Camden Iron Works v. United States

51 Ct. Cl. 9, 1915 U.S. Ct. Cl. LEXIS 11, 1915 WL 1117
United States Court of Claims·Decided December 6, 1915·No. No. 157, Departmental·Published·Cited by 4 cases

Opinion

Downey, Judge,

reviewing the facts found to be established, delivered the opinion of the court:

There are three amounts which it is contended the claimant is entitled to recover, and consideration of the one which it seems to us presents the real subject of controversy may best receive our attention by first disposing of the other two. They are stated by counsel as follows:

1. Admitted balance------------------------------------$3, 711. 86
2. Erroneous deduction_________________________________ 5, 500.00
3. Cost of making changes____________________________ 4, 375. 74

Item 1 is a retained percentage of 25 per cent, which is admittedly due, but has not been paid because of the prescribed condition attached to its payment that the claimant should execute a release of all debts, claims, or demands on account of the contract.

Item 3 is a claim for cost of making changes on the theory that the contract conditions of the test were not complied with, and it was therefore never properly ascertained that the pumps as originally furnished did not corfiply with the requirements, as to which it is sufficient to say that under the conditions of the tests actually made the claimant’s representative conceded that they did not meet the contract requirements, and independent of such concession the court can not conclude otherwise than that as a matter of fact they did not meet such requirements.

The remaining item, 2, is the amount of deduction under the liquidated damage clause for the period from May 4, 1907, to March 31, 1908, inclusive, 278 days at $20 per day, alleged to be erroneous.

[13] It is contended by claimant that the clause in this contract providing for liquidated damages is not an enforceable provision as such, because the contract is for 10 separate units and the damage for nondelivery of one is the same as for nondelivery of all; but there are other matters for consideration which may render the determination of that question unnecessary.

The contract as written was for delivery f. o. b. factory. The final date for its performance was April 3, 1907, extended to May 3, 1907. The test was a factory test which was to be made within the contract period, and the only conclusion to be drawn from the whole contract is that when the pumps had been satisfactorily tested at the factory under the supervision of the Government’s representative and found to meet the requirements and had been delivered on the cars they were there delivered to the Government as its property and as pumps accepted under the contract. The various paragraphs of the specifications sustaining this view need not be referred to in detail.

The letter of August 25,1906, attached to the contract, was written after the bid was made by the claimant, but before the date of the contract. It was in the alternative as to the place of test, prescribing certain conditions if the test was to be made at Garden City, but did not then change the contract in this respect. Indeed, there seems to have been no final conclusion that the contract was to be modified as to place of test until December 6, 1906. It appears from evidence, but not deemed material to the findings, that during this period the claimant was investigating as to whether the prescribed conditions for the test might not be found at the works of the electric company at Schenectady, where the pump motors were to be made.

From correspondence referred to in Finding IY, it appears quite conclusively that it was thereby agreed that Garden City was substituted as the place of delivery and of “ the final acceptance test.”

The conditions of the letter of August 25, if the test should be made at Garden City, then became operative, and in lieu of the original contract it was agreed (1) that the test should be made at ©arden City instead of at the fac[14] tory; (2) that it should be made within 60 days after delivery at Garden City; and (3) that payment should be deferred until acceptance after such test.

It follows from the facts stated that there was a material change in the contract conditions. As originally written, the contractor was required to complete the machinery and test it at the factory, and deliver it to the United States f. o. b. cars at the factory by a date certain. The period required for testing necessarily preceded the prescribed date of delivery, and was included in the contract period. The court will know without proof upon the question that Garden City is far removed from the claimant’s plant at Camden, and that some considerable period of time must necessarily be required to transport machinery from Camden to Garden City. What that period of time is the court is not informed by evidence and can not judicially know. It is a matter of common knowledge that the time occupied in the transportation of freight between two such remote points is uncertain.

It is beyond the pale of reason to assume that under the modified contract the claimant was required to complete the machinery at such time in advance of the date limited for delivery at its factory that it might be on that date delivered to the Government at Garden City. And if by the terms of the modified contract the claimant was required to deliver the machinery to the Government at Garden City at some date subsequent to that prescribed for delivery on the cars at its plant under the original contract, we are not informed by any contract stipulation between the parties as to the date when it was required so to deliver. For some purposes under such conditions it might readily be said that delivery was required to be made within a reasonable time, but “ reasonable time ” is a term of such flexibility that it can seldom, if ever, furnish a satisfactory basis for the enforcement of a contract for liquidated damages.

Free access — add to your briefcase to read the full text and ask questions with AI

Camden Iron Works v. United States, 51 Ct. Cl. 9, 1915 U.S. Ct. Cl. LEXIS 11, 1915 WL 1117 (cc 1915).

51 Ct. Cl. 9 (Camden Iron Works v. United States) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Levering & Garrigues Co. v. United States
73 Ct. Cl. 566 (Court of Claims, 1932)
Greeley Iron Works v. United States
66 Ct. Cl. 328 (Court of Claims, 1928)
Austin Co. v. United States
58 Ct. Cl. 98 (Court of Claims, 1923)