Schmoll v. United States

91 Ct. Cl. 1, 1940 U.S. Ct. Cl. LEXIS 122, 1940 WL 4133
CourtUnited States Court of Claims
DecidedJanuary 8, 1940
DocketNo. 42519-B
StatusPublished
Cited by11 cases

This text of 91 Ct. Cl. 1 (Schmoll v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Schmoll v. United States, 91 Ct. Cl. 1, 1940 U.S. Ct. Cl. LEXIS 122, 1940 WL 4133 (cc 1940).

Opinion

GheeN, Judge,

on January 8,1940, delivered the opinion of the court:

This is a suit on a contract made with the defendant by Murch Brothers Construction Company, Inc., and performed by that company and its subcontractors. It was originally brought by the contractor. Thereafter, for reasons not necessary to be set out here, by leave of court the present plaintiff was substituted as trustee and has succeeded to all the rights of the contracting company.

The plaintiff seeks to recover the sum of $4,632.51, representing liquidated damages assessed and deducted by the contracting officer at the time of final settlement, and also the additional sum of $30,418.15 on account of damages and extra costs alleged to have been incurred in the performance of the contract, making a total of $35,110.12, for which he asks judgment.

On June 13,1929, the Murch Brothers Construction Company, Inc., made a contract with the United States Veterans’ Bureau for the construction of nine separate buildings with connecting corridors, together with certain roads"” walks, and grading, at the United States Veterans’ Hospital at Somerset Hills, New Jersey.

The contract required the work to commence within 10 calendar days after receipt of notice to proceed and to be completed within 350 calendar days thereafter. It further provided for the payment of liquidated damages of $200 a day for each calendar day beyond the date stated in the hid which the contractor might require to complete the contract. The terms [24]*24of the contract with respect to this matter are set out in. Finding 7.

The contract was awarded to Murch Brothers Construction Company, and notice to proceed with all the work except building No. 10 was received on July 12,1929. Notice to proceed with “attendants’ quarters No. 10” was received on September 26,1929, which was 76 days subsequent to the first notice to proceed with all the other buildings. Nothing was stated in this last notice as to when the building should be completed. The delay in giving this notice was due to the failure of the defendant to obtain good title to the site on which building No. 10 was required to be constructed.

All the contract work, except buildings Nos. 1, 5, and 10, was completed and accepted on September 24, 1930. Buildings Nos. 1, 6, and 10 were completed and accepted on September 27,1930.

The matters at issue in the case will be taken up in the order that they are submitted in argument.

As above stated, in making the final payment to the plaintiff, defendant deducted $4,632.57 as liquidated damages for failure to complete the work within the time required by the contract. Plaintiff insists that no liquidated damages could properly be assessed and seeks to recover the amount so deducted.

The provision of the contract with reference to liquidated damages is set out in Finding 7. It provided for the payment of $200 for each day beyond the date stated in the bid which the contractor might require to complete the contract. The recoi’d does not show the date stated in the contractor’s bid, but counsel on both sides assume that the contract in this respect followed the terms of the bid and, as stated above, required work thereunder to commence within 10 calendar' days after receipt of notice to proceed and to be completed within 350 calendar days thereafter. The contractor did not complete the work within 350 days from the time it was given a notice to proceed, but plaintiff contends that the provisions of the contract with reference to completion of the work and liquidated damages were entirely .abrogated through the acts of the defendant.

[25]*25It appears from the evidence that by reason of neglect on the part of the defendant, to obtain title to the premises on which building No. 10 was to be erected, construction work on that building had to be postponed. Consequently defendant did not serve a notice to proceed, as was clearly contemplated by the contract, but gave notice to proceed with the work except on building No. 10, and 76 days later gave notice to proceed with the work on the building last named. Later the defendant found it necessary to extend the time on all the buildings 61 days, which had the effect of granting a further extension on building No. 10 for that time beyond the 76 days already granted.

It was the duty of the defendant to acquire title, or at least control of the premises upon which the buildings were to be erected, prior to giving notice to the contractor to proceed with the work. The execution of the contract implied an agreement to that effect and the failure of the defendant in this respect operated as a waiver of the time limit of the contract. Moreover, the contract implied that one notice to proceed with the work and only one would be given, and when by reason of its own fault and negligence defendant attempted to segregate the work to be done under the contract and serve notices differing as to the date of completion it again violated the contract. It is argued on behalf of defendant that the contract provided for a suspension of the work under certain circumstances and that there was authority for its act in this provision. There is no foundation for this argument either in the dictionary definitions or in common knowledge as to how these words would be understood and this defense is unavailing. To “suspend” work means to stop work already begun. It cannot apply to a direction to postpone the commencement of work. Moreover, we are not here discussing whether defendant had the right to postpone the work, which in itself and alone is immaterial as the contractor went on. with the work in accordance with the directions of the defendant. The question here is whether defendant could postpone the commencement of work so as to make impracticable the performance of the contract within the time specified therein and then insist [26]*26on liquidated damages because the contract had not been performed as originally stipulated.

It is also argued on behalf of defendant that the contract is divisible and, admitting that its claim for liquidated damages could not apply to building No. 10, it is said there was still a default on the part of the contractor in not completing the other buildings within the extended time granted and that liquidated damages should follow even though the contractor made no new agreement with reference to the completion of the other buildings. In support of this contention, counsel quote a provision of the contract with reference to an apportionment of liquidated damages when part of the buildings are completed within the time specified by the contract and part are not. But this has application only where a specified time for completion of the buildings still remains a part of the contract, or, in other words, this provision can not apply unless it is first found and held that the defendant is entitled to liquidated damages.

The argument of counsel for the Government is in effect that regardless of the contract the defendant could fix any date which seemed necessary or desirable for the commencement of the work as to one or more buildings, to be completed in 350 days thereafter, and recover liquidated damages if the other buildings were not completed within 350 days from the time when notice to proceed was given with reference thereto. We do not think this can be the law. Certainly it cannot where the fault or negligence of the party claiming liquidated damages is the cause of the delay and the violation of the contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

George Sollitt Construction Co. v. United States
64 Fed. Cl. 229 (Federal Claims, 2005)
R.P. Wallace, Inc. v. United States
63 Fed. Cl. 402 (Federal Claims, 2004)
PCL Construction Services, Inc. v. United States
53 Fed. Cl. 479 (Federal Claims, 2002)
Fortec Constructors v. United States
32 Cont. Cas. Fed. 73,702 (Court of Claims, 1985)
Prestex, Inc. v. United States
31 Cont. Cas. Fed. 71,508 (Court of Claims, 1983)
Pathman Construction Co. v. Hi-Way Electric Co.
382 N.E.2d 453 (Appellate Court of Illinois, 1978)
Acme Process Equipment Co. v. United States
171 Ct. Cl. 324 (Court of Claims, 1965)
Acme Process Equipment Co. v. United States
347 F.2d 509 (First Circuit, 1965)
Wunderlich v. United States
117 Ct. Cl. 92 (Court of Claims, 1950)
Pfotzer v. United States
77 F. Supp. 390 (Court of Claims, 1948)

Cite This Page — Counsel Stack

Bluebook (online)
91 Ct. Cl. 1, 1940 U.S. Ct. Cl. LEXIS 122, 1940 WL 4133, Counsel Stack Legal Research, https://law.counselstack.com/opinion/schmoll-v-united-states-cc-1940.