United Engineering & Contracting Co. v. United States

47 Ct. Cl. 489, 1912 U.S. Ct. Cl. LEXIS 19, 1911 WL 1375
CourtUnited States Court of Claims
DecidedNovember 11, 1912
DocketNo. 30072
StatusPublished
Cited by3 cases

This text of 47 Ct. Cl. 489 (United Engineering & Contracting Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United Engineering & Contracting Co. v. United States, 47 Ct. Cl. 489, 1912 U.S. Ct. Cl. LEXIS 19, 1911 WL 1375 (cc 1912).

Opinion

Peelle, Ch. J.,

delivered the opinion of the court:

The Government by motion seeks a new trial on the assigned ground of error of fact and of law, and also asks that [499]*499Findings X and XI be amended in certain particulars. We will, therefore, review the case.

This action arises out of delays of the Government and for deductions as liquidated damages from the contract price for delays of the claimant in the performance of contracts in the construction of a pumping plant to be operated by electricity for dry docks at the navy yard in New York and for extra and additional work.

The original contract was entered into through the Chief of the Bureau of Yards and Docks September 15, 1900, whereby the claimant agreed, for the consideration of $79,435, to furnish all necessary labor and materials and to complete within seven calendar months, in accordance with the plans and specifications made part of the contract, a pumping plant for Dry Dock No. 3 at the New York Navy Yard.

In accordance with the contract the claimant began work and after it had excavated for the pump pit, driven some piles in and around same, made drawings for the pumps and motors necessary to install the plant, the Navy Department concluded to connect Dry Dock No. 2 with Dry Dock No. 3 and to build a single pumping plant for both docks to be operated wholly by electricity. To this end a supplemental contract (A) was entered into, whereby the claimant, for the additional consideration of $42,885, agreed to furnish all necessary labor and materials to carry out the changes so agreed upon and to complete the same on or before October 15, 1901, to which date the original contract was extended.

After the date agreed upon for the completion of the work under the' original and supplemental contracts and while the work thereunder was progressing, the claimant, on February 16, 1903. entered into a second supplemental contract (B) with the United States, whereby the claimant agreed to construct three hatches in the roof of the pump well for the additional sum of $959.80, nothing being said therein as to the tim,e of the completion of the work or as to delays under prior contracts.

During the progress of the work a controversy arose between the claimant and the civil engineer in charge as to the method of designing and constructing the floor of the [500]*500pump well and also as to tbe requirement of the specifications respecting the construction of the suction chamber, which disagreement resulted in the appointment of a board by the Chief of the Bureau of Yards and Docks to consider changes in the bottom of the pump well and the compensation to Be paid therefor. The board reported that the work had been done by the claimant in accordance with the specifications and that it was chargeable with no improper work or procedure. The board estimated the increased cost of the new work at $6,708.05, for the doing of which a third supplemental contract (C) was entered into March 7, 1903, in which no mention was made as to the time of completion of either the original or supplemental contracts nor as to the subject of delays prior thereto.

By reason of the changes so made by the Government and the use of the dock for docking vessels, as set forth in Finding YII, the claimant was delayed in getting the work ready for the installation of the machinery until May 1, 1903, during which time the claimant incurred extra expenses of superintendence and maintenance of the plant amounting to $3,000, for which amount, being due to the delays of the Government, the claimant is entitled to recover.

During the period from May 1, 1903, to April 21, 1904, when the plant was completed ready for tests, the claimant unreasonably delayed the work, as set forth in Finding VIII, for about 210 days, by reason of which the Government was damaged, if measured by the liquida ted-damage clause of the contract, $5,250; otherwise there is no evidence as to the actual damage sustained; and if only actual damages are recoverable then the claimant is entitled to recover the whole amount of the deduction, $6,000; otherwise $750, the difference between said deduction and the amount found by the court, as set forth in Finding VIII.

And in respect of this branch of the case the claimant’s contention is that, as the work was not completed within the extended contract time by reason of the delays of the Government, and no other time was fixed in the second or subsequent supplemental contracts, the time limit was thereby waived, and the claimant was therefore entitled to. a reasonable time within which to do the work; and if not [501]*501done within a reasonable time and the Government was thereby damaged, then actual damages only can be recovered, to be shown by evidence independent of the provision of the liquidated-damage clause of the contract. In support of this contention the claimant cites the cases of District of Columbia v. The Camden Iron Works (181 U. S., 453), King v. United States (37 C. Cls., 428), United States ex rel. The International Contracting Co. v. Lamont (155 U. S., 303), and United States v. Gleason (175 U. S., 588, 609).

That the claimant was, for the reasons stated, entitled to a reasonable time within which to do the work is in effect conceded by the defendants, but they insist that the liquidated-damage clause of the contract was continued in force and furnishes the measure of damages without other proof.

The provision of the contract, being paragraph 12 of the specifications relied upon, provides:

“Damage for delay. — In case the work is not completed within the time specified in the contract, or the time allowed by the Chief of the Bureau of Yards and Docks under paragraph 11 of this specification, it is distinctly understood and agreed that reductions at the rate of $25 per day shall be made from the contract price for each and every calendar day after and exclusive of the date within which completion was required up to and including the date of completion and acceptance of the work, said sum being specifically agreed upon as the measure of damage to the United States by reason of delay in the completion of the work; and the contractor shall agree and consent that the contract price, reduced by the aggregate_ of damages so deducted, shall be accepted in full satisfaction for all work done under the contract.”

It is true that as a general rule the courts — not regarding forfeitures with favor — incline to construe the damage clause of contracts, where not clearly expressed otherwise, as a penalty where the same can be accurately ascertained.

The sum so specifically agreed upon in the paragraph of the specifications quoted as the measure of damages, it is therein provided, shall be deducted from the contract price, and the amount so reduced “ shall be accepted in full satisfaction for all work done under the contract.” While neither the word penalty ” nor liquidated ” damages is mentioned [502]*502in the contract, the intention of the parties, from a fair construction of the language, is clear. (Globe Refining Company v. Landa Cotton Oil Company, 190 U. S., 540; Sun Printing and Publishing Co. v. Moore, 183 U. S., 642.)

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Sternberg v. United States
87 Ct. Cl. 332 (Court of Claims, 1938)
Christensen Construction Co. v. United States
72 Ct. Cl. 500 (Court of Claims, 1931)

Cite This Page — Counsel Stack

Bluebook (online)
47 Ct. Cl. 489, 1912 U.S. Ct. Cl. LEXIS 19, 1911 WL 1375, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-engineering-contracting-co-v-united-states-cc-1912.