Austin Co. v. United States

58 Ct. Cl. 98, 1923 U.S. Ct. Cl. LEXIS 355, 1923 WL 2132
CourtUnited States Court of Claims
DecidedMarch 12, 1923
DocketNo. 47-A
StatusPublished
Cited by5 cases

This text of 58 Ct. Cl. 98 (Austin Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Austin Co. v. United States, 58 Ct. Cl. 98, 1923 U.S. Ct. Cl. LEXIS 355, 1923 WL 2132 (cc 1923).

Opinion

Camebell, Ohief Justice,

delivered the opinion of the court:

On or about December 13, 1917, the Austin Co. entered into a contract (No. 2713) with the defendant, represented by the Bureau of Yards and Docks, for the construction and completion of 22 powder dry houses, in accordance with certain specifications, the work to be done at the defendant’s naval proving ground, Indianhead, Md. The work was to be done under what is called a “ cost-plus ” contract. It involved an estimated expenditure of approximately $366,-000. The defendant had let contracts for other work at Indianhead to other contractors and found it necessary to annul some of these and relet the work to plaintiff under the oost-plus plan.. Still other work was provided for under plaintiff’s contract, the general character of which is indicated by what was called change orders ” D, E, F, G, I, K, and L, copies of which are attached to the petition, all [133]*133referring to additional work under the terms of contract No. 2713. Change orders A, B, and C refer to work begun by other contractors and relet to plaintiff, as above stated', and these different change orders contemplated 15 or more distinct structures — storehouses, powder dry houses, office buildings, solvent recovery buildings, gun bases, and others.

In addition to the contract and change orders mentioned, the plaintiff and defendant entered into seven or more other contracts for the construction of buildings and works at Indianhead upon the cost-plus plan, viz: No. 2602, for two blending towers; No. 2715, for extension of power house; No. 2747, for two magazine buildings; No. 2748, for five sets of double quarters; No. 2749, for pulping and poaching house; No. 2873, for cottages, garage, and quarters; and No. 2912, for construction camp. These contracts were made between December 24, 1917, and April 18, 1918. The expenditures involved under plaintiff’s first contract grew under the additional contracts and change orders from the amount above stated to about two and a quarter millions of dollars. A general provision of the contracts and change orders was that the contractor’s compensation would be a sum equal to 10 per cent of the cost of the work performed directly and involving no subcontracts for labor at the site, and 5 per cent where the work was done indirectly and by subcontractors for labor at the site.

After the work was completed or suspended, as parts of it were, differences arose between the plaintiff and the Navy Department involving the amounts plaintiff was entitled to receive as compensation and amounts claimed by the Navy Department as proper deductions from sums it conceded would otherwise be payable to plaintiff. These questions are hereinafter stated under the several items of claim.

The plaintiff was an experienced contractor, had an excellent organization, and had undertaken many and large contracts for construction. It was strong financially.

The Naval Proving Ground at Indianhead was an isolated place on the Potomac River, remote from railroad connections, and reached by water transportation from Washington, about 45 miles, and by wagon road from the same place, [134]*134about 20 miles. Neither the necessary labor nor materials for the work were to be had at Indianhead. Labor had to bo sought at other, and sometimes remote, places, and materials had to be purchased elsewhere and transported, principally through the navy yard at Washington. An added obstacle to transportation of materials, and at times to the prosecution of the work itself, was an abnormal and almost unprecedented spell of cold weather in the winter of 1917-18.

The large number of contracts calling for different “ jobs,” each of which is treated separately in the requests for findings, have extended the court’s findings of facts to an unusual length, but it is believed that the findings as they appear make it unnecessary to discuss at length the facts. We shall therefore state our conclusions upon the several items made the bases of contention by the parties.

Item 1 involves a claim by plaintiff for reimbursement of its expenses in securing labor, and in connection therewith the maintaining of an office in Washington for the purchase of materials and the expedition of their delivery. The amount involved, including the percentage to plaintiff, is not controverted. The Government admits that the maintenance and expense of the office to expedite labor, purchase material and expediting delivery thereof, was a necessity under these contracts. Without any such concession, however, we think the facts demonstrate the necessity. It denies, however, that the expense of the maintenance should be borne by the defendant, and argues that whatever authority ■ the plaintiff had to. operate said office or incur this expense was for a temporary expedient. The facts show (Finding II) that at the time of beginning the work the plaintiff was authorized to incur the expense stated, and that arrangements were accordingly made “ with the approval of the officer in charge” for the performance of the service. The labor agent had to report directly to the officer in charge, who directed in one or more instances his movements. The officer fixed the number of men to be used in this work, and from time to time their wages. It also appears that in March of 1918 there was paid to plaintiff, on approval of the officer in charge, a considerable sum for the expense to March 14 of the office and service in question. In view of these facts, [135]*135and the conduct of the parties, it can not be reasonably maintained that the defendant should not reimburse plaintiff for the expense incurred and pay the agreed percentage. The payment made for a portion of the time when the same kinds of expense were involved, and there was a full knowledge of the facts, furnishes a practical interpretation by the parties of the meaning of their contracts in this regard, which is entitled to much weight, especially when such payments were made before the matter became a subject of controversy. See Lowry v. Hawaii, 206 U. S. 206, 222. In view of the facts and circumstances of the case, we think that the defendant’s suggestion that the bureau only approved the expense in the event the labor was solely intended for In-dianhead, and therefore that plaintiff can not recover this item, is without merit. It can at least be said, however, that the suggestion is an admission that there was some authority from the bureau itself for the expense in question.

Item 2 (Finding III) is a claim for reimbursement and commissions on account of the construction and maintenance of the commissary. The stipulation of parties that, among other things, it was necessary, on behalf of the United States, to establish and conduct facilities for housing and feeding employees engaged in the work at Indianhead, sufficiently shows the importance of this item of charge, and we think should fix the defendant’s liability. In addition, however, it appears from the findings that the defendant’s agents had entire control of the conduct of the commissary and fixed its charges. Over the objection, or at least against the advice, of the plaintiff’s experienced agent the charges were for a period reduced and the reduction added to plaintiff’s loss. The expenses of this operation were a part of the cost of the work, and, according to the stipulation, were a necessary part of it. And if not, why was plaintiff paid for part of the expenditure ? The plaintiff was not conducting an independent boarding house. See Brogan v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Waxman v. United States
112 F. Supp. 570 (Court of Claims, 1953)
Twin City Forge & Foundry Co. v. United States
60 Ct. Cl. 673 (Court of Claims, 1925)
Austin Co. v. United States
59 Ct. Cl. 554 (Court of Claims, 1924)
James Stewart & Co. v. United States
59 Ct. Cl. 295 (Court of Claims, 1924)

Cite This Page — Counsel Stack

Bluebook (online)
58 Ct. Cl. 98, 1923 U.S. Ct. Cl. LEXIS 355, 1923 WL 2132, Counsel Stack Legal Research, https://law.counselstack.com/opinion/austin-co-v-united-states-cc-1923.