.D.N.Y.1990). From these several orders, Sand appeals.

DISCUSSION

I Tender of Delivery

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Ashley v. City of Bridgeport
Second Circuit, 2023
Wellin v. Farace
D. South Carolina, 2022
Chasewood v. Kay
E.D. New York, 2020
Greene v. Virgin Islands Water & Power Authority
65 V.I. 67 (Superior Court of The Virgin Islands, 2016)
Themis Capital, LLC v. Democratic Republic of Congo
881 F. Supp. 2d 508 (S.D. New York, 2012)
Deso v. CSX Transportation, Inc.
790 F. Supp. 2d 1 (N.D. New York, 2011)
North American Communications, Inc. v. InfoPrint Solutions Co.
817 F. Supp. 2d 623 (W.D. Pennsylvania, 2011)
Wojciechowski v. National Oilwell Varco, L.P.
763 F. Supp. 2d 832 (S.D. Texas, 2011)
Mattera v. JPMorgan Chase Corp.
740 F. Supp. 2d 561 (S.D. New York, 2010)
Travelers Casualty & Surety Co. v. Dormitory Authority-State
735 F. Supp. 2d 42 (S.D. New York, 2010)
East Coast Resources, LLC v. Town of Hempstead
707 F. Supp. 2d 401 (E.D. New York, 2010)
Nextec Applications v. BROOKWOOD COMPANIES, INC.
703 F. Supp. 2d 390 (S.D. New York, 2010)
Khan v. Douglas MacHine & Tool Co., Inc.
661 F. Supp. 2d 437 (S.D. New York, 2009)

Cite This Page — Counsel Stack

Bluebook (online)
934 F.2d 450, 14 U.C.C. Rep. Serv. 2d (West) 1111, 1991 U.S. App. LEXIS 11278, 1991 WL 90444, Counsel Stack Legal Research, https://law.counselstack.com/opinion/h-sand-co-inc-v-airtemp-corporation-ca2-1991.