System Fuels, Inc. v. United States

78 Fed. Cl. 769, 2007 U.S. Claims LEXIS 325
CourtUnited States Court of Federal Claims
DecidedOctober 11, 2007
DocketNo. 03-2624C
StatusPublished
Cited by21 cases

This text of 78 Fed. Cl. 769 (System Fuels, Inc. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
System Fuels, Inc. v. United States, 78 Fed. Cl. 769, 2007 U.S. Claims LEXIS 325 (uscfc 2007).

Opinion

MEMORANDUM OPINION AND ORDER

BRADEN, Judge.

On July 29, 2005, the United States Court of Federal Claims held that on January 31, 1998, the Department of Energy (“the Government”) was liable for a partial breach of a June 30, 1983 Standard Contract (“Standard Contract”) with System Fuels, Inc. (“SFI”). See System Fuels, Inc. v. United States, 66 Fed.Cl. 722, 735 (Fed.Cl.2005) (“System Fuels I”). On September 9, 2005, the United States Court of Appeals for the Federal Circuit ruled, in a similar case involving the Government’s partial breach of the Standard Contract, that when “[the utility’s] claim is premised upon the government’s partial breach, its damages [are] limited to those costs incuiTed prior to the date of its suit.” Ind. Mich. Power Co. v. United States, 422 F.3d 1369, 1376-77 (Fed.Cir.2005) (“Indiana Michigan IP’) (“If the breach is partial only, the injured party may recover damages for nonperformance only to the time of trial and may not recover damages for anticipated future nonperformance.” (emphasis, quotations, and citations omitted)). In this case, Plaintiffs have asserted that the January 31, 1998 partial breach of the Standard Contract caused Plaintiffs to incur $12,178,000 of costs during the period January 15, 1998 through August 31, 2005, to plan, design, and construct a dry fuel storage project at the Grand Gulf Nuclear Station, located near Vicksburg, Mississippi (“Grand Gulf’).1

After weighing the evidence, the court has determined that Plaintiffs have established that a substantial portion of the costs Plaintiff incurred should be included in an award of damages.

To facilitate a review of this Memorandum Opinion and Order, the court provides the following outline:

I. RELEVANT FACTS.......................................................773

A. Congress Required The Department Of Energy To Provide For The Permanent Disposal Of Spent Nuclear Fuel And High Level Radioactive Waste.........................................................773

B. The Department Of Energy Established Procedures To Dispose and

Store Spent Nuclear Fuel and High Level Radioactive Waste............775

C. On June 30, 1983, Three Corporate Entities Entered Into A Standard Contract With The Department Of Energy To Dispose And Store Spent Nuclear Fuel And/Or High-Level Radioactive Waste Generated At The Grand Gulf Nuclear Station.................................776

1. Three Corporate Entities That Own The Grand Gulf Nuclear

Station..........................................................776

a. System Fuels, Inc..............................................776

b. Middle South Energy, Inc.......................................776

c. South Mississippi Electric Power Association.....................776

2. The Utility Parties To The Standard Contract........................777

D. On June 30, 1985, The Department Of Energy Published A Plan To

Implement The Civilian Radioactive Waste Management Program......778

E. On January 31, 1998, The Department of Energy Partially Breached

The Standard Contract...............................................779

F. Plaintiffs’ Decision To Construct A Dry Fuel Storage Project At The

Grand Gulf Nuclear Station To Mitigate The Government’s Partial

Breach Of The Standard Contract.....................................779

1. The Refueling Process At The Grand Gulf Nuclear Station............779

[772]*7722. Planning Initiated By Entergy Corporation That Led To Approval Of The Design and Construction Of A Dry Fuel Storage Project At The Grand Gulf Nuclear Station........................... ,780

3. In 2005, Grand Gulf Expanded Spent Nuclear Fuel Storage By Cell Recovery............................................... .782

G. The Construction Of The Dry Fuel Storage Project At Grand Gulf. .783

1. Capital Work Orders Were Established To Account For The Costs Of The Grand Gulf Dry Fuel Storage Project.................. .783

2. Description Of Plaintiffs’ Capital Work Orders.................. .783

a. Capital Work Order N31937: Spent Fuel Studies And Reports. .783

b. Capital Work Order N32172: ISFSI Design And Construction. .784

c. Capital Work Order N32271: Cask Fabrication Facility...... .784

d. Capital Work Order N32302: Dry Fuel Equipment Storage Building................................................ .784

e. Capital Work Order N32350: ISFSI Electrical And Security Systems................................................ ,784

f. Capital Work Order N32136: Auxiliary Building Door Modification............................................. .784

3. Cost Of Borrowed Funds....................................... .785

II. PROCEDURAL HISTORY............................................ .785

III. DISCUSSION......................................................... .787

A. Jurisdiction...................................................... .787

B. Standing......................................................... .787

C. Standard of Review............................................... .788

1. The Parties’ Arguments........................................ 788

2. The Court’s Resolution......................................... 789

D. The Court’s Determination Of Causation In This Case................ 790

1. Plaintiffs Established That Dry Fuel Storage Was “Reasonably Foreseeable” To The Department Of Energy On June 30, 1983. 790

2. Plaintiffs Established That The Department of Energy’s Partial Breach Of The Standard Contract Was A Direct And “Substantial Cause” Of The Costs Incurred................... 791

3. Certain Of The Costs Plaintiffs Incurred Were Ascertained With Reasonable Certainty.................................... 795

E. The Court’s Determination Regarding The Reasonableness Of The Government’s Requested Offsets.................................. 796

1. Cask Loading Costs............................................ 797

2. Internal Labor Costs........................................... 797

3. Loader Costs................................................... 798

a. Payroll Loader............................................. 799

b. Materials Loader.......................................... 799

c. Capital Expense Loader..................................... 800

4. Auxiliary Building Modifications................................ 800

a. Railroad Bay Floor......................................... 801

b. 208-Foot Elevation Civil Design and Implementation.......... 802

c. Electrical Service........................................... 802

d. Relocating The Horizontal Fuel Transfer System Insert Storage Rack............................................

Free access — add to your briefcase to read the full text and ask questions with AI

Related

System Fuels, Inc. v. United States
120 Fed. Cl. 635 (Federal Claims, 2015)
Energy Northwest v. United States
115 Fed. Cl. 69 (Federal Claims, 2014)
Portland General Electric Co. v. United States
107 Fed. Cl. 633 (Federal Claims, 2012)
Kansas Gas and Electric Co. v. United States
685 F.3d 1361 (Federal Circuit, 2012)
System Fuels, Inc. v. United States
666 F.3d 1306 (Federal Circuit, 2012)
Niagara Mohawk Power Corp. v. United States
98 Fed. Cl. 313 (Federal Claims, 2011)
Kansas Gas & Electric Co. v. United States
95 Fed. Cl. 257 (Federal Claims, 2010)
Entergy Nuclear Vermont Yankee, LLC v. United States
95 Fed. Cl. 160 (Federal Claims, 2010)
Yankee Atomic Power Co. v. United States
94 Fed. Cl. 678 (Federal Claims, 2010)
Nwogu v. United States
94 Fed. Cl. 637 (Federal Claims, 2010)
Southern California Edison Co. v. United States
93 Fed. Cl. 337 (Federal Claims, 2010)
Wisconsin Electric Power Co. v. United States
90 Fed. Cl. 714 (Federal Claims, 2009)
Dominion Resources, Inc. v. United States
84 Fed. Cl. 259 (Federal Claims, 2008)
Carolina Power & Light Co. v. United States
82 Fed. Cl. 23 (Federal Claims, 2008)
Schooner Harbor Ventures, Inc. v. United States
81 Fed. Cl. 404 (Federal Claims, 2008)
Boston Edison Co. v. United States
80 Fed. Cl. 468 (Federal Claims, 2008)

Cite This Page — Counsel Stack

Bluebook (online)
78 Fed. Cl. 769, 2007 U.S. Claims LEXIS 325, Counsel Stack Legal Research, https://law.counselstack.com/opinion/system-fuels-inc-v-united-states-uscfc-2007.